5524 N AUCKLAND AVE 91601
Certificate Information: 5524 N AUCKLAND AVE 91601
- Application / Permit
- 20016-20000-30124
- Plan Check / Job No.
- B20VN15146
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) 18'-0" X 19'-6" STORAGE TO (N) ACCESSORY DWELLING UNIT PER GCS 65852.2(E)(1)(A), (E) 18' X 20'-6" ATTACHED GARAGE TO REMAIN. ALL WORK PER ENGINEERING.
- Permit Issued
- Issued on 6/7/2021
- Issuing Office
- Current Status
- CofO Issued on 6/11/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/19/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 11/24/2020 | GURUNATH NESARAJAH |
| Corrections Issued | 11/28/2020 | GURUNATH NESARAJAH |
| Applicant returned to address corrections | 2/8/2021 | GURUNATH NESARAJAH |
| Plan Check Approved | 4/29/2021 | JENNIFER LEE |
| Refund Closed | 5/26/2021 | TERENCE SHIA |
| Issued | 6/7/2021 | APPLICANT |
| Building Plans Picked Up | 6/7/2021 | APPLICANT |
| Refund in Progress-Status Void | 7/14/2021 | EMILY HU |
| Re-Activate Permit | 7/21/2021 | MARY SUM |
| CofO in Progress | 4/1/2022 | MATT KELLERMAN |
| CofO in Progress | 4/1/2022 | MATT KELLERMAN |
| Permit Finaled | 6/11/2022 | MICHAEL SMITH |
| CofO Issued | 6/11/2022 | MICHAEL SMITH |
| Permit Finaled | 6/11/2022 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 2/11/2021 | GABRIEL ROBLES |
| Roof/Waste drainage to street | Cleared | 2/11/2021 | GABRIEL ROBLES |
| Sewer availability | Cleared | 2/11/2021 | GABRIEL ROBLES |
| Eng Process Fee Ord 176,300 | Cleared | 2/16/2021 | GABRIEL ROBLES |
| Construction near power lines | Cleared | 4/22/2021 | RIDWAN HARDY |
| Construction within easement | Cleared | 4/22/2021 | RIDWAN HARDY |
Contact Information
| Contractor | 4 Elements General Contracting; Lic. No.: 570129-B | 5062 LANKERSHIM BLVD STE 141 NORTH HOLLYWOOD, CA 91601 |
| Engineer | Basso,, Alexandre; Lic. No.: C77670 | 7231 SUMMITROSE ST TUJUNGA, CA 91042 |
Inspector Information
| GAREN HAYRAPETYAN, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
| ROBERTO PALACIOS-LOPEZ, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| SGSOV-Seismic Gas S/O Valve | 5/12/2021 | SGSOV Not Ready | DANIEL DREW |
| Pre-Inspection | 7/12/2021 | Not Ready for Inspection | DANIEL DREW |
| PLUMBING-Rough | 7/15/2021 | Partial Approval | DANIEL DREW |
| Sewer | 7/15/2021 | Approved | DANIEL DREW |
| PLUMBING-Rough | 7/28/2021 | Not Ready for Inspection | DANIEL DREW |
| Pre-Inspection | 8/9/2021 | Approved | DANIEL DREW |
| Wood Frame | 8/19/2021 | Not Ready for Inspection | DANIEL DREW |
| Wood Frame | 8/23/2021 | Not Ready for Inspection | DANIEL DREW |
| Pre-Inspection | 8/24/2021 | Approved | DANIEL DREW |
| BUILDING-Rough-Frame | 9/3/2021 | Approved | DANIEL DREW |
| ELECTRICAL-Rough | 9/24/2021 | Corrections Issued | ALIZAH MAYAGOITIA |
| PLUMBING-Rough | 9/24/2021 | Corrections Issued | ALIZAH MAYAGOITIA |
| ELECTRICAL-Rough | 9/28/2021 | Conditional Approval | ALIZAH MAYAGOITIA |
| PLUMBING-Rough | 9/28/2021 | Approved | ALIZAH MAYAGOITIA |
| HVAC-Rough | 9/29/2021 | Not Ready for Inspection | DANIEL DREW |
| ELECTRICAL-Rough | 9/30/2021 | Approved | ALIZAH MAYAGOITIA |
| BUILDING-Rough-Frame | 12/22/2021 | Approved | CHRISTOPHE COCHRAN |
| Drywall Nailing | 12/22/2021 | Approved | CHRISTOPHE COCHRAN |
| Final | 12/22/2021 | Corrections Issued | CHRISTOPHE COCHRAN |
| Green Building Final | 12/22/2021 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| Green Building Rough | 12/22/2021 | Approved | CHRISTOPHE COCHRAN |
| PLUMBING-Final | 12/22/2021 | Approved | CHRISTOPHE COCHRAN |
| SGSOV-Seismic Gas S/O Valve | 12/22/2021 | SGSOV Not Ready | CHRISTOPHE COCHRAN |
| Smoke Detectors | 12/22/2021 | Approved | CHRISTOPHE COCHRAN |
| Service/Power Release | 2/3/2022 | Corrections Issued | MICHAEL TEMPLE |
| ELECTRICAL-Rough | 3/10/2022 | Partial Approval | MATT KELLERMAN |
| HVAC-Rough | 3/10/2022 | Not Ready for Inspection | MATT KELLERMAN |
| Service/Power Release | 3/10/2022 | Not Ready for Inspection | MATT KELLERMAN |
| ELECTRICAL-Final | 3/17/2022 | Corrections Issued | MISAEL ESPARZA |
| Final | 3/17/2022 | Corrections Issued | MISAEL ESPARZA |
| HVAC-Final | 3/17/2022 | Corrections Issued | MISAEL ESPARZA |
| Final | 3/31/2022 | OK to Issue CofO | MATT KELLERMAN |
| Green Building Final | 3/31/2022 | Approved | MATT KELLERMAN |
| SGSOV-Seismic Gas S/O Valve | 3/31/2022 | SGSOV Approved | MATT KELLERMAN |