10149 N LANGDON AVE 91345
Certificate Information: 10149 N LANGDON AVE 91345
- Application / Permit
- 20016-20000-30040
- Plan Check / Job No.
- B20VN15057
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- CONVERT THE (E) 20' X 32' GARAGE INTO A (N) ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(A). ALL WORK PER WFPP.
- Permit Issued
- Issued on 2/24/2022
- Issuing Office
- Current Status
- CofO Issued on 3/7/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/25/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 12/3/2020 | OMAR GARNICA |
| Corrections Issued | 12/3/2020 | OMAR GARNICA |
| Applicant returned to address corrections | 11/2/2021 | OMAR GARNICA |
| Plan Check Approved | 1/24/2022 | OMAR GARNICA |
| Building Plans Picked Up | 2/7/2022 | APPLICANT |
| Issued | 2/24/2022 | APPLICANT |
| CofO in Progress | 3/2/2023 | JENNIFER RABUCHIN |
| CofO Issued | 3/7/2023 | MICHAEL SMITH |
| Permit Finaled | 3/7/2023 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 3/4/2021 | JOHN TRIANTAFYLLOS |
| Eng Process Fee Ord 176,300 | Cleared | 3/4/2021 | JOHN TRIANTAFYLLOS |
| Sewer availability | Cleared | 3/4/2021 | JOHN TRIANTAFYLLOS |
| Construction near power lines | Cleared | 10/19/2021 | WALTER RAMIREZ |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JOHN COLEMAN, (818) 374-1179 | Office Hours: 7:00-8:00 AM MON-FRI |
| JENNIFER RABUCHIN, (818) 374-1179 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 3/7/2022 | Corrections Issued | JENNIFER RABUCHIN |
| Sewer | 3/7/2022 | Partial Approval | JENNIFER RABUCHIN |
| PLUMBING-Rough | 3/8/2022 | Not Ready for Inspection | JENNIFER RABUCHIN |
| Gas Test | 3/9/2022 | No Access for Inspection | RICHARD DOCKUS |
| PLUMBING-Rough | 3/17/2022 | Partial Approval | JENNIFER RABUCHIN |
| Sewer | 3/17/2022 | Approved | JENNIFER RABUCHIN |
| Gas Test | 3/18/2022 | Not Ready for Inspection | JENNIFER RABUCHIN |
| Underground Mechanical | 3/18/2022 | Approved | JENNIFER RABUCHIN |
| Footing/Foundation/Slab | 3/22/2022 | Approved | JENNIFER RABUCHIN |
| Gas Test | 3/22/2022 | Partial Approval | JENNIFER RABUCHIN |
| Deputy Drilled-In Anchors | 4/21/2022 | Partial Approval | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 4/25/2022 | Corrections Issued | JENNIFER RABUCHIN |
| Green Building Rough | 4/25/2022 | Not Ready for Inspection | JENNIFER RABUCHIN |
| MERV13>=Rough | 4/25/2022 | Not Ready for Inspection | JENNIFER RABUCHIN |
| Floor/Roof Diaphrgm/Shear Wall | 4/26/2022 | Partial Approval | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 5/2/2022 | Partial Approval | JENNIFER RABUCHIN |
| ELECTRICAL-Rough | 5/2/2022 | Corrections Issued | JENNIFER RABUCHIN |
| Gas Test | 5/2/2022 | Partial Approval | JENNIFER RABUCHIN |
| Green Building Rough | 5/2/2022 | Approved | JENNIFER RABUCHIN |
| Interior/Exterior Lathing | 5/2/2022 | Corrections Issued | JENNIFER RABUCHIN |
| PLUMBING-Rough | 5/2/2022 | Corrections Issued | JENNIFER RABUCHIN |
| ELECTRICAL-Rough | 5/4/2022 | Approved | JENNIFER RABUCHIN |
| Insulation | 5/4/2022 | Approved | JENNIFER RABUCHIN |
| Drywall Nailing | 5/9/2022 | Corrections Issued | DEANDRE HOFFMAN |
| Interior/Exterior Lathing | 5/11/2022 | Partial Approval | DEANDRE HOFFMAN |
| Drywall Nailing | 5/12/2022 | Approved | MICHAEL TEMPLE |
| Interior/Exterior Lathing | 5/12/2022 | Approved | MICHAEL TEMPLE |
| PLUMBING-Rough | 5/12/2022 | Approved | MICHAEL TEMPLE |
| ELECTRICAL-Final | 5/16/2022 | Corrections Issued | JENNIFER RABUCHIN |
| Floor/Roof Diaphrgm/Shear Wall | 5/16/2022 | Partial Inspection | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 6/1/2022 | Approved | JENNIFER RABUCHIN |
| ELECTRICAL-Final | 6/1/2022 | Corrections Issued | JENNIFER RABUCHIN |
| Final | 6/1/2022 | Corrections Issued | JENNIFER RABUCHIN |
| Green Building Final | 6/1/2022 | Approved | JENNIFER RABUCHIN |
| HVAC-Final | 6/1/2022 | Approved | JENNIFER RABUCHIN |
| MERV13>=Final | 6/1/2022 | Approved | JENNIFER RABUCHIN |
| MERV13>=Rough | 6/1/2022 | Approved | JENNIFER RABUCHIN |
| PLUMBING-Final | 6/1/2022 | Corrections Issued | JENNIFER RABUCHIN |
| SGSOV-Seismic Gas S/O Valve | 6/1/2022 | SGSOV Approved | JENNIFER RABUCHIN |
| Smoke Detectors | 6/1/2022 | Approved | JENNIFER RABUCHIN |
| Final | 8/18/2022 | Corrections Issued | JENNIFER RABUCHIN |
| Final | 1/19/2023 | Not Ready for Inspection | JOHN COLEMAN |
| ELECTRICAL-Final | 2/8/2023 | Approved | JENNIFER RABUCHIN |
| Final | 2/8/2023 | OK to Issue CofO | JENNIFER RABUCHIN |
| HVAC-Final | 2/8/2023 | Approved | JENNIFER RABUCHIN |
| PLUMBING-Final | 2/8/2023 | Approved | JENNIFER RABUCHIN |