22044-22046 W GILMORE ST 91303
Certificate Information: 22044-22046 W GILMORE ST 91303
- Application / Permit
- 20016-20000-29658
- Plan Check / Job No.
- B20VN14885
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- CONVERT THE 18' X 20' (E) TWO CAR GARAGE AND 152 SF PORTION OF MAIN DWELLING TO ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(A). REFRAME EX. GARAGE PORTION. ALL WORK PER WFPP.
- Permit Issued
- Issued on 6/25/2021
- Issuing Office
- Valley
- Current Status
- CofO Issued on 9/3/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/16/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 11/24/2020 | JEFFREY TANGONAN |
| Corrections Issued | 11/29/2020 | JEFFREY TANGONAN |
| Applicant returned to address corrections | 3/18/2021 | JEFFREY TANGONAN |
| Plan Check Approved | 5/18/2021 | JEFFREY TANGONAN |
| Building Plans Picked Up | 5/20/2021 | APPLICANT |
| Issued | 6/25/2021 | APPLICANT |
| CofO in Progress | 8/29/2021 | TROY SANDERS |
| Permit Finaled | 9/3/2021 | JOHN JANSON |
| CofO Issued | 9/3/2021 | JOHN JANSON |
| Permit Finaled | 9/3/2021 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 4/19/2021 | GABRIEL ROBLES |
| Sewer availability | Cleared | 4/19/2021 | GABRIEL ROBLES |
| Eng Process Fee Ord 176,300 | Cleared | 4/26/2021 | GABRIEL ROBLES |
Contact Information
| Contractor | Barani Construction Inc; Lic. No.: 1001764-B | 3093 MILESTONE AVE SIMI VALLEY, CA 93065 |
Inspector Information
| GEVORK IPCHYAN, (818) 774-4308 | Office Hours: 7:00-8:00 AM MON-FRI |
| TROY SANDERS, (818) 774-4308 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 6/30/2021 | Approved | TROY SANDERS |
| PLUMBING-Rough | 6/30/2021 | Partial Approval | TROY SANDERS |
| Sewer | 6/30/2021 | Approved | TROY SANDERS |
| BUILDING-Rough-Frame | 7/6/2021 | Partial Approval | TROY SANDERS |
| ELECTRICAL-Rough | 7/6/2021 | Approved | TROY SANDERS |
| Green Building Rough | 7/6/2021 | Not Ready for Inspection | TROY SANDERS |
| PLUMBING-Rough | 7/6/2021 | Approved | TROY SANDERS |
| Wood Frame | 7/6/2021 | Not Ready for Inspection | TROY SANDERS |
| Gas Test | 7/8/2021 | Approved | RYAN SALAZAR |
| Insulation | 7/8/2021 | Corrections Issued | RYAN SALAZAR |
| Interior/Exterior Lathing | 7/8/2021 | Approved | RYAN SALAZAR |
| Drywall Nailing | 7/12/2021 | Not Ready for Inspection | LILIANA PORTILLO |
| Insulation | 7/12/2021 | Corrections Issued | LILIANA PORTILLO |
| Wood Frame | 7/12/2021 | Partial Approval | LILIANA PORTILLO |
| Insulation | 7/14/2021 | Approved | ALIZAH MAYAGOITIA |
| Drywall Nailing | 7/16/2021 | Approved | ALIZAH MAYAGOITIA |
| Interior/Exterior Lathing | 7/20/2021 | Approved | ALIZAH MAYAGOITIA |
| BUILDING-Rough-Frame | 8/19/2021 | Approved | TROY SANDERS |
| Final | 8/19/2021 | Corrections Issued | TROY SANDERS |
| Green Building Final | 8/19/2021 | Corrections Issued | TROY SANDERS |
| Green Building Rough | 8/19/2021 | Approved | TROY SANDERS |
| HVAC-Final | 8/19/2021 | Approved | TROY SANDERS |
| SGSOV-Seismic Gas S/O Valve | 8/19/2021 | SGSOV Gas Company | TROY SANDERS |
| Smoke Detectors | 8/19/2021 | Approved | TROY SANDERS |
| Final | 8/27/2021 | OK to Issue CofO | TROY SANDERS |
| Green Building Final | 8/27/2021 | Approved | TROY SANDERS |