13305 W HERRON ST 91342
Certificate Information: 13305 W HERRON ST 91342
- Application / Permit
- 20016-20000-29616
- Plan Check / Job No.
- B20VN14851
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) DETACHED 24' X 24' GARAGE TO ADU. ALL WORK DONE PER WFPP.
- Permit Issued
- Issued on 1/28/2021
- Issuing Office
- Current Status
- CofO Issued on 3/5/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/20/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 11/24/2020 | GURUNATH NESARAJAH |
| Corrections Issued | 11/28/2020 | GURUNATH NESARAJAH |
| Plan Check Approved | 1/10/2021 | GURUNATH NESARAJAH |
| Issued | 1/28/2021 | APPLICANT |
| CofO in Progress | 2/10/2022 | JOHN HAYES |
| CofO Issued | 3/5/2022 | MICHAEL SMITH |
| Permit Finaled | 3/5/2022 | MICHAEL SMITH |
Permit Application Clearance Information
| ZI | Cleared | 12/14/2020 | MIGUEL GAMBOA |
| Address approval | Cleared | 12/18/2020 | GUILLERMO PETRA |
| Sewer availability | Cleared | 12/18/2020 | GUILLERMO PETRA |
| Eng Process Fee Ord 176,300 | Cleared | 12/21/2020 | GUILLERMO PETRA |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| KEVIN BERBERYAN, (818) 374-9931 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 2/8/2021 | Conditional Approval | MISAEL ESPARZA |
| Deputy Drilled-In Anchors | 2/9/2021 | Conditional Approval | MISAEL ESPARZA |
| Footing/Foundation/Slab | 2/9/2021 | Conditional Approval | MISAEL ESPARZA |
| Deputy Drilled-In Anchors | 2/11/2021 | Conditional Approval | MISAEL ESPARZA |
| Floor/Roof Diaphrgm/Shear Wall | 3/9/2021 | Not Ready for Inspection | MISAEL ESPARZA |
| BUILDING-Rough-Frame | 4/5/2021 | Not Ready for Inspection | MISAEL ESPARZA |
| ELECTRICAL-Rough | 4/5/2021 | Not Ready for Inspection | MISAEL ESPARZA |
| Green Building Rough | 4/5/2021 | Not Ready for Inspection | MISAEL ESPARZA |
| Interior/Exterior Lathing | 4/5/2021 | Not Ready for Inspection | MISAEL ESPARZA |
| PLUMBING-Rough | 4/5/2021 | Corrections Issued | MISAEL ESPARZA |
| Rough-Elec/Plmb/HVAC | 4/5/2021 | Not Ready for Inspection | MISAEL ESPARZA |
| Sewer | 4/5/2021 | Partial Approval | MISAEL ESPARZA |
| Wood Frame | 4/5/2021 | Not Ready for Inspection | MISAEL ESPARZA |
| ELECTRICAL-Rough | 4/13/2021 | Approved | MISAEL ESPARZA |
| Gas Test | 4/13/2021 | Not Ready for Inspection | MISAEL ESPARZA |
| HVAC-Rough | 4/13/2021 | Not Ready for Inspection | MISAEL ESPARZA |
| PLUMBING-Rough | 4/13/2021 | Not Ready for Inspection | MISAEL ESPARZA |
| Sewer | 4/13/2021 | Approved | MISAEL ESPARZA |
| BUILDING-Rough-Frame | 4/19/2021 | Not Ready for Inspection | MISAEL ESPARZA |
| Gas Test | 4/19/2021 | Partial Approval | MISAEL ESPARZA |
| Green Building Rough | 4/19/2021 | Not Ready for Inspection | MISAEL ESPARZA |
| PLUMBING-Rough | 4/26/2021 | Approved | MISAEL ESPARZA |
| Insulation | 5/3/2021 | Partial Approval | MISAEL ESPARZA |
| HVAC-Rough | 5/10/2021 | Approved | MISAEL ESPARZA |
| Insulation | 5/10/2021 | Approved | MISAEL ESPARZA |
| Wood Frame | 5/10/2021 | Approved | MISAEL ESPARZA |
| Drywall Nailing | 5/25/2021 | Approved | MORRIS JACKSON |
| Shower Pan | 6/1/2021 | Approved | MISAEL ESPARZA |
| Interior/Exterior Lathing | 6/8/2021 | Approved | DEANDRE HOFFMAN |
| Footing/Foundation/Slab | 6/21/2021 | Approved | MISAEL ESPARZA |
| BUILDING-Rough-Frame | 9/21/2021 | Not Ready for Inspection | JOHN HAYES |
| Final | 9/21/2021 | Corrections Issued | JOHN HAYES |
| Green Building Final | 9/21/2021 | Not Ready for Inspection | JOHN HAYES |
| Green Building Rough | 9/21/2021 | Not Ready for Inspection | JOHN HAYES |
| SGSOV-Seismic Gas S/O Valve | 9/21/2021 | SGSOV Not Ready | JOHN HAYES |
| Smoke Detectors | 9/21/2021 | Not Ready for Inspection | JOHN HAYES |
| BUILDING-Rough-Frame | 9/28/2021 | Not Ready for Inspection | JOHN HAYES |
| Final | 9/28/2021 | Corrections Issued | JOHN HAYES |
| Green Building Final | 9/28/2021 | Not Ready for Inspection | JOHN HAYES |
| Green Building Rough | 9/28/2021 | Not Ready for Inspection | JOHN HAYES |
| SGSOV-Seismic Gas S/O Valve | 9/28/2021 | SGSOV Not Ready | JOHN HAYES |
| Smoke Detectors | 9/28/2021 | Not Ready for Inspection | JOHN HAYES |
| BUILDING-Rough-Frame | 11/4/2021 | Not Ready for Inspection | JOHN HAYES |
| Final | 11/4/2021 | Corrections Issued | JOHN HAYES |
| Green Building Final | 11/4/2021 | Not Ready for Inspection | JOHN HAYES |
| Green Building Rough | 11/4/2021 | Not Ready for Inspection | JOHN HAYES |
| SGSOV-Seismic Gas S/O Valve | 11/4/2021 | SGSOV Not Ready | JOHN HAYES |
| Smoke Detectors | 11/4/2021 | Not Ready for Inspection | JOHN HAYES |
| BUILDING-Rough-Frame | 11/23/2021 | Approved | MICHEL ABAJAN |
| Final | 11/23/2021 | Not Ready for Inspection | MICHEL ABAJAN |
| Green Building Final | 11/23/2021 | Not Ready for Inspection | MICHEL ABAJAN |
| Green Building Rough | 11/23/2021 | Approved | MICHEL ABAJAN |
| SGSOV-Seismic Gas S/O Valve | 11/23/2021 | SGSOV Approved | MICHEL ABAJAN |
| Smoke Detectors | 11/23/2021 | Approved | MICHEL ABAJAN |
| Final | 12/20/2021 | Corrections Issued | JOHN HAYES |
| Green Building Final | 12/20/2021 | Not Ready for Inspection | JOHN HAYES |
| Final | 12/27/2021 | Corrections Issued | JOHN HAYES |
| Green Building Final | 12/27/2021 | Not Ready for Inspection | JOHN HAYES |
| Final | 1/25/2022 | Not Ready for Inspection | JOHN HAYES |
| Green Building Final | 1/25/2022 | Not Ready for Inspection | JOHN HAYES |
| Final | 2/10/2022 | OK to Issue CofO | JOHN HAYES |
| Green Building Final | 2/10/2022 | Approved | JOHN HAYES |