13305 W HERRON ST 91342

Certificate Information: 13305 W HERRON ST 91342

Application / Permit
20016-20000-29616
Plan Check / Job No.
B20VN14851
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) DETACHED 24' X 24' GARAGE TO ADU. ALL WORK DONE PER WFPP.
Permit Issued
Issued on 1/28/2021
Issuing Office
Current Status
CofO Issued on 3/5/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/20/2020 APPLICANT
Assigned to Plan Check Engineer 11/24/2020 GURUNATH NESARAJAH
Corrections Issued 11/28/2020 GURUNATH NESARAJAH
Plan Check Approved 1/10/2021 GURUNATH NESARAJAH
Issued 1/28/2021 APPLICANT
CofO in Progress 2/10/2022 JOHN HAYES
CofO Issued 3/5/2022 MICHAEL SMITH
Permit Finaled 3/5/2022 MICHAEL SMITH

Permit Application Clearance Information

ZI Cleared 12/14/2020 MIGUEL GAMBOA
Address approval Cleared 12/18/2020 GUILLERMO PETRA
Sewer availability Cleared 12/18/2020 GUILLERMO PETRA
Eng Process Fee Ord 176,300 Cleared 12/21/2020 GUILLERMO PETRA

Contact Information

Contractor Owner-Builder       ,

Inspector Information

KEVIN BERBERYAN, (818) 374-9931 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 2/8/2021 Conditional Approval MISAEL ESPARZA
Deputy Drilled-In Anchors 2/9/2021 Conditional Approval MISAEL ESPARZA
Footing/Foundation/Slab 2/9/2021 Conditional Approval MISAEL ESPARZA
Deputy Drilled-In Anchors 2/11/2021 Conditional Approval MISAEL ESPARZA
Floor/Roof Diaphrgm/Shear Wall 3/9/2021 Not Ready for Inspection MISAEL ESPARZA
BUILDING-Rough-Frame 4/5/2021 Not Ready for Inspection MISAEL ESPARZA
ELECTRICAL-Rough 4/5/2021 Not Ready for Inspection MISAEL ESPARZA
Green Building Rough 4/5/2021 Not Ready for Inspection MISAEL ESPARZA
Interior/Exterior Lathing 4/5/2021 Not Ready for Inspection MISAEL ESPARZA
PLUMBING-Rough 4/5/2021 Corrections Issued MISAEL ESPARZA
Rough-Elec/Plmb/HVAC 4/5/2021 Not Ready for Inspection MISAEL ESPARZA
Sewer 4/5/2021 Partial Approval MISAEL ESPARZA
Wood Frame 4/5/2021 Not Ready for Inspection MISAEL ESPARZA
ELECTRICAL-Rough 4/13/2021 Approved MISAEL ESPARZA
Gas Test 4/13/2021 Not Ready for Inspection MISAEL ESPARZA
HVAC-Rough 4/13/2021 Not Ready for Inspection MISAEL ESPARZA
PLUMBING-Rough 4/13/2021 Not Ready for Inspection MISAEL ESPARZA
Sewer 4/13/2021 Approved MISAEL ESPARZA
BUILDING-Rough-Frame 4/19/2021 Not Ready for Inspection MISAEL ESPARZA
Gas Test 4/19/2021 Partial Approval MISAEL ESPARZA
Green Building Rough 4/19/2021 Not Ready for Inspection MISAEL ESPARZA
PLUMBING-Rough 4/26/2021 Approved MISAEL ESPARZA
Insulation 5/3/2021 Partial Approval MISAEL ESPARZA
HVAC-Rough 5/10/2021 Approved MISAEL ESPARZA
Insulation 5/10/2021 Approved MISAEL ESPARZA
Wood Frame 5/10/2021 Approved MISAEL ESPARZA
Drywall Nailing 5/25/2021 Approved MORRIS JACKSON
Shower Pan 6/1/2021 Approved MISAEL ESPARZA
Interior/Exterior Lathing 6/8/2021 Approved DEANDRE HOFFMAN
Footing/Foundation/Slab 6/21/2021 Approved MISAEL ESPARZA
BUILDING-Rough-Frame 9/21/2021 Not Ready for Inspection JOHN HAYES
Final 9/21/2021 Corrections Issued JOHN HAYES
Green Building Final 9/21/2021 Not Ready for Inspection JOHN HAYES
Green Building Rough 9/21/2021 Not Ready for Inspection JOHN HAYES
SGSOV-Seismic Gas S/O Valve 9/21/2021 SGSOV Not Ready JOHN HAYES
Smoke Detectors 9/21/2021 Not Ready for Inspection JOHN HAYES
BUILDING-Rough-Frame 9/28/2021 Not Ready for Inspection JOHN HAYES
Final 9/28/2021 Corrections Issued JOHN HAYES
Green Building Final 9/28/2021 Not Ready for Inspection JOHN HAYES
Green Building Rough 9/28/2021 Not Ready for Inspection JOHN HAYES
SGSOV-Seismic Gas S/O Valve 9/28/2021 SGSOV Not Ready JOHN HAYES
Smoke Detectors 9/28/2021 Not Ready for Inspection JOHN HAYES
BUILDING-Rough-Frame 11/4/2021 Not Ready for Inspection JOHN HAYES
Final 11/4/2021 Corrections Issued JOHN HAYES
Green Building Final 11/4/2021 Not Ready for Inspection JOHN HAYES
Green Building Rough 11/4/2021 Not Ready for Inspection JOHN HAYES
SGSOV-Seismic Gas S/O Valve 11/4/2021 SGSOV Not Ready JOHN HAYES
Smoke Detectors 11/4/2021 Not Ready for Inspection JOHN HAYES
BUILDING-Rough-Frame 11/23/2021 Approved MICHEL ABAJAN
Final 11/23/2021 Not Ready for Inspection MICHEL ABAJAN
Green Building Final 11/23/2021 Not Ready for Inspection MICHEL ABAJAN
Green Building Rough 11/23/2021 Approved MICHEL ABAJAN
SGSOV-Seismic Gas S/O Valve 11/23/2021 SGSOV Approved MICHEL ABAJAN
Smoke Detectors 11/23/2021 Approved MICHEL ABAJAN
Final 12/20/2021 Corrections Issued JOHN HAYES
Green Building Final 12/20/2021 Not Ready for Inspection JOHN HAYES
Final 12/27/2021 Corrections Issued JOHN HAYES
Green Building Final 12/27/2021 Not Ready for Inspection JOHN HAYES
Final 1/25/2022 Not Ready for Inspection JOHN HAYES
Green Building Final 1/25/2022 Not Ready for Inspection JOHN HAYES
Final 2/10/2022 OK to Issue CofO JOHN HAYES
Green Building Final 2/10/2022 Approved JOHN HAYES