715 W HOWARD ST 90292
Certificate Information: 715 W HOWARD ST 90292
- Application / Permit
- 20016-20000-29602
- Plan Check / Job No.
- B20VN14840
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- INTERIOR REMODEL; WINDOW CHANGE OUT; NEW 12'-10" X 4'-2" BALCONY
- Permit Issued
- Issued on 4/12/2021
- Issuing Office
- Current Status
- Permit Finaled on 8/10/2022
Permit Application Status History
| Submitted | 11/16/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 11/24/2020 | SELLA BENYAMIN |
| Corrections Issued | 11/30/2020 | SELLA BENYAMIN |
| Applicant returned to address corrections | 2/2/2021 | SELLA BENYAMIN |
| Plan Check Approved | 3/26/2021 | SELLA BENYAMIN |
| Issued | 4/12/2021 | APPLICANT |
| Building Plans Picked Up | 4/20/2021 | APPLICANT |
| Permit Finaled | 8/9/2022 | JESUS RODRIGUEZ |
Permit Application Clearance Information
| Specific Plan | Cleared | 2/9/2021 | SIENNA KUO |
| Specific Plan | Cleared | 2/9/2021 | SIENNA KUO |
| Coastal Zone | Cleared | 3/8/2021 | MIGUEL GAMBOA |
Contact Information
| Contractor | J B New Construction Inc; Lic. No.: 923970-B | 13923 S CRENSHAW BLVD HAWTHORNE, CA 90250 |
Inspector Information
| DAKOTA LOW, (310) 914-3895 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 5/3/2021 | Approved | ENRIQUE MIRELES |
| BUILDING-Rough-Frame | 9/28/2021 | Partial Inspection | ENRIQUE MIRELES |
| PLUMBING-Rough | 9/28/2021 | Approved | ENRIQUE MIRELES |
| BUILDING-Rough-Frame | 10/6/2021 | Approved | ENRIQUE MIRELES |
| ELECTRICAL-Rough | 10/6/2021 | Approved | ENRIQUE MIRELES |
| HVAC-Rough | 10/6/2021 | Approved | ENRIQUE MIRELES |
| PLUMBING-Rough | 10/6/2021 | Approved | ENRIQUE MIRELES |
| Structural Steel Frame | 10/6/2021 | Approved | ENRIQUE MIRELES |
| Insulation | 10/20/2021 | Approved | DEANDRE HOFFMAN |
| Drywall Nailing | 11/2/2021 | Approved | KRISTEN CAUSEY |
| Drywall Nailing | 11/4/2021 | Partial Inspection | STEPHANIE SWANSON |
| Interior/Exterior Lathing | 12/13/2021 | Approved | ENRIQUE MIRELES |
| Shower Pan | 12/13/2021 | Approved | ENRIQUE MIRELES |
| ELECTRICAL-Final | 8/9/2022 | Approved | JESUS RODRIGUEZ |
| Final | 8/9/2022 | Permit Finaled | JESUS RODRIGUEZ |
| HVAC-Final | 8/9/2022 | Approved | JESUS RODRIGUEZ |
| PLUMBING-Final | 8/9/2022 | Approved | JESUS RODRIGUEZ |
| SGSOV-Seismic Gas S/O Valve | 8/9/2022 | SGSOV Approved | JESUS RODRIGUEZ |
| Smoke Detectors | 8/9/2022 | Approved | JESUS RODRIGUEZ |