19313 W FRIAR ST 91335
Certificate Information: 19313 W FRIAR ST 91335
- Application / Permit
- 20016-20000-29600
- Plan Check / Job No.
- B20VN14839
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) DETACHED GARAGE TO ACCESSORY DWELLING UNIT (372 SQ FT).
- Permit Issued
- Issued on 1/7/2021
- Issuing Office
- Current Status
- CofO Corrected on 8/16/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/16/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 11/24/2020 | JEROME MAGAT PALMA |
| Corrections Issued | 11/26/2020 | JEROME MAGAT PALMA |
| Plan Check Approved | 12/29/2020 | JEROME MAGAT PALMA |
| Issued | 1/7/2021 | APPLICANT |
| CofO in Progress | 8/13/2021 | HENRY KIM |
| Re-Activate Permit | 8/16/2021 | JOHN JANSON |
| CofO Issued-Status Void | 8/16/2021 | JOHN JANSON |
| Permit Finaled-Status Void | 8/16/2021 | JOHN JANSON |
| CofO Corrected | 8/16/2021 | JOHN JANSON |
| Permit Finaled | 8/16/2021 | JOHN JANSON |
Permit Application Clearance Information
| ZI | Cleared | 12/7/2020 | LAUREN PADICK |
| Address approval | Cleared | 12/14/2020 | JOHN TRIANTAFYLLOS |
| Sewer availability | Cleared | 12/14/2020 | JOHN TRIANTAFYLLOS |
| Eng Process Fee Ord 176,300 | Cleared | 12/15/2020 | JOHN TRIANTAFYLLOS |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Hajdari,, Genti; Lic. No.: C88031 | 140 S MENTOR AVE APT #207 PASADENA, CA 91106 |
Inspector Information
| ALEXANDER HANDY, (818) 774-4317 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 1/29/2021 | Corrections Issued | HENRY KIM |
| PLUMBING-Rough | 1/29/2021 | Partial Approval | HENRY KIM |
| Footing/Foundation/Slab | 2/1/2021 | Approved | HENRY KIM |
| Pre-Inspection | 2/1/2021 | Corrections Issued | HENRY KIM |
| Floor/Roof Diaphrgm/Shear Wall | 2/9/2021 | Corrections Issued | HENRY KIM |
| Green Building Rough | 2/9/2021 | Not Ready for Inspection | HENRY KIM |
| BUILDING-Rough-Frame | 2/24/2021 | Partial Approval | HENRY KIM |
| ELECTRICAL-Rough | 2/24/2021 | Corrections Issued | HENRY KIM |
| PLUMBING-Rough | 2/24/2021 | Approved | HENRY KIM |
| Sewer | 2/24/2021 | Approved | HENRY KIM |
| Underground Mechanical | 2/24/2021 | Corrections Issued | HENRY KIM |
| ELECTRICAL-Rough | 3/2/2021 | Approved | HENRY KIM |
| HVAC-Rough | 3/2/2021 | Approved | HENRY KIM |
| Underground Mechanical | 3/2/2021 | Corrections Issued | HENRY KIM |
| BUILDING-Rough-Frame | 3/5/2021 | Corrections Issued | HENRY KIM |
| ELECTRICAL-Final | 3/5/2021 | Corrections Issued | HENRY KIM |
| Insulation | 3/5/2021 | Approved | HENRY KIM |
| BUILDING-Rough-Frame | 3/10/2021 | Corrections Issued | HENRY KIM |
| Drywall Nailing | 3/10/2021 | Not Ready for Inspection | HENRY KIM |
| Floor/Roof Diaphrgm/Shear Wall | 3/10/2021 | Partial Approval | HENRY KIM |
| BUILDING-Rough-Frame | 3/15/2021 | Corrections Issued | HENRY KIM |
| Drywall Nailing | 3/15/2021 | Approved | HENRY KIM |
| Floor/Roof Diaphrgm/Shear Wall | 3/15/2021 | Not Ready for Inspection | HENRY KIM |
| Green Building Rough | 3/15/2021 | Approved | HENRY KIM |
| Shower Pan | 3/15/2021 | Approved | HENRY KIM |
| BUILDING-Rough-Frame | 3/18/2021 | Approved | HENRY KIM |
| Floor/Roof Diaphrgm/Shear Wall | 3/18/2021 | Approved | HENRY KIM |
| Interior/Exterior Lathing | 3/18/2021 | Approved | HENRY KIM |
| ELECTRICAL-Final | 5/19/2021 | Corrections Issued | HENRY KIM |
| Final | 5/19/2021 | Corrections Issued | HENRY KIM |
| Green Building Final | 5/19/2021 | Approved | HENRY KIM |
| HVAC-Final | 5/19/2021 | Corrections Issued | HENRY KIM |
| PLUMBING-Final | 5/19/2021 | Corrections Issued | HENRY KIM |
| SGSOV-Seismic Gas S/O Valve | 5/19/2021 | SGSOV Not Ready | HENRY KIM |
| Smoke Detectors | 5/19/2021 | Approved | HENRY KIM |
| ELECTRICAL-Final | 8/13/2021 | Approved | HENRY KIM |
| Final | 8/13/2021 | OK to Issue CofO | HENRY KIM |
| HVAC-Final | 8/13/2021 | Approved | HENRY KIM |
| PLUMBING-Final | 8/13/2021 | Approved | HENRY KIM |
| SGSOV-Seismic Gas S/O Valve | 8/13/2021 | SGSOV Approved | HENRY KIM |