20650-20652 W LEMAY ST 91306

Certificate Information: 20650-20652 W LEMAY ST 91306

Application / Permit
20016-20000-29533
Plan Check / Job No.
B20VN14822
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
CONVERT 18' X 22;-4" (E) ATTACHED GARAGE INTO (N) ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) AND (e). ALL WORK PER WFPP.
Permit Issued
Issued on 2/3/2021
Issuing Office
Current Status
CofO Issued on 7/9/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/16/2020 APPLICANT
Assigned to Plan Check Engineer 11/23/2020 RAPHAEL ROSAS
Corrections Issued 11/23/2020 RAPHAEL ROSAS
Plan Check Approved 1/5/2021 RAPHAEL ROSAS
Issued 2/3/2021 APPLICANT
CofO in Progress 7/8/2021 HENRY KIM
CofO Issued 7/9/2021 MICHAEL SMITH
Permit Finaled 7/9/2021 MICHAEL SMITH

Permit Application Clearance Information

ZI Cleared 12/1/2020 STEVEN WECHSLER
Address approval Cleared 12/7/2020 JOHN TRIANTAFYLLOS
Eng Process Fee Ord 176,300 Cleared 12/7/2020 JOHN TRIANTAFYLLOS
Sewer availability Cleared 12/7/2020 JOHN TRIANTAFYLLOS

Contact Information

Contractor South Pacific Development Construction Inc; Lic. No.: 1063751-B 14926 TOUCHWOOD AVE      BELLFLOWER, CA 90706

Inspector Information

ALEXANDER HANDY, (818) 774-4317 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

ELECTRICAL-Rough 3/2/2021 Corrections Issued HENRY KIM
Footing/Foundation/Slab 3/2/2021 Corrections Issued HENRY KIM
PLUMBING-Rough 3/2/2021 Corrections Issued HENRY KIM
BUILDING-Rough-Frame 3/31/2021 Not Ready for Inspection HENRY KIM
ELECTRICAL-Rough 3/31/2021 Not Ready for Inspection HENRY KIM
Footing/Foundation/Slab 3/31/2021 Corrections Issued HENRY KIM
PLUMBING-Rough 3/31/2021 Corrections Issued HENRY KIM
BUILDING-Rough-Frame 4/9/2021 Corrections Issued HENRY KIM
Floor/Roof Diaphrgm/Shear Wall 4/9/2021 Partial Approval HENRY KIM
Footing/Foundation/Slab 4/9/2021 Approved HENRY KIM
PLUMBING-Rough 4/9/2021 Corrections Issued HENRY KIM
BUILDING-Rough-Frame 4/26/2021 Partial Approval HENRY KIM
ELECTRICAL-Rough 4/26/2021 Corrections Issued HENRY KIM
Floor/Roof Diaphrgm/Shear Wall 4/26/2021 Partial Approval HENRY KIM
Underground Mechanical 4/26/2021 Corrections Issued HENRY KIM
BUILDING-Rough-Frame 5/3/2021 Approved HENRY KIM
ELECTRICAL-Rough 5/3/2021 Approved HENRY KIM
Floor/Roof Diaphrgm/Shear Wall 5/3/2021 Approved HENRY KIM
Green Building Rough 5/3/2021 Approved HENRY KIM
Insulation 5/3/2021 Approved HENRY KIM
Interior/Exterior Lathing 5/3/2021 Approved HENRY KIM
Underground Mechanical 5/3/2021 Approved HENRY KIM
Drywall Nailing 5/12/2021 Approved LILIANA PORTILLO
Interior/Exterior Lathing 5/12/2021 Approved LILIANA PORTILLO
Special/Order Compliance 5/12/2021 Partial Inspection JESUS PINEDA
ELECTRICAL-Final 7/1/2021 Corrections Issued HENRY KIM
Final 7/1/2021 Not Ready for Inspection HENRY KIM
Gas Test 7/1/2021 Corrections Issued HENRY KIM
Green Building Final 7/1/2021 Approved HENRY KIM
HVAC-Final 7/1/2021 Corrections Issued HENRY KIM
PLUMBING-Final 7/1/2021 Corrections Issued HENRY KIM
SGSOV-Seismic Gas S/O Valve 7/1/2021 SGSOV Not Ready HENRY KIM
Smoke Detectors 7/1/2021 Corrections Issued HENRY KIM
ELECTRICAL-Final 7/8/2021 Approved HENRY KIM
Final 7/8/2021 OK to Issue CofO HENRY KIM
Gas Test 7/8/2021 Approved HENRY KIM
HVAC-Final 7/8/2021 Approved HENRY KIM
PLUMBING-Final 7/8/2021 Approved HENRY KIM
SGSOV-Seismic Gas S/O Valve 7/8/2021 SGSOV Approved HENRY KIM
Smoke Detectors 7/8/2021 Approved HENRY KIM