330 N WESTERN AVE 90004
Certificate Information: 330 N WESTERN AVE 90004
- Application / Permit
- 20016-20000-29507
- Plan Check / Job No.
- B20VN14812
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (16) Retail
- Work Description
- REMODEL STOREFRONT, INTERIOR T. I., ADA COMPLIANT RESTROOMS AND CHANGE OF USE FROM DRESS MANU. TO RETAIL , NO CHANGE IN PARKING
- Permit Issued
- Issued on 7/11/2021
- Issuing Office
- Current Status
- CofO Issued on 12/27/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/13/2020 | APPLICANT |
| Disabled Access Plans Picked Up | 11/30/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 12/10/2020 | MOHAMMAD ESMAILI |
| Corrections Issued | 1/8/2021 | MOHAMMAD ESMAILI |
| Quality Review Completed | 1/8/2021 | OMID HEDAYAT |
| Building Plans Picked Up | 2/11/2021 | APPLICANT |
| Plan Check Approved | 6/23/2021 | MOHAMMAD ESMAILI |
| Issued | 7/11/2021 | APPLICANT |
| CofO Issued | 12/27/2024 | ERNESTO CORRAL |
| Permit Finaled | 12/27/2024 | ERNESTO CORRAL |
Permit Application Clearance Information
| Address approval | Cleared | 3/25/2021 | WALLIE JONG |
| Sewer availability | Cleared | 3/25/2021 | WALLIE JONG |
| Eng Process Fee Ord 176,300 | Cleared | 3/26/2021 | WALLIE JONG |
| DAS Clearance | Cleared | 4/1/2021 | NORLITO MEDRANO |
| ZI | Cleared | 6/15/2021 | DAVID URITA |
Contact Information
| Architect | Ro,, Jungdack; Lic. No.: C31119 | 4931 MURIETTA AVENUE SHERMAN OAKS, CA 91423 |
| Contractor | R K S Zone Inc; Lic. No.: 961017-B | 4931 MURIETTA AVE SHERMAN OAKS, CA 91423 |
| Engineer | Park,, Juntae; Lic. No.: C65104 | 3055 WILSHIRE BLVD 880 LOS ANGELES, CA 90010 |
Inspector Information
| TIMOTHY POWELL, (213) 482-0360 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Light Gage Steel Frame | 8/11/2021 | Approved | JONATHAN QUACH |
| Interior/Exterior Lathing | 8/19/2021 | Approved | RUSSELL BONVOULOIR |
| Final | 11/8/2021 | Not Ready for Inspection | SORIN CIRSTOIU |
| Reinforced Masonry Frame | 11/8/2021 | Not Ready for Inspection | SORIN CIRSTOIU |
| SGSOV-Seismic Gas S/O Valve | 11/8/2021 | SGSOV Not Ready | SORIN CIRSTOIU |
| Smoke Detectors | 11/8/2021 | Not Ready for Inspection | SORIN CIRSTOIU |
| Wood Frame | 11/8/2021 | Partial Inspection | SORIN CIRSTOIU |
| Final | 11/24/2021 | Not Ready for Inspection | SORIN CIRSTOIU |
| Reinforced Masonry Frame | 11/24/2021 | Not Ready for Inspection | SORIN CIRSTOIU |
| SGSOV-Seismic Gas S/O Valve | 11/24/2021 | SGSOV Not Ready | SORIN CIRSTOIU |
| Smoke Detectors | 11/24/2021 | Not Ready for Inspection | SORIN CIRSTOIU |
| Wood Frame | 11/24/2021 | Not Ready for Inspection | SORIN CIRSTOIU |
| Final | 12/1/2022 | Partial Approval | RONALD JIMENEZ |
| Reinforced Masonry Frame | 12/1/2022 | Approved | RONALD JIMENEZ |
| SGSOV-Seismic Gas S/O Valve | 12/1/2022 | SGSOV Approved | RONALD JIMENEZ |
| Smoke Detectors | 12/1/2022 | Approved | RONALD JIMENEZ |
| Wood Frame | 12/1/2022 | Approved | RONALD JIMENEZ |
| Final | 12/8/2022 | Not Ready for Inspection | RAFAEL CORTES |
| Final | 12/12/2022 | Not Ready for Inspection | RAFAEL CORTES |
| Final | 12/20/2022 | Partial Approval | RONALD JIMENEZ |
| Special/Order Compliance | 12/20/2024 | Approved | LUIS CCAMACHO |
| Final | 12/23/2024 | Partial Approval | LUIS CCAMACHO |