8038 S CAMPION DR 90045

Certificate Information: 8038 S CAMPION DR 90045

Application / Permit
20016-20000-29430
Plan Check / Job No.
B20VN14774
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT EX DETACHED GARAGE INTO ACCESSORY DWELLING UNIT PER ORD #186,481. ALL WORK PER WFPP.
Permit Issued
Issued on 4/21/2021
Issuing Office
Current Status
CofO Issued on 10/25/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/13/2020 APPLICANT
Assigned to Plan Check Engineer 11/20/2020 HAYATO TSUCHIYA
Corrections Issued 11/22/2020 HAYATO TSUCHIYA
Applicant returned to address corrections 2/2/2021 HAYATO TSUCHIYA
Plan Check Approved 3/4/2021 HAYATO TSUCHIYA
Plan Check Approved 4/12/2021 HAYATO TSUCHIYA
Building Plans Picked Up 4/13/2021 APPLICANT
Issued 4/21/2021 APPLICANT
CofO in Progress 10/6/2021 BRENDAN LOONEY
Permit Finaled 10/25/2021 DANIEL ORRANTE
CofO Issued 10/25/2021 DANIEL ORRANTE
Permit Finaled 10/25/2021 DANIEL ORRANTE

Permit Application Clearance Information

Address approval Cleared 12/15/2020 SAUL GARCIA
Sewer availability Cleared 12/15/2020 SAUL GARCIA
Eng Process Fee Ord 176,300 Cleared 12/16/2020 SAUL GARCIA
Permit Cleared 12/16/2020 SAUL GARCIA
Specific Plan Cleared 1/7/2021 PEDRO AYALA

Contact Information

Contractor Way To Go Builders; Lic. No.: 1043721-B 6700 FALLBROOK AVE STE 133      WEST HILLS, CA 91307

Inspector Information

MICHAEL LEWIS, (310) 914-3979 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 6/4/2021 Partial Approval PIERRE VEGA
Footing/Foundation/Slab 6/7/2021 Not Ready for Inspection BRENDAN LOONEY
Deputy Drilled-In Anchors 6/10/2021 Approved BRENDAN LOONEY
Footing/Foundation/Slab 6/10/2021 Approved BRENDAN LOONEY
ELECTRICAL-Rough 6/30/2021 Not Ready for Inspection BRENDAN LOONEY
Floor/Roof Diaphrgm/Shear Wall 6/30/2021 Not Ready for Inspection BRENDAN LOONEY
HVAC-Rough 6/30/2021 Not Ready for Inspection BRENDAN LOONEY
PLUMBING-Rough 6/30/2021 Not Ready for Inspection BRENDAN LOONEY
ELECTRICAL-Rough 7/1/2021 Not Ready for Inspection BRENDAN LOONEY
HVAC-Rough 7/1/2021 Not Ready for Inspection BRENDAN LOONEY
PLUMBING-Rough 7/1/2021 Not Ready for Inspection BRENDAN LOONEY
Underground Mechanical 7/1/2021 Partial Approval BRENDAN LOONEY
ELECTRICAL-Rough 7/6/2021 Corrections Issued DONALD GALLAGHER
Floor/Roof Diaphrgm/Shear Wall 7/6/2021 Partial Approval DONALD GALLAGHER
HVAC-Rough 7/6/2021 Approved DONALD GALLAGHER
PLUMBING-Rough 7/6/2021 Partial Approval DONALD GALLAGHER
ELECTRICAL-Rough 7/14/2021 Approved BRENDAN LOONEY
Floor/Roof Diaphrgm/Shear Wall 7/14/2021 Approved BRENDAN LOONEY
PLUMBING-Rough 7/14/2021 Approved BRENDAN LOONEY
Wood Frame 7/14/2021 Approved BRENDAN LOONEY
Insulation 7/15/2021 Approved BRENDAN LOONEY
Drywall Nailing 7/19/2021 Approved BRENDAN LOONEY
Green Building Rough 7/19/2021 Approved BRENDAN LOONEY
Interior/Exterior Lathing 7/19/2021 Partial Approval BRENDAN LOONEY
Footing/Foundation/Slab 7/20/2021 Not Ready for Inspection BRENDAN LOONEY
Interior/Exterior Lathing 7/20/2021 Partial Approval BRENDAN LOONEY
BUILDING-Rough-Frame 9/22/2021 Approved BRENDAN LOONEY
ELECTRICAL-Final 9/22/2021 Corrections Issued BRENDAN LOONEY
Final 9/22/2021 Corrections Issued BRENDAN LOONEY
Green Building Final 9/22/2021 Approved BRENDAN LOONEY
HVAC-Final 9/22/2021 Approved BRENDAN LOONEY
METHANE-Final 9/22/2021 Approved BRENDAN LOONEY
METHANE-Rough 9/22/2021 Approved BRENDAN LOONEY
PLUMBING-Final 9/22/2021 Corrections Issued BRENDAN LOONEY
SGSOV-Seismic Gas S/O Valve 9/22/2021 SGSOV Not Ready BRENDAN LOONEY
Smoke Detectors 9/22/2021 Approved BRENDAN LOONEY
Final 9/30/2021 Corrections Issued BRENDAN LOONEY
PLUMBING-Final 9/30/2021 Not Ready for Inspection BRENDAN LOONEY
SGSOV-Seismic Gas S/O Valve 9/30/2021 SGSOV Approved BRENDAN LOONEY
Final 10/5/2021 OK to Issue CofO BRENDAN LOONEY
Gas Test 10/5/2021 Approved BRENDAN LOONEY