6421 N ORION AVE 91406

Certificate Information: 6421 N ORION AVE 91406

Application / Permit
20016-20000-29425
Plan Check / Job No.
B20VN14771
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
INTERIOR REMODEL TO (E) KITCHEN, BATHROOM AT SECOND FLOOR, AND MASTER BATHROOM AT FIRST FLOOR. REMOVE WALLS AT KITCHEN. WORK PER ENGINEER.
Permit Issued
Issued on 12/3/2020
Issuing Office
Current Status
Permit Finaled on 10/5/2021

Permit Application Status History

Submitted 11/13/2020 APPLICANT
Assigned to Plan Check Engineer 11/24/2020 ROSENDO MEDINA
Corrections Issued 11/27/2020 ROSENDO MEDINA
Plan Check Approved 12/3/2020 ROSENDO MEDINA
Issued 12/3/2020 APPLICANT
Permit Finaled 10/4/2021 RICHARD DOCKUS

Permit Application Clearance Information

No Data Available.

Contact Information

Contractor Owner-Builder       ,
Engineer Reith,, David Lee; Lic. No.: C72122 1319 FEATHER AVE      THOUSAND OAKS, CA 91360

Inspector Information

JOSE AVILA, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI
VINCENT HANLEY, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

BUILDING-Rough-Frame 12/10/2020 Partial Approval MICHEL ABAJAN
ELECTRICAL-Rough 12/10/2020 Partial Approval MICHEL ABAJAN
HVAC-Rough 12/10/2020 Partial Approval MICHEL ABAJAN
MERV13>=Rough 12/10/2020 Approved MICHEL ABAJAN
PLUMBING-Rough 12/10/2020 Partial Approval MICHEL ABAJAN
PLUMBING-Rough 12/14/2020 Not Ready for Inspection JOHN HAYES
PLUMBING-Rough 12/15/2020 Corrections Issued MICHAEL TEMPLE
PLUMBING-Rough 12/21/2020 Not Ready for Inspection BEAU COLLINS
Shower Pan 12/24/2020 Corrections Issued MISAEL ESPARZA
Interior/Exterior Lathing 1/4/2021 Approved JENNIFER RABUCHIN
Shower Pan 1/4/2021 Approved JENNIFER RABUCHIN
ELECTRICAL-Final 4/13/2021 No Access for Inspection MICHAEL TEMPLE
HVAC-Final 4/13/2021 No Access for Inspection MICHAEL TEMPLE
PLUMBING-Final 4/13/2021 Not Ready for Inspection MICHAEL TEMPLE
ELECTRICAL-Final 4/21/2021 Partial Approval ARTHUR SARGSYAN
PLUMBING-Final 4/21/2021 Partial Approval ARTHUR SARGSYAN
BUILDING-Rough-Frame 5/13/2021 Corrections Issued JENNIFER RABUCHIN
ELECTRICAL-Rough 5/13/2021 Corrections Issued JENNIFER RABUCHIN
HVAC-Rough 5/13/2021 Partial Approval JENNIFER RABUCHIN
PLUMBING-Rough 5/13/2021 Corrections Issued JENNIFER RABUCHIN
Shower Pan 5/13/2021 Approved JENNIFER RABUCHIN
BUILDING-Rough-Frame 5/21/2021 Not Ready for Inspection MARK JOHNSON
ELECTRICAL-Rough 5/21/2021 Partial Approval MARK JOHNSON
Footing/Foundation/Slab 5/21/2021 Partial Approval MARK JOHNSON
HVAC-Rough 5/21/2021 Partial Approval MARK JOHNSON
ELECTRICAL-Rough 5/27/2021 Partial Approval MICHEL ABAJAN
HVAC-Rough 5/27/2021 Partial Approval MICHEL ABAJAN
Interior/Exterior Lathing 5/27/2021 Approved MICHEL ABAJAN
PLUMBING-Rough 5/27/2021 Partial Approval MICHEL ABAJAN
BUILDING-Rough-Frame 6/4/2021 Approved MICHAEL TEMPLE
Drywall Nailing 6/4/2021 Approved JESUS RODRIGUEZ
Final 9/29/2021 Corrections Issued JACK KARGODORIAN
MERV13>=Final 9/29/2021 Approved JACK KARGODORIAN
SGSOV-Seismic Gas S/O Valve 9/29/2021 SGSOV Approved JACK KARGODORIAN
Smoke Detectors 9/29/2021 Approved JACK KARGODORIAN
Final 10/4/2021 Permit Finaled RICHARD DOCKUS