8012-8014 N ALLOTT AVE 91402
Certificate Information: 8012-8014 N ALLOTT AVE 91402
- Application / Permit
- 20016-20000-29329
- Plan Check / Job No.
- B20VN14752
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- CONVERT (E) ATTACHED GARAGE AND PORTION OF (E) DWELLING TO ACCESSORY DWELLING UNIT (628 SQ FT) PER LAMC 12.22 A. 33(c) and (e)
- Permit Issued
- Issued on 1/11/2021
- Issuing Office
- Current Status
- CofO Issued on 10/6/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/12/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 11/20/2020 | ROSENDO MEDINA |
| Corrections Issued | 11/22/2020 | ROSENDO MEDINA |
| Plan Check Approved | 1/4/2021 | JEROME MAGAT PALMA |
| Issued | 1/11/2021 | APPLICANT |
| CofO in Progress | 10/5/2021 | GREGG CUMMINGS |
| CofO Issued | 10/6/2021 | MICHAEL SMITH |
| Permit Finaled | 10/6/2021 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 12/15/2020 | JOHN TRIANTAFYLLOS |
| Eng Process Fee Ord 176,300 | Cleared | 12/15/2020 | JOHN TRIANTAFYLLOS |
| Sewer availability | Cleared | 12/15/2020 | JOHN TRIANTAFYLLOS |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Adzhemyan,, Arsen; Lic. No.: C89103 | 1010 RALEIGH ST APT 107 GLENDALE, CA 91205 |
Inspector Information
| OGANES TARAKHCHYAN, (818) 374-1162 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 2/16/2021 | Approved | GREGG CUMMINGS |
| Footing/Foundation/Slab | 4/6/2021 | Corrections Issued | GREGG CUMMINGS |
| Footing/Foundation/Slab | 4/14/2021 | Approved | GREGG CUMMINGS |
| ELECTRICAL-Rough | 4/30/2021 | Not Ready for Inspection | GREGG CUMMINGS |
| HVAC-Rough | 4/30/2021 | Approved | GREGG CUMMINGS |
| PLUMBING-Rough | 4/30/2021 | Not Ready for Inspection | GREGG CUMMINGS |
| Wood Frame | 4/30/2021 | Not Ready for Inspection | GREGG CUMMINGS |
| ELECTRICAL-Rough | 5/7/2021 | Approved | GREGG CUMMINGS |
| HVAC-Rough | 5/7/2021 | Partial Inspection | GREGG CUMMINGS |
| Wood Frame | 5/7/2021 | Corrections Issued | GREGG CUMMINGS |
| Wood Frame | 5/20/2021 | Corrections Issued | GREGG CUMMINGS |
| Insulation | 6/7/2021 | Approved | KRISTEN CAUSEY |
| Drywall Nailing | 6/17/2021 | Partial Approval | JAVIER RAMOS JR |
| BUILDING-Rough-Frame | 6/24/2021 | Approved | GREGG CUMMINGS |
| Drywall Nailing | 6/24/2021 | Approved | GREGG CUMMINGS |
| Green Building Rough | 6/24/2021 | Approved | GREGG CUMMINGS |
| PLUMBING-Rough | 6/24/2021 | Approved | GREGG CUMMINGS |
| Gas Test | 7/12/2021 | Approved | CALEB MEISTER |
| Final | 9/1/2021 | Corrections Issued | JOHN HAYES |
| Green Building Final | 9/1/2021 | Not Ready for Inspection | JOHN HAYES |
| SGSOV-Seismic Gas S/O Valve | 9/1/2021 | SGSOV Not Ready | JOHN HAYES |
| Smoke Detectors | 9/1/2021 | Not Ready for Inspection | JOHN HAYES |
| Final | 9/21/2021 | Corrections Issued | GREGG CUMMINGS |
| Green Building Final | 9/21/2021 | Approved | GREGG CUMMINGS |
| PLUMBING-Final | 9/21/2021 | Approved | GREGG CUMMINGS |
| SGSOV-Seismic Gas S/O Valve | 9/21/2021 | SGSOV Approved | GREGG CUMMINGS |
| Smoke Detectors | 9/21/2021 | Approved | GREGG CUMMINGS |
| Final | 10/5/2021 | OK to Issue CofO | GREGG CUMMINGS |