21024-21026 W BALTAR ST 91304
Certificate Information: 21024-21026 W BALTAR ST 91304
- Application / Permit
- 20016-20000-29295
- Plan Check / Job No.
- B20VN14715
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- CONVERT ATTACHED GARAGE ( 464 SQ FT ) TO ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(A). WORK PER DESIGN.
- Permit Issued
- Issued on 5/22/2021
- Issuing Office
- Current Status
- CofO Issued on 8/31/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/12/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 11/20/2020 | ROSENDO MEDINA |
| Corrections Issued | 11/22/2020 | ROSENDO MEDINA |
| Plan Check Approved | 2/3/2021 | ROSENDO MEDINA |
| Issued | 5/22/2021 | APPLICANT |
| CofO in Progress | 8/30/2022 | STEVEN BACK |
| Permit Finaled | 8/31/2022 | JOHN JANSON |
| CofO Issued | 8/31/2022 | JOHN JANSON |
| Permit Finaled | 8/31/2022 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 12/7/2020 | GABRIEL ROBLES |
| Eng Process Fee Ord 176,300 | Cleared | 12/7/2020 | GABRIEL ROBLES |
| Roof/Waste drainage to street | Cleared | 12/7/2020 | GABRIEL ROBLES |
| Sewer availability | Cleared | 12/7/2020 | GABRIEL ROBLES |
Contact Information
| Architect | Salcedo,, Glen Charles; Lic. No.: C33143 | P O BOX 14202 VAN NUYS, CA 91409 |
| Contractor | Jem Remodel & Construction Inc; Lic. No.: 1010179-B | 2720 S HARBOR BLVD #H SANTA ANA, CA 92704 |
Inspector Information
| ALEXANDER HANDY, (818) 774-4317 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 6/1/2021 | Corrections Issued | HENRY KIM |
| PLUMBING-Rough | 6/1/2021 | Corrections Issued | HENRY KIM |
| Deputy Drilled-In Anchors | 6/7/2021 | Approved | HENRY KIM |
| Floor/Roof Diaphrgm/Shear Wall | 6/7/2021 | Partial Approval | HENRY KIM |
| Footing/Foundation/Slab | 6/7/2021 | Approved | HENRY KIM |
| PLUMBING-Rough | 6/7/2021 | Partial Approval | HENRY KIM |
| BUILDING-Rough-Frame | 6/21/2021 | Not Ready for Inspection | HENRY KIM |
| ELECTRICAL-Rough | 6/21/2021 | Corrections Issued | HENRY KIM |
| Green Building Rough | 6/21/2021 | Not Ready for Inspection | HENRY KIM |
| Insulation | 6/21/2021 | Corrections Issued | HENRY KIM |
| PLUMBING-Rough | 6/21/2021 | Corrections Issued | HENRY KIM |
| Deputy Wood Construction | 6/22/2021 | Approved | KRISTEN CAUSEY |
| Floor/Roof Diaphrgm/Shear Wall | 7/2/2021 | Partial Inspection | HENRY KIM |
| Insulation | 7/2/2021 | Partial Approval | HENRY KIM |
| BUILDING-Rough-Frame | 8/11/2021 | Not Ready for Inspection | DAVID STEPANYAN |
| Green Building Rough | 8/11/2021 | Not Ready for Inspection | DAVID STEPANYAN |
| Interior/Exterior Lathing | 8/17/2021 | Approved | HENRY KIM |
| Shower Pan | 8/17/2021 | Approved | HENRY KIM |
| ELECTRICAL-Rough | 9/3/2021 | Approved | HENRY KIM |
| Floor/Roof Diaphrgm/Shear Wall | 9/3/2021 | Approved | HENRY KIM |
| Underground Mechanical | 9/3/2021 | Partial Approval | HENRY KIM |
| Insulation | 9/9/2021 | Conditional Approval | KRISTEN CAUSEY |
| Drywall Nailing | 9/13/2021 | Approved | HENRY KIM |
| Insulation | 9/13/2021 | Approved | HENRY KIM |
| Interior/Exterior Lathing | 9/13/2021 | Corrections Issued | HENRY KIM |
| Interior/Exterior Lathing | 9/17/2021 | Approved | HENRY KIM |
| BUILDING-Rough-Frame | 12/13/2021 | Approved | STEVEN BACK |
| Final | 12/13/2021 | Corrections Issued | STEVEN BACK |
| Green Building Rough | 12/13/2021 | Approved | STEVEN BACK |
| SGSOV-Seismic Gas S/O Valve | 12/13/2021 | SGSOV Not Ready | STEVEN BACK |
| Sewer | 12/13/2021 | Approved | STEVEN BACK |
| Smoke Detectors | 12/13/2021 | Approved | STEVEN BACK |
| Final | 12/28/2021 | Not Ready for Inspection | STEVEN BACK |
| Green Building Final | 12/28/2021 | Approved | STEVEN BACK |
| SGSOV-Seismic Gas S/O Valve | 12/28/2021 | SGSOV Approved | STEVEN BACK |
| Final | 8/30/2022 | OK to Issue CofO | STEVEN BACK |