12261-12263 W KLING ST 91607

Certificate Information: 12261-12263 W KLING ST 91607

Application / Permit
20016-20000-29289
Plan Check / Job No.
B20VN14710
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
CONVERT THE 21'x22' ATTACHED GARAGE INTO AN ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33 (c) AND (e).
Permit Issued
Issued on 1/20/2021
Issuing Office
Valley
Current Status
CofO Issued on 12/18/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/12/2020 APPLICANT
Assigned to Plan Check Engineer 11/20/2020 LUIS RINCON
Corrections Issued 11/23/2020 LUIS RINCON
Plan Check Approved 12/31/2020 JEROME MAGAT PALMA
Issued 1/20/2021 APPLICANT
CofO in Progress 11/4/2021 JENNIFER RABUCHIN
CofO in Progress 11/4/2021 JENNIFER RABUCHIN
Permit Finaled 12/18/2021 MICHAEL SMITH
CofO Issued 12/18/2021 MICHAEL SMITH
Permit Finaled 12/18/2021 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 12/8/2020 JOHN TRIANTAFYLLOS
Eng Process Fee Ord 176,300 Cleared 12/8/2020 JOHN TRIANTAFYLLOS
Sewer availability Cleared 12/8/2020 JOHN TRIANTAFYLLOS
ZI Cleared 12/9/2020 PABLO ESTRADA
Specific Plan Cleared 12/17/2020 ERIN NASH
ZI Cleared 12/17/2020 ERIN NASH

Contact Information

Contractor Owner-Builder       ,

Inspector Information

CHRISTOPHE COCHRAN, (818) 374-1165 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 5/25/2021 Partial Inspection ARAM AVEDISIAN
Footing/Foundation/Slab 6/1/2021 Approved MICHEL ABAJAN
BUILDING-Rough-Frame 6/9/2021 Approved MICHEL ABAJAN
Green Building Rough 6/9/2021 Approved MICHEL ABAJAN
MERV13>=Rough 6/9/2021 Approved MICHEL ABAJAN
PLUMBING-Rough 6/9/2021 Partial Approval MICHEL ABAJAN
ELECTRICAL-Rough 6/16/2021 Approved ARAM AVEDISIAN
Drywall Nailing 6/30/2021 Approved ALAN MORELOS
Interior/Exterior Lathing 6/30/2021 Partial Approval ALAN MORELOS
Pre-Inspection 7/19/2021 Not Ready for Inspection ARAM AVEDISIAN
Final 8/20/2021 Not Ready for Inspection ARAM AVEDISIAN
Green Building Final 8/20/2021 Not Ready for Inspection ARAM AVEDISIAN
MERV13>=Final 8/20/2021 Not Ready for Inspection ARAM AVEDISIAN
SGSOV-Seismic Gas S/O Valve 8/20/2021 SGSOV Not Ready ARAM AVEDISIAN
Smoke Detectors 8/20/2021 Not Ready for Inspection ARAM AVEDISIAN
Special/Order Compliance 9/1/2021 Corrections Issued ARAM AVEDISIAN
Special/Order Compliance 9/1/2021 Partial Inspection MICHAEL PELHAM
Final 9/9/2021 Corrections Issued JENNIFER RABUCHIN
Gas Test 9/9/2021 Approved JENNIFER RABUCHIN
Green Building Final 9/9/2021 Corrections Issued JENNIFER RABUCHIN
HVAC-Final 9/9/2021 Approved JENNIFER RABUCHIN
HVAC-Rough 9/9/2021 Approved JENNIFER RABUCHIN
Insulation 9/9/2021 Approved JENNIFER RABUCHIN
Interior/Exterior Lathing 9/9/2021 Approved JENNIFER RABUCHIN
MERV13>=Final 9/9/2021 Approved JENNIFER RABUCHIN
PLUMBING-Final 9/9/2021 Approved JENNIFER RABUCHIN
PLUMBING-Rough 9/9/2021 Approved JENNIFER RABUCHIN
SGSOV-Seismic Gas S/O Valve 9/9/2021 SGSOV Approved JENNIFER RABUCHIN
Shower Pan 9/9/2021 Approved JENNIFER RABUCHIN
Smoke Detectors 9/9/2021 Approved JENNIFER RABUCHIN
ELECTRICAL-Final 10/14/2021 Approved JENNIFER RABUCHIN
Final 10/14/2021 Partial Approval JENNIFER RABUCHIN
Green Building Final 10/14/2021 Not Ready for Inspection JENNIFER RABUCHIN
Final 11/4/2021 OK to Issue CofO JENNIFER RABUCHIN
Green Building Final 11/4/2021 Approved JENNIFER RABUCHIN