5150 N SHOSHONE AVE 91316
Certificate Information: 5150 N SHOSHONE AVE 91316
- Application / Permit
- 20016-20000-29153
- Plan Check / Job No.
- B20VN14687
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- INTERIOR REMODEL TO THE 1ST AND 2ND FLOOR OF (E) TWO-STORY SINGLE FAMILY DWELLING
- Permit Issued
- Issued on 6/7/2021
- Issuing Office
- Current Status
- Issued on 6/7/2021
Permit Application Status History
| Submitted | 11/16/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 11/19/2020 | SEAN SHAHMIRI |
| Corrections Issued | 11/22/2020 | SEAN SHAHMIRI |
| Quality Review Completed | 11/24/2020 | OMID HEDAYAT |
| Building Plans Picked Up | 11/24/2020 | APPLICANT |
| Applicant returned to address corrections | 5/4/2021 | SEAN SHAHMIRI |
| Applicant returned to address corrections | 5/14/2021 | SEAN SHAHMIRI |
| Applicant returned to address corrections | 6/7/2021 | SEAN SHAHMIRI |
| Plan Check Approved | 6/7/2021 | SEAN SHAHMIRI |
| Issued | 6/7/2021 | APPLICANT |
Permit Application Clearance Information
| ZI | Cleared | 1/26/2021 | MIGUEL GAMBOA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Yuzon,, Benigno S; Lic. No.: S3454 | 2511 PEACHWOOD PLACE WESTLAKE VILLAGE, CA 91361 |
Inspector Information
| JON MCHUGH, (818) 774-4348 | Office Hours: 7:00-8:00 AM MON-FRI |
| IVAN SARABIA, (818) 774-4348 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 6/14/2021 | Corrections Issued | STEVEN BACK |
| Interior/Exterior Lathing | 6/21/2021 | Partial Approval | RYAN SALAZAR |
| Shower Pan | 6/21/2021 | Partial Approval | RYAN SALAZAR |
| PLUMBING-Rough | 6/25/2021 | Partial Approval | STEVEN BACK |
| ELECTRICAL-Rough | 6/30/2021 | Not Ready for Inspection | DAVID SANDOVAL |
| Pre-Inspection | 7/16/2021 | Partial Inspection | RYAN SALAZAR |
| Excavation/Setback/Form/Re-Bar | 7/19/2021 | Corrections Issued | STEVEN BACK |
| HVAC-Rough | 7/20/2021 | Not Ready for Inspection | DAVID SANDOVAL |
| BUILDING-Rough-Frame | 8/11/2021 | Corrections Issued | STEVEN BACK |
| ELECTRICAL-Rough | 8/18/2021 | Approved | STEVEN BACK |
| PLUMBING-Rough | 8/18/2021 | Approved | STEVEN BACK |
| HVAC-Rough | 8/19/2021 | Corrections Issued | STEVEN BACK |
| Insulation | 8/19/2021 | Not Ready for Inspection | STEVEN BACK |
| BUILDING-Rough-Frame | 8/25/2021 | Partial Approval | STEVEN BACK |
| Final | 8/25/2021 | Corrections Issued | STEVEN BACK |
| HVAC-Rough | 8/25/2021 | Approved | STEVEN BACK |
| Drywall Nailing | 9/17/2021 | Approved | STEVEN BACK |
| ELECTRICAL-Final | 9/17/2021 | Not Ready for Inspection | STEVEN BACK |
| HVAC-Final | 9/17/2021 | Not Ready for Inspection | STEVEN BACK |
| Insulation | 9/17/2021 | Partial Approval | STEVEN BACK |
| PLUMBING-Final | 9/17/2021 | Not Ready for Inspection | STEVEN BACK |
| Smoke Detectors | 9/17/2021 | Not Ready for Inspection | STEVEN BACK |
| Gas Test | 10/6/2021 | Approved | STEVEN BACK |
| Final | 10/19/2021 | Corrections Issued | SEAN HAUPT |
| SGSOV-Seismic Gas S/O Valve | 10/19/2021 | SGSOV Approved | SEAN HAUPT |
| Smoke Detectors | 10/19/2021 | Approved | SEAN HAUPT |
| Final | 10/26/2021 | Conditional Approval | SEAN HAUPT |