464 S COMSTOCK AVE 90024
Certificate Information: 464 S COMSTOCK AVE 90024
- Application / Permit
- 20016-20000-29049
- Plan Check / Job No.
- B20VN14608
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- CONVERT 16'-5" X 17'-2" (E) ATTACHED GARAGE INTO A (N) JR. ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(A) AND 65852.22 AND CONVERT 4'-11" X 16'-5" PORTION OF GARAGE TO LAUNDRY ROOM. ALL WORK PER WFPP.
- Permit Issued
- Issued on 7/20/2021
- Issuing Office
- Current Status
- CofO Issued on 10/2/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/10/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 11/18/2020 | RAPHAEL ROSAS |
| Corrections Issued | 11/19/2020 | RAPHAEL ROSAS |
| Applicant returned to address corrections | 1/21/2021 | RAPHAEL ROSAS |
| Applicant returned to address corrections | 7/8/2021 | RAPHAEL ROSAS |
| Plan Check Approved | 7/15/2021 | RAPHAEL ROSAS |
| Building Plans Picked Up | 7/16/2021 | APPLICANT |
| Issued | 7/20/2021 | APPLICANT |
| CofO in Progress | 9/23/2021 | GERMAN RODRIGUEZ MENDOZA |
| CofO Issued | 10/2/2021 | DEROLD HAUFF |
| Permit Finaled | 10/2/2021 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 1/15/2021 | HISASHI KOBAYAKAWA |
| Eng Process Fee Ord 176,300 | Cleared | 6/28/2021 | DENNIS BRAGIN |
| Sewer availability | Cleared | 6/28/2021 | DENNIS BRAGIN |
| Grading Pre-Inspection | Cleared | 7/6/2021 | PATRICK MISCHLICH |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| DAVID SCANTLIN, (310) 914-3863 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 7/23/2021 | Approved | GERMAN RODRIGUEZ MENDOZA |
| ELECTRICAL-Rough | 7/26/2021 | Not Ready for Inspection | GERMAN RODRIGUEZ MENDOZA |
| PLUMBING-Rough | 7/26/2021 | Not Ready for Inspection | GERMAN RODRIGUEZ MENDOZA |
| Wood Frame | 7/26/2021 | Partial Approval | GERMAN RODRIGUEZ MENDOZA |
| BUILDING-Rough-Frame | 7/30/2021 | Corrections Issued | KIM BEAUCHAMP |
| ELECTRICAL-Rough | 7/30/2021 | Not Ready for Inspection | KIM BEAUCHAMP |
| Green Building Rough | 7/30/2021 | Not Ready for Inspection | KIM BEAUCHAMP |
| HVAC-Rough | 7/30/2021 | Not Ready for Inspection | KIM BEAUCHAMP |
| PLUMBING-Rough | 7/30/2021 | Not Ready for Inspection | KIM BEAUCHAMP |
| ELECTRICAL-Rough | 8/3/2021 | Partial Approval | ALIZAH MAYAGOITIA |
| Insulation | 8/3/2021 | Approved | ALIZAH MAYAGOITIA |
| PLUMBING-Rough | 8/3/2021 | Corrections Issued | ALIZAH MAYAGOITIA |
| BUILDING-Rough-Frame | 8/6/2021 | Approved | GERMAN RODRIGUEZ MENDOZA |
| Drywall Nailing | 8/6/2021 | Approved | GERMAN RODRIGUEZ MENDOZA |
| ELECTRICAL-Rough | 8/6/2021 | Partial Approval | GERMAN RODRIGUEZ MENDOZA |
| HVAC-Rough | 8/6/2021 | Approved | GERMAN RODRIGUEZ MENDOZA |
| PLUMBING-Rough | 8/6/2021 | Approved | GERMAN RODRIGUEZ MENDOZA |
| BUILDING-Rough-Frame | 9/17/2021 | Approved | GERMAN RODRIGUEZ MENDOZA |
| Final | 9/17/2021 | Corrections Issued | GERMAN RODRIGUEZ MENDOZA |
| Green Building Final | 9/17/2021 | Approved | GERMAN RODRIGUEZ MENDOZA |
| Green Building Rough | 9/17/2021 | Approved | GERMAN RODRIGUEZ MENDOZA |
| SGSOV-Seismic Gas S/O Valve | 9/17/2021 | SGSOV Approved | GERMAN RODRIGUEZ MENDOZA |
| Smoke Detectors | 9/17/2021 | Approved | GERMAN RODRIGUEZ MENDOZA |
| Final | 9/20/2021 | Conditional Approval | GERMAN RODRIGUEZ MENDOZA |