1913 S RIDGELEY DR 90016

Certificate Information: 1913 S RIDGELEY DR 90016

Application / Permit
20016-20000-29048
Plan Check / Job No.
B20VN14606
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) DETACHED GARAGE TO ACCESSORY DWELLING UNIT (429 SQ FT)
Permit Issued
Issued on 6/16/2021
Issuing Office
Current Status
CofO Issued on 2/16/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/10/2020 APPLICANT
Assigned to Plan Check Engineer 11/18/2020 JEROME MAGAT PALMA
Corrections Issued 11/19/2020 JEROME MAGAT PALMA
Plan Check Approved 6/7/2021 JEROME MAGAT PALMA
Building Plans Picked Up 6/8/2021 APPLICANT
Issued 6/16/2021 APPLICANT
CofO in Progress 2/9/2022 JOSE AVILA
Permit Finaled 2/16/2022 DEROLD HAUFF
CofO Issued 2/16/2022 DEROLD HAUFF
Permit Finaled 2/16/2022 DEROLD HAUFF

Permit Application Clearance Information

Sewer availability Cleared 1/28/2021 CELINA MORENO
Address approval Cleared 1/29/2021 CELINA MORENO
Eng Process Fee Ord 176,300 Cleared 1/29/2021 CELINA MORENO
Construction near power lines Cleared 5/18/2021 RIDWAN HARDY

Contact Information

Contractor Treeium Inc; Lic. No.: 617148-B 5352 LAUREL CANYON BLVD #200      VALLEY VILLAGE, CA 91607

Inspector Information

DAVID WILLIAMS, (213) 202-3126 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 6/22/2021 Approved CHRIS CHRISTENSEN
PLUMBING-Rough 6/22/2021 Partial Approval CHRIS CHRISTENSEN
Underground Mechanical 6/22/2021 Approved CHRIS CHRISTENSEN
BUILDING-Rough-Frame 7/22/2021 Not Ready for Inspection CHRISTOPHER DELLEFIELD
ELECTRICAL-Rough 7/22/2021 Corrections Issued CHRISTOPHER DELLEFIELD
Green Building Rough 7/22/2021 Not Ready for Inspection CHRISTOPHER DELLEFIELD
PLUMBING-Rough 7/22/2021 Approved CHRISTOPHER DELLEFIELD
Insulation 7/30/2021 Not Ready for Inspection JUSTIN HAWLEY
Interior/Exterior Lathing 7/30/2021 Not Ready for Inspection JUSTIN HAWLEY
Insulation 8/9/2021 Corrections Issued WILLIAM WREN
Interior/Exterior Lathing 8/9/2021 Approved WILLIAM WREN
Insulation 8/27/2021 Approved WILLIAM WREN
Drywall Nailing 9/9/2021 Corrections Issued ALAN MORELOS
Insulation 9/9/2021 Not Ready for Inspection ALAN MORELOS
Shower Pan 9/9/2021 Not Ready for Inspection ALAN MORELOS
Drywall Nailing 9/13/2021 Approved CALEB MEISTER
Interior/Exterior Lathing 9/13/2021 Approved CALEB MEISTER
Shower Pan 9/13/2021 Approved CALEB MEISTER
BUILDING-Rough-Frame 11/16/2021 Corrections Issued JOSE AVILA
Final 11/16/2021 Not Ready for Inspection JOSE AVILA
Green Building Final 11/16/2021 Corrections Issued JOSE AVILA
Green Building Rough 11/16/2021 Approved JOSE AVILA
SGSOV-Seismic Gas S/O Valve 11/16/2021 SGSOV Approved JOSE AVILA
Smoke Detectors 11/16/2021 Corrections Issued JOSE AVILA
BUILDING-Rough-Frame 12/17/2021 Corrections Issued JOSE AVILA
ELECTRICAL-Final 12/17/2021 Corrections Issued JOSE AVILA
Final 12/17/2021 Corrections Issued JOSE AVILA
Green Building Final 12/17/2021 Corrections Issued JOSE AVILA
HVAC-Final 12/17/2021 Approved JOSE AVILA
PLUMBING-Final 12/17/2021 Approved JOSE AVILA
Smoke Detectors 12/17/2021 Approved JOSE AVILA
BUILDING-Rough-Frame 1/19/2022 Approved JOSE AVILA
ELECTRICAL-Final 1/19/2022 Approved JOSE AVILA
PLUMBING-Final 1/19/2022 Approved JOSE AVILA
Final 2/8/2022 OK to Issue CofO JOSE AVILA
Green Building Final 2/8/2022 Approved JOSE AVILA