4600 E RICHELIEU TER 90032
Certificate Information: 4600 E RICHELIEU TER 90032
- Application / Permit
- 20016-20000-28944
- Plan Check / Job No.
- B20VN14574
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- INTERIOR REMODEL TO (E) SFD. CONVERT STORAGE ROOMS TO BATHROOM AND CLOSET. CONVERT DEN TO BEDROOM. REMODEL KITCHEN. WORK PER ENGINEER.
- Permit Issued
- Issued on 3/5/2021
- Issuing Office
- Metro
- Current Status
- CofO Issued on 3/14/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/9/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 11/16/2020 | ROSENDO MEDINA |
| Corrections Issued | 11/17/2020 | ROSENDO MEDINA |
| Plan Check Approved | 2/11/2021 | ROSENDO MEDINA |
| Issued | 3/5/2021 | APPLICANT |
| CofO in Progress | 3/10/2022 | COREY HUPP |
| CofO in Progress | 3/10/2022 | COREY HUPP |
| Permit Finaled | 3/14/2022 | DEROLD HAUFF |
| CofO Issued | 3/14/2022 | DEROLD HAUFF |
| Permit Finaled | 3/14/2022 | DEROLD HAUFF |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 12/17/2020 | ROSA SILVA |
| Sewer availability | Cleared | 12/17/2020 | ROSA SILVA |
| Grading Pre-Inspection | Cleared | 2/5/2021 | BARTON HOLMES |
Contact Information
| Contractor | Ahn'S Construction; Lic. No.: 1022756-B | 13330 BLOOMFIELD AVENUE SUITE 220 NORWALK, CA 90650 |
| Engineer | Singh,, Jasbir; Lic. No.: C38767 | 16194 EASTRIDGE CT CHINO HILLS, CA 91709 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 4/28/2021 | Conditional Approval | THOMAS LOGRASSO |
| Footing/Foundation/Slab | 5/4/2021 | Corrections Issued | OSVALDO PARAMO |
| PLUMBING-Rough | 5/4/2021 | Not Ready for Inspection | OSVALDO PARAMO |
| Wood Frame | 5/4/2021 | Not Ready for Inspection | OSVALDO PARAMO |
| Footing/Foundation/Slab | 5/10/2021 | Corrections Issued | COREY HUPP |
| Wood Frame | 5/10/2021 | Not Ready for Inspection | COREY HUPP |
| Footing/Foundation/Slab | 5/17/2021 | Corrections Issued | COREY HUPP |
| Footing/Foundation/Slab | 5/24/2021 | Approved | COREY HUPP |
| Wood Frame | 6/8/2021 | Not Ready for Inspection | CRAIG VAUGHAN |
| BUILDING-Rough-Frame | 6/22/2021 | Not Ready for Inspection | OSVALDO PARAMO |
| Rough-Elec/Plmb/HVAC | 6/22/2021 | Not Ready for Inspection | OSVALDO PARAMO |
| Drywall Nailing | 7/1/2021 | Not Ready for Inspection | COREY HUPP |
| Rough-Elec/Plmb/HVAC | 7/1/2021 | Corrections Issued | COREY HUPP |
| Wood Frame | 7/1/2021 | Not Ready for Inspection | COREY HUPP |
| BUILDING-Rough-Frame | 7/6/2021 | Not Ready for Inspection | OSVALDO PARAMO |
| Rough-Elec/Plmb/HVAC | 7/6/2021 | No Access for Inspection | OSVALDO PARAMO |
| BUILDING-Rough-Frame | 8/9/2021 | Corrections Issued | COREY HUPP |
| BUILDING-Rough-Frame | 8/11/2021 | Corrections Issued | COREY HUPP |
| BUILDING-Rough-Frame | 8/27/2021 | Partial Approval | SCOTT FINNILA |
| Wood Frame | 8/27/2021 | Partial Approval | SCOTT FINNILA |
| Interior/Exterior Lathing | 9/24/2021 | Not Ready for Inspection | COREY HUPP |
| Interior/Exterior Lathing | 9/30/2021 | Corrections Issued | ROBERT VORHIS |
| Shower Pan | 9/30/2021 | Corrections Issued | ROBERT VORHIS |
| Interior/Exterior Lathing | 10/6/2021 | Partial Inspection | RUBEN SALAS |
| Shower Pan | 10/6/2021 | Approved | COREY HUPP |
| Drywall Nailing | 10/19/2021 | Conditional Approval | COREY HUPP |
| Interior/Exterior Lathing | 10/22/2021 | Partial Approval | OSVALDO PARAMO |
| Interior/Exterior Lathing | 10/29/2021 | Approved | COREY HUPP |
| BUILDING-Rough-Frame | 1/24/2022 | Approved | OSVALDO PARAMO |
| Final | 1/24/2022 | Corrections Issued | OSVALDO PARAMO |
| SGSOV-Seismic Gas S/O Valve | 1/24/2022 | SGSOV Not Ready | OSVALDO PARAMO |
| Smoke Detectors | 1/24/2022 | Approved | OSVALDO PARAMO |
| Final | 2/24/2022 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| SGSOV-Seismic Gas S/O Valve | 2/24/2022 | SGSOV Not Ready | HAMIK HARTOUNIAN |
| Final | 3/4/2022 | Corrections Issued | COREY HUPP |
| SGSOV-Seismic Gas S/O Valve | 3/4/2022 | SGSOV Approved | COREY HUPP |
| Final | 3/10/2022 | OK to Issue CofO | COREY HUPP |