7100-7102 N HATILLO AVE 91306
Certificate Information: 7100-7102 N HATILLO AVE 91306
- Application / Permit
- 20016-20000-28816
- Plan Check / Job No.
- B20VN14538
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- CONVERT THE (E) GARAGE INTO A (N) ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) AND (e).
- Permit Issued
- Issued on 3/18/2021
- Issuing Office
- West Los Angeles
- Current Status
- CofO Issued on 2/14/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/9/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 11/16/2020 | LUIS RINCON |
| Corrections Issued | 11/18/2020 | LUIS RINCON |
| Applicant returned to address corrections | 1/4/2021 | LUIS RINCON |
| Applicant returned to address corrections | 2/23/2021 | LUIS RINCON |
| Plan Check Approved | 3/1/2021 | LUIS RINCON |
| Building Plans Picked Up | 3/3/2021 | APPLICANT |
| Issued | 3/18/2021 | APPLICANT |
| CofO in Progress | 2/10/2022 | STEVEN BACK |
| Permit Finaled | 2/14/2022 | JOHN JANSON |
| CofO Issued | 2/14/2022 | JOHN JANSON |
| Permit Finaled | 2/14/2022 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 12/9/2020 | MARKOS PEREZ-BRAN |
| Sewer availability | Cleared | 12/9/2020 | MARKOS PEREZ-BRAN |
| Eng Process Fee Ord 176,300 | Cleared | 12/11/2020 | MARKOS PEREZ-BRAN |
Contact Information
| Contractor | Trig Builders Inc; Lic. No.: 1030887-B | 6442 COLDWATER CANYON AVE 111 NORTH HOLLYWOOD, CA 91606 |
| Engineer | Sayah,, Daniel Hoshyar; Lic. No.: C67905 | 15233 VENTURA BLVD STE 1130 SHERMAN OAKS, CA 91403 |
Inspector Information
| ALEXANDER HANDY, (818) 774-4317 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 4/29/2021 | Partial Approval | HENRY KIM |
| Sewer | 4/29/2021 | Approved | HENRY KIM |
| Footing/Foundation/Slab | 5/3/2021 | Corrections Issued | HENRY KIM |
| Footing/Foundation/Slab | 5/10/2021 | Corrections Issued | HENRY KIM |
| Footing/Foundation/Slab | 5/14/2021 | Approved | HENRY KIM |
| BUILDING-Rough-Frame | 5/27/2021 | Corrections Issued | HENRY KIM |
| ELECTRICAL-Rough | 5/27/2021 | Corrections Issued | HENRY KIM |
| Floor/Roof Diaphrgm/Shear Wall | 5/27/2021 | Corrections Issued | HENRY KIM |
| HVAC-Rough | 5/27/2021 | Corrections Issued | HENRY KIM |
| PLUMBING-Rough | 5/27/2021 | Approved | HENRY KIM |
| BUILDING-Rough-Frame | 7/12/2021 | Partial Approval | HENRY KIM |
| HVAC-Rough | 7/12/2021 | Corrections Issued | HENRY KIM |
| BUILDING-Rough-Frame | 8/5/2021 | Corrections Issued | DAVID SANDOVAL |
| ELECTRICAL-Rough | 8/5/2021 | Approved | DAVID SANDOVAL |
| Green Building Rough | 8/5/2021 | Not Ready for Inspection | DAVID SANDOVAL |
| HVAC-Rough | 8/5/2021 | Not Ready for Inspection | DAVID SANDOVAL |
| Interior/Exterior Lathing | 8/23/2021 | Partial Approval | STEPHANIE SWANSON |
| BUILDING-Rough-Frame | 9/8/2021 | Corrections Issued | HENRY KIM |
| Green Building Rough | 9/8/2021 | Not Ready for Inspection | HENRY KIM |
| HVAC-Final | 9/8/2021 | Corrections Issued | HENRY KIM |
| HVAC-Rough | 9/8/2021 | Approved | HENRY KIM |
| Insulation | 9/8/2021 | Approved | HENRY KIM |
| HVAC-Rough | 9/10/2021 | Not Ready for Inspection | HENRY KIM |
| Insulation | 9/10/2021 | Not Ready for Inspection | HENRY KIM |
| Pre-Inspection | 9/10/2021 | Partial Inspection | KRISTEN CAUSEY |
| BUILDING-Rough-Frame | 9/20/2021 | Corrections Issued | HENRY KIM |
| Green Building Rough | 9/20/2021 | Not Ready for Inspection | HENRY KIM |
| BUILDING-Rough-Frame | 10/4/2021 | Approved | HENRY KIM |
| Drywall Nailing | 10/4/2021 | Approved | HENRY KIM |
| ELECTRICAL-Final | 10/4/2021 | Corrections Issued | HENRY KIM |
| Green Building Rough | 10/4/2021 | Approved | HENRY KIM |
| PLUMBING-Final | 10/4/2021 | Corrections Issued | HENRY KIM |
| Interior/Exterior Lathing | 10/29/2021 | Approved | JESUS PINEDA |
| Final | 12/16/2021 | Corrections Issued | STEVEN BACK |
| Green Building Final | 12/16/2021 | Approved | STEVEN BACK |
| SGSOV-Seismic Gas S/O Valve | 12/16/2021 | SGSOV Not Ready | STEVEN BACK |
| Smoke Detectors | 12/16/2021 | Not Ready for Inspection | STEVEN BACK |
| Final | 1/7/2022 | Corrections Issued | STEVEN BACK |
| SGSOV-Seismic Gas S/O Valve | 1/7/2022 | SGSOV Approved | STEVEN BACK |
| Smoke Detectors | 1/7/2022 | Not Ready for Inspection | STEVEN BACK |
| Final | 1/20/2022 | Corrections Issued | STEVEN BACK |
| Smoke Detectors | 1/20/2022 | Approved | STEVEN BACK |
| ELECTRICAL-Final | 2/10/2022 | Approved | STEVEN BACK |
| Final | 2/10/2022 | OK to Issue CofO | STEVEN BACK |
| HVAC-Final | 2/10/2022 | Approved | STEVEN BACK |
| PLUMBING-Final | 2/10/2022 | Approved | STEVEN BACK |