5137 1/2 N EAGLE ROCK BLVD 90041

Certificate Information: 5137 1/2 N EAGLE ROCK BLVD 90041

Application / Permit
20016-20000-28756
Plan Check / Job No.
B20VN14503
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT 17'-6" X 28' (E) DETACHED STORAGE INTO A (N) ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(D) AND LAMC 12.22 A.33(c)(d) AND (g). ALL WORK PER WFPP.
Permit Issued
Issued on 12/18/2020
Issuing Office
Current Status
CofO Issued on 5/8/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/6/2020 APPLICANT
Assigned to Plan Check Engineer 11/13/2020 RAPHAEL ROSAS
Corrections Issued 11/15/2020 RAPHAEL ROSAS
Issued 12/18/2020 APPLICANT
CofO in Progress 4/14/2021 CRAIG VAUGHAN
Permit Finaled 5/8/2021 DEROLD HAUFF
Permit Finaled 5/8/2021 DEROLD HAUFF
CofO Issued 5/8/2021 DEROLD HAUFF

Permit Application Clearance Information

Construction near power lines Cleared 12/3/2020 WALTER RAMIREZ
Address approval Cleared 12/9/2020 RENZ SORIANO
Eng Process Fee Ord 176,300 Cleared 12/9/2020 RENZ SORIANO
Sewer availability Cleared 12/9/2020 RENZ SORIANO

Contact Information

Contractor Owner-Builder       ,

Inspector Information

RONNIE MEDINA, (213) 469-5852 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 12/30/2020 Corrections Issued CRAIG VAUGHAN
BUILDING-Rough-Frame 2/9/2021 Partial Approval CRAIG VAUGHAN
ELECTRICAL-Rough 2/9/2021 Corrections Issued CRAIG VAUGHAN
Green Building Final 2/9/2021 Not Ready for Inspection CRAIG VAUGHAN
Green Building Rough 2/9/2021 Not Ready for Inspection CRAIG VAUGHAN
HVAC-Rough 2/9/2021 Corrections Issued CRAIG VAUGHAN
PLUMBING-Rough 2/9/2021 Corrections Issued CRAIG VAUGHAN
SGSOV-Seismic Gas S/O Valve 2/9/2021 SGSOV Not Ready CRAIG VAUGHAN
Smoke Detectors 2/9/2021 Corrections Issued CRAIG VAUGHAN
BUILDING-Rough-Frame 2/18/2021 Approved CRAIG VAUGHAN
ELECTRICAL-Rough 2/18/2021 Partial Approval CRAIG VAUGHAN
Green Building Rough 2/18/2021 Approved CRAIG VAUGHAN
HVAC-Rough 2/18/2021 Approved CRAIG VAUGHAN
PLUMBING-Rough 2/18/2021 Approved CRAIG VAUGHAN
Final 3/15/2021 Not Ready for Inspection BRIAN SULLIVAN
Green Building Final 3/15/2021 Not Ready for Inspection BRIAN SULLIVAN
SGSOV-Seismic Gas S/O Valve 3/15/2021 SGSOV Not Ready BRIAN SULLIVAN
Smoke Detectors 3/15/2021 Approved BRIAN SULLIVAN
PLUMBING-Final 3/16/2021 Corrections Issued CRAIG VAUGHAN
Final 3/24/2021 Not Ready for Inspection HAMIK HARTOUNIAN
Green Building Final 3/24/2021 Not Ready for Inspection HAMIK HARTOUNIAN
SGSOV-Seismic Gas S/O Valve 3/24/2021 SGSOV Not Ready HAMIK HARTOUNIAN
PLUMBING-Final 4/1/2021 Not Ready for Inspection HAMIK HARTOUNIAN
Drywall Nailing 4/13/2021 Approved CRAIG VAUGHAN
ELECTRICAL-Rough 4/13/2021 Approved CRAIG VAUGHAN
Final 4/13/2021 OK to Issue CofO CRAIG VAUGHAN
Footing/Foundation/Slab 4/13/2021 Approved CRAIG VAUGHAN
Green Building Final 4/13/2021 Approved CRAIG VAUGHAN
Insulation 4/13/2021 Approved CRAIG VAUGHAN
SGSOV-Seismic Gas S/O Valve 4/13/2021 SGSOV Approved CRAIG VAUGHAN