11540 W HESBY ST 91601

Certificate Information: 11540 W HESBY ST 91601

Application / Permit
20016-20000-28714
Plan Check / Job No.
B20VN14469
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) 20'3" X 18'2" DETACHED GARAGE TO ACCESSORY DWELLING UNIT AS PER LAMC12.22.A33(C) AND (E), NFPA-13D FIRE SPRINKLERS REQUIRED THROUGHOUT , ALL WORK PER ENGINEERING
Permit Issued
Issued on 9/8/2022
Issuing Office
Valley
Current Status
CofO Issued on 8/8/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/7/2020 APPLICANT
Assigned to Plan Check Engineer 12/3/2020 RARES BODEA
Corrections Issued 12/5/2020 RARES BODEA
Quality Review Completed 12/16/2020 STEVEN KIM
Building Plans Picked Up 12/16/2020 APPLICANT
Applicant returned to address corrections 2/14/2022 RARES BODEA
Applicant returned to address corrections 7/27/2022 RARES BODEA
Plan Check Approved 8/5/2022 RARES BODEA
Issued 9/8/2022 APPLICANT
CofO in Progress 7/10/2024 VINCENT HANLEY
Permit Finaled 8/8/2024 RUBEN SALAS
CofO Issued 8/8/2024 RUBEN SALAS
Permit Finaled 8/8/2024 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 2/1/2021 ABDULLAH SADOZAI
Eng Process Fee Ord 176,300 Cleared 2/1/2021 ABDULLAH SADOZAI
Roof/Waste drainage to street Cleared 2/1/2021 ABDULLAH SADOZAI
Sewer availability Cleared 2/1/2021 ABDULLAH SADOZAI
Specific Plan Cleared 2/16/2021 ERIN NASH
ZI Cleared 2/16/2021 ERIN NASH
ZI Cleared 2/16/2021 ERIN NASH

Contact Information

Contractor Savs Enterprises; Lic. No.: 814956-B 4500 SUNNYCREST DRIVE      LOS ANGELES, CA 90065
Engineer Avila,, Albert Guerrero; Lic. No.: C41726 10034 GLADE AVNENUE      CHATSWORTH, CA 91311

Inspector Information

JAVIER RAMOS JR, (818) 374-1163 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 11/18/2022 Corrections Issued JACK KARGODORIAN
Footing/Foundation/Slab 11/18/2022 Partial Approval JACK KARGODORIAN
Footing/Foundation/Slab 12/15/2022 Not Ready for Inspection JOHN COLEMAN
Footing/Foundation/Slab 12/20/2022 Approved JACK KARGODORIAN
Footing/Foundation/Slab 12/27/2022 Approved JACK KARGODORIAN
PLUMBING-Rough 12/27/2022 Partial Approval JACK KARGODORIAN
Floor/Roof Diaphrgm/Shear Wall 3/2/2023 Approved JACK KARGODORIAN
Underground Mechanical 4/6/2023 Not Ready for Inspection JACK KARGODORIAN
ELECTRICAL-Rough 5/25/2023 Corrections Issued THOMAS FINNILA
Interior/Exterior Lathing 5/25/2023 Not Ready for Inspection THOMAS FINNILA
ELECTRICAL-Rough 5/30/2023 Approved JACK KARGODORIAN
Interior/Exterior Lathing 5/30/2023 Partial Approval JACK KARGODORIAN
Wood Frame 6/2/2023 Approved JACK KARGODORIAN
Insulation 6/8/2023 Approved JACK KARGODORIAN
Drywall Nailing 6/23/2023 Not Ready for Inspection JACK KARGODORIAN
Drywall Nailing 7/3/2023 Approved THOMAS FINNILA
Shower Pan 7/28/2023 Approved CHRISTOPHE COCHRAN
Interior/Exterior Lathing 8/7/2023 Partial Approval JACK KARGODORIAN
BUILDING-Rough-Frame 6/20/2024 Approved CHRISTOPHER ROJAS
Final 6/20/2024 Corrections Issued CHRISTOPHER ROJAS
Green Building Final 6/20/2024 Not Ready for Inspection CHRISTOPHER ROJAS
Green Building Rough 6/20/2024 Approved CHRISTOPHER ROJAS
MERV13>=Final 6/20/2024 Not Ready for Inspection CHRISTOPHER ROJAS
MERV13>=Rough 6/20/2024 Approved CHRISTOPHER ROJAS
SGSOV-Seismic Gas S/O Valve 6/20/2024 SGSOV Approved CHRISTOPHER ROJAS
Smoke Detectors 6/20/2024 Approved CHRISTOPHER ROJAS
ELECTRICAL-Final 6/28/2024 Approved VINCENT HANLEY
Final 6/28/2024 OK to Issue CofO VINCENT HANLEY
Green Building Final 6/28/2024 Approved VINCENT HANLEY
HVAC-Final 6/28/2024 Approved VINCENT HANLEY
MERV13>=Final 6/28/2024 Approved VINCENT HANLEY
PLUMBING-Final 6/28/2024 Approved VINCENT HANLEY