22604-22606 W GILMORE ST 91307

Certificate Information: 22604-22606 W GILMORE ST 91307

Application / Permit
20016-20000-28713
Plan Check / Job No.
B20VN14470
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
CONVERT (E) 20' 9" X 20' ATTACHED 2-CAR GARAGE TO ADU. ALL WORK DONE PER WFPP.
Permit Issued
Issued on 2/11/2021
Issuing Office
Current Status
CofO Issued on 7/6/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/20/2020 APPLICANT
Assigned to Plan Check Engineer 11/24/2020 GURUNATH NESARAJAH
Corrections Issued 11/28/2020 GURUNATH NESARAJAH
Plan Check Approved 1/16/2021 GURUNATH NESARAJAH
Issued 2/11/2021 APPLICANT
CofO in Progress 5/20/2021 TROY SANDERS
Permit Finaled 7/6/2021 JOHN JANSON
CofO Issued 7/6/2021 JOHN JANSON
Permit Finaled 7/6/2021 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 12/17/2020 GABRIEL ROBLES
Sewer availability Cleared 12/17/2020 GABRIEL ROBLES
Eng Process Fee Ord 176,300 Cleared 12/21/2020 GABRIEL ROBLES

Contact Information

Contractor Dreamworks Builders; Lic. No.: 1052079-B 22647 VENTURA BLVE SUITE 586      WOODLAND HILLS, CA 91364

Inspector Information

GEVORK IPCHYAN, (818) 774-4308 Office Hours: 7:00-8:00 AM MON-FRI
TROY SANDERS, (818) 774-4308 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 2/12/2021 Approved TROY SANDERS
Deputy Drilled-In Anchors 2/17/2021 Partial Approval TROY SANDERS
BUILDING-Rough-Frame 3/2/2021 Approved TROY SANDERS
Floor/Roof Diaphrgm/Shear Wall 3/2/2021 Approved TROY SANDERS
Footing/Foundation/Slab 3/2/2021 Approved TROY SANDERS
Gas Test 3/2/2021 Approved TROY SANDERS
Green Building Rough 3/2/2021 Approved TROY SANDERS
Interior/Exterior Lathing 3/2/2021 Approved TROY SANDERS
Rough-Elec/Plmb/HVAC 3/2/2021 Approved TROY SANDERS
Sewer 3/2/2021 Approved TROY SANDERS
Wood Frame 3/2/2021 Approved TROY SANDERS
Insulation 3/5/2021 Approved TROY SANDERS
Interior/Exterior Lathing 3/5/2021 Approved TROY SANDERS
Shower Pan 3/5/2021 Approved TROY SANDERS
Interior/Exterior Lathing 3/9/2021 Approved TROY SANDERS
Drywall Nailing 3/18/2021 Approved TROY SANDERS
Final 5/4/2021 Corrections Issued TROY SANDERS
Green Building Final 5/4/2021 Corrections Issued TROY SANDERS
HVAC-Rough 5/4/2021 Approved TROY SANDERS
SGSOV-Seismic Gas S/O Valve 5/4/2021 SGSOV Approved TROY SANDERS
Smoke Detectors 5/4/2021 Approved TROY SANDERS
Final 5/20/2021 OK to Issue CofO TROY SANDERS
Green Building Final 5/20/2021 Approved TROY SANDERS