22604-22606 W GILMORE ST 91307
Certificate Information: 22604-22606 W GILMORE ST 91307
- Application / Permit
- 20016-20000-28713
- Plan Check / Job No.
- B20VN14470
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- CONVERT (E) 20' 9" X 20' ATTACHED 2-CAR GARAGE TO ADU. ALL WORK DONE PER WFPP.
- Permit Issued
- Issued on 2/11/2021
- Issuing Office
- Current Status
- CofO Issued on 7/6/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/20/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 11/24/2020 | GURUNATH NESARAJAH |
| Corrections Issued | 11/28/2020 | GURUNATH NESARAJAH |
| Plan Check Approved | 1/16/2021 | GURUNATH NESARAJAH |
| Issued | 2/11/2021 | APPLICANT |
| CofO in Progress | 5/20/2021 | TROY SANDERS |
| Permit Finaled | 7/6/2021 | JOHN JANSON |
| CofO Issued | 7/6/2021 | JOHN JANSON |
| Permit Finaled | 7/6/2021 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 12/17/2020 | GABRIEL ROBLES |
| Sewer availability | Cleared | 12/17/2020 | GABRIEL ROBLES |
| Eng Process Fee Ord 176,300 | Cleared | 12/21/2020 | GABRIEL ROBLES |
Contact Information
| Contractor | Dreamworks Builders; Lic. No.: 1052079-B | 22647 VENTURA BLVE SUITE 586 WOODLAND HILLS, CA 91364 |
Inspector Information
| GEVORK IPCHYAN, (818) 774-4308 | Office Hours: 7:00-8:00 AM MON-FRI |
| TROY SANDERS, (818) 774-4308 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 2/12/2021 | Approved | TROY SANDERS |
| Deputy Drilled-In Anchors | 2/17/2021 | Partial Approval | TROY SANDERS |
| BUILDING-Rough-Frame | 3/2/2021 | Approved | TROY SANDERS |
| Floor/Roof Diaphrgm/Shear Wall | 3/2/2021 | Approved | TROY SANDERS |
| Footing/Foundation/Slab | 3/2/2021 | Approved | TROY SANDERS |
| Gas Test | 3/2/2021 | Approved | TROY SANDERS |
| Green Building Rough | 3/2/2021 | Approved | TROY SANDERS |
| Interior/Exterior Lathing | 3/2/2021 | Approved | TROY SANDERS |
| Rough-Elec/Plmb/HVAC | 3/2/2021 | Approved | TROY SANDERS |
| Sewer | 3/2/2021 | Approved | TROY SANDERS |
| Wood Frame | 3/2/2021 | Approved | TROY SANDERS |
| Insulation | 3/5/2021 | Approved | TROY SANDERS |
| Interior/Exterior Lathing | 3/5/2021 | Approved | TROY SANDERS |
| Shower Pan | 3/5/2021 | Approved | TROY SANDERS |
| Interior/Exterior Lathing | 3/9/2021 | Approved | TROY SANDERS |
| Drywall Nailing | 3/18/2021 | Approved | TROY SANDERS |
| Final | 5/4/2021 | Corrections Issued | TROY SANDERS |
| Green Building Final | 5/4/2021 | Corrections Issued | TROY SANDERS |
| HVAC-Rough | 5/4/2021 | Approved | TROY SANDERS |
| SGSOV-Seismic Gas S/O Valve | 5/4/2021 | SGSOV Approved | TROY SANDERS |
| Smoke Detectors | 5/4/2021 | Approved | TROY SANDERS |
| Final | 5/20/2021 | OK to Issue CofO | TROY SANDERS |
| Green Building Final | 5/20/2021 | Approved | TROY SANDERS |