13558 W LOUVRE ST 91331

Certificate Information: 13558 W LOUVRE ST 91331

Application / Permit
20016-20000-28696
Plan Check / Job No.
B20VN14456
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) 20' X 20' DETACHED GARAGE TO ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(A). WORK PER WFPP.
Permit Issued
Issued on 2/3/2021
Issuing Office
Current Status
CofO Issued on 6/19/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/9/2020 APPLICANT
Assigned to Plan Check Engineer 11/16/2020 ROSENDO MEDINA
Corrections Issued 11/17/2020 ROSENDO MEDINA
Plan Check Approved 2/1/2021 ROSENDO MEDINA
Issued 2/3/2021 APPLICANT
CofO in Progress 4/8/2021 MICHEL ABAJAN
CofO Issued 6/19/2021 MICHAEL SMITH
Permit Finaled 6/19/2021 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 1/22/2021 ADRIAN CASTRO
Eng Process Fee Ord 176,300 Cleared 1/22/2021 ADRIAN CASTRO
Sewer availability Cleared 1/22/2021 ADRIAN CASTRO

Contact Information

Contractor Owner-Builder       ,

Inspector Information

MICHEL ABAJAN, (818) 374-9932 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 2/16/2021 Approved MICHEL ABAJAN
Footing/Foundation/Slab 2/16/2021 Approved MICHEL ABAJAN
ELECTRICAL-Rough 3/5/2021 Approved MICHEL ABAJAN
HVAC-Rough 3/5/2021 Approved MICHEL ABAJAN
PLUMBING-Rough 3/5/2021 Approved MICHEL ABAJAN
Wood Frame 3/5/2021 Approved MICHEL ABAJAN
Insulation 3/9/2021 Approved MICHEL ABAJAN
Interior/Exterior Lathing 3/9/2021 Approved MICHEL ABAJAN
Drywall Nailing 3/12/2021 Approved MICHEL ABAJAN
BUILDING-Rough-Frame 4/8/2021 Approved MICHEL ABAJAN
ELECTRICAL-Final 4/8/2021 Approved MICHEL ABAJAN
Final 4/8/2021 OK to Issue CofO MICHEL ABAJAN
Green Building Final 4/8/2021 Approved MICHEL ABAJAN
Green Building Rough 4/8/2021 Approved MICHEL ABAJAN
HVAC-Final 4/8/2021 Approved MICHEL ABAJAN
METHANE-Final 4/8/2021 Approved MICHEL ABAJAN
METHANE-Rough 4/8/2021 Approved MICHEL ABAJAN
PLUMBING-Final 4/8/2021 Approved MICHEL ABAJAN
SGSOV-Seismic Gas S/O Valve 4/8/2021 SGSOV Approved MICHEL ABAJAN
Smoke Detectors 4/8/2021 Approved MICHEL ABAJAN