5423 W HAROLD WAY 90027
Certificate Information: 5423 W HAROLD WAY 90027
- Application / Permit
- 20016-20000-28232
- Plan Check / Job No.
- B20VN14296
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- CONVERT EXISTING REC ROOM & PORTION OF EXISTING LAUNDRY ROOM WITHIN EXISTING 11 UNIT, 2 STORY APARTMENT BUILDING INTO ACCESSORY DWELLING UNIT PER ADM-2021-9153-ADU (Multiple ADUs per State Law, CA Govt. Code 65852.2(e)(1)(C))
- Permit Issued
- Issued on 6/21/2022
- Issuing Office
- Metro
- Current Status
- CofO Issued on 6/24/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/3/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 11/10/2020 | HAYATO TSUCHIYA |
| Corrections Issued | 11/11/2020 | HAYATO TSUCHIYA |
| Applicant returned to address corrections | 4/7/2021 | PETER MOSESIAN |
| Applicant returned to address corrections | 10/29/2021 | RACHEL BEYENE |
| Applicant returned to address corrections | 2/4/2022 | AUNG SOE |
| Plan Check Approved | 5/12/2022 | PETER MOSESIAN |
| Issued | 6/21/2022 | APPLICANT |
| Building Plans Picked Up | 8/23/2022 | APPLICANT |
| CofO in Progress | 6/20/2024 | ALFREDO LOPEZ |
| CofO Issued | 6/24/2024 | ERNESTO CORRAL |
| Permit Finaled | 6/24/2024 | ERNESTO CORRAL |
Permit Application Clearance Information
| Address approval | Cleared | 1/29/2021 | CECILIO NAVARRO |
| Sewer availability | Cleared | 1/29/2021 | CECILIO NAVARRO |
| "Q" conditions | Cleared | 8/18/2021 | DENZEL HENDERSON |
| ZI | Cleared | 8/18/2021 | DENZEL HENDERSON |
| Redevelopment Project Area | Cleared | 10/4/2021 | DAVID URITA |
| Eng Process Fee Ord 176,300 | Cleared | 10/19/2021 | CELINA MORENO |
| Specific Plan | Cleared | 11/5/2021 | DANALYNN DOMINGUEZ |
| Supp. Use District POD/CDO/TDO | Cleared | 11/16/2021 | MAXFIELD VERMY |
| Hydrant and Access approval | Cleared | 11/30/2021 | GILBERT URREA |
| Fire Marshal Fire Life Safety | Cleared | 1/11/2022 | MENOA AGHAJANI |
Contact Information
| Contractor | Ben Porat Moshe M; Lic. No.: 963181-B | P O BOX 48603 LOS ANGELES, CA 90048 |
| Engineer | Standley,, Craig Erick; Lic. No.: C87675 | 5330 ZELZAH AVE UNIT 7 ENCINO, CA 91316 |
Inspector Information
| TIMOTHY POWELL, (213) 482-0360 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Green Building Rough | 11/9/2022 | Not Ready for Inspection | JONATHAN QUACH |
| Insulation | 11/9/2022 | Not Ready for Inspection | JONATHAN QUACH |
| Wood Frame | 11/9/2022 | Not Ready for Inspection | JONATHAN QUACH |
| Green Building Rough | 11/15/2022 | Approved | ALAN MORELOS |
| Insulation | 11/15/2022 | Approved | ALAN MORELOS |
| Wood Frame | 11/15/2022 | Partial Inspection | ALAN MORELOS |
| Drywall Nailing | 11/29/2022 | Approved | MARK FERRARI |
| Interior/Exterior Lathing | 11/29/2022 | Approved | MARK FERRARI |
| Final | 1/24/2023 | Conditional Approval | ALFREDO LOPEZ |
| Green Building Final | 1/24/2023 | Approved | ALFREDO LOPEZ |
| SGSOV-Seismic Gas S/O Valve | 1/24/2023 | SGSOV Not Ready | ALFREDO LOPEZ |
| Smoke Detectors | 1/24/2023 | Approved | ALFREDO LOPEZ |
| Wood Frame | 1/24/2023 | Approved | ALFREDO LOPEZ |
| Final | 6/20/2024 | OK to Issue CofO | ALFREDO LOPEZ |
| SGSOV-Seismic Gas S/O Valve | 6/20/2024 | SGSOV Approved | ALFREDO LOPEZ |