14342 W COHASSET ST 91405

Certificate Information: 14342 W COHASSET ST 91405

Application / Permit
20016-20000-27886
Plan Check / Job No.
B20VN14168
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT 20' X 30' (E) DETACHED GARAGE AND STORAGE INTO A (N) ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) AND (d). ALL WORK PER WFPP. "COMPLY WITH DEPARTMENT ORDER effective date 09/13/2020. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE"
Permit Issued
Issued on 4/19/2022
Issuing Office
Current Status
CofO Issued on 11/15/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/16/2020 APPLICANT
Assigned to Plan Check Engineer 11/23/2020 RAPHAEL ROSAS
Corrections Issued 11/23/2020 RAPHAEL ROSAS
Applicant returned to address corrections 4/3/2022 RAPHAEL ROSAS
Issued 4/19/2022 APPLICANT
Building Plans Picked Up 4/21/2022 APPLICANT
CofO in Progress 8/15/2024 SCOTT SHUSTER
Permit Finaled 11/15/2024 DAVID JAMES
CofO Issued 11/15/2024 DAVID JAMES
Permit Finaled 11/15/2024 DAVID JAMES

Permit Application Clearance Information

Address approval Cleared 12/4/2020 ADRIAN CASTRO
Sewer availability Cleared 12/4/2020 ADRIAN CASTRO
Eng Process Fee Ord 176,300 Cleared 6/3/2021 ADRIAN CASTRO

Contact Information

Contractor Owner-Builder       ,
Engineer Khatchadourian,, Vicken; Lic. No.: S3141 1221 N CEDAR ST      GLENDALE, CA 92107

Inspector Information

ARA SINANIAN, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
HASANTHA WEERASEKARA, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
SCOTT SHUSTER, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
JOEL GUARDADO, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
MARIYA MIHALEVA, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
JOSE RUBIO, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
DAVID JAMES, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
DAVID HICKMAN, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
JOHN HAMILTON, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
JOHN STEPHENS, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
PIERRE VEGA, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
MARK VAN SLOOTEN, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
MICKEY YAMASHITA, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
RICHARD ROBLES, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
HAGOP BADOSSIAN, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
KIM BEAUCHAMP, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
MARK DOVICO, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
THOMAS WOODS, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
RAUL VASQUEZ, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
AUGUSTUS ALBAS, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
FELIPE PENICHE, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
LEO MILBAUER, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 1/30/2023 Corrections Issued BRYAN MEYER
Deputy Drilled-In Anchors 2/17/2023 Conditional Approval BRYAN MEYER
Footing/Foundation/Slab 2/17/2023 Corrections Issued KIM BEAUCHAMP
Deputy Drilled-In Anchors 2/24/2023 Conditional Approval KIM BEAUCHAMP
Footing/Foundation/Slab 2/28/2023 Partial Approval BRYAN MEYER
Deputy Drilled-In Anchors 3/7/2023 Conditional Approval BRYAN MEYER
Footing/Foundation/Slab 3/28/2023 Approved BRYAN MEYER
ELECTRICAL-Rough 4/18/2023 Approved BRYAN MEYER
HVAC-Rough 4/18/2023 Not Ready for Inspection BRYAN MEYER
PLUMBING-Rough 4/18/2023 Approved BRYAN MEYER
HVAC-Rough 6/13/2023 Partial Inspection BRYAN MEYER
Interior/Exterior Lathing 6/13/2023 Not Ready for Inspection BRYAN MEYER
HVAC-Rough 6/26/2023 Approved BRYAN MEYER
Interior/Exterior Lathing 7/11/2023 Partial Approval BRYAN MEYER
BUILDING-Rough-Frame 7/21/2023 Partial Inspection SCOTT SHUSTER
Green Building Rough 7/21/2023 Partial Approval SCOTT SHUSTER
Shower Pan 7/21/2023 Approved SCOTT SHUSTER
BUILDING-Rough-Frame 7/27/2023 Approved BRYAN MEYER
Green Building Rough 7/27/2023 Approved BRYAN MEYER
Insulation 7/27/2023 Approved BRYAN MEYER
Drywall Nailing 8/1/2023 Approved BRYAN MEYER
Interior/Exterior Lathing 8/1/2023 Not Ready for Inspection BRYAN MEYER
Shower Pan 8/7/2023 Partial Inspection BRYAN MEYER
Interior/Exterior Lathing 8/14/2023 Approved BRYAN MEYER
Final 10/23/2023 Partial Inspection BRYAN MEYER
Green Building Final 10/23/2023 Approved BRYAN MEYER
SGSOV-Seismic Gas S/O Valve 10/23/2023 SGSOV Not Ready BRYAN MEYER
Smoke Detectors 10/23/2023 Approved BRYAN MEYER
Final 11/8/2023 Conditional Approval BRYAN MEYER
SGSOV-Seismic Gas S/O Valve 11/8/2023 SGSOV Approved BRYAN MEYER
Final 3/20/2024 Conditional Approval BRYAN MEYER
Final 8/15/2024 OK to Issue CofO SCOTT SHUSTER