109 N FORMOSA AVE 90036
Certificate Information: 109 N FORMOSA AVE 90036
- Application / Permit
- 20016-20000-27876
- Plan Check / Job No.
- B20VN14165
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- REMOVE 7' 6" X 19' PORTION OF DETACHED GARAGE AND CONVERT GARAGE TO ADU. ALL WORK DONE PER STRUCTURAL ENGINEERING.
- Permit Issued
- Issued on 3/9/2021
- Issuing Office
- Current Status
- CofO Issued on 3/9/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/29/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 11/6/2020 | GURUNATH NESARAJAH |
| Corrections Issued | 11/7/2020 | GURUNATH NESARAJAH |
| Plan Check Approved | 3/9/2021 | GURUNATH NESARAJAH |
| Issued | 3/9/2021 | APPLICANT |
| Building Plans Picked Up | 3/10/2021 | APPLICANT |
| CofO in Progress | 3/1/2023 | MICHAEL LEWIS |
| Permit Finaled | 3/9/2023 | DEROLD HAUFF |
| CofO Issued | 3/9/2023 | DEROLD HAUFF |
| Permit Finaled | 3/9/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| CPC | Cleared | 11/10/2020 | STEVEN WECHSLER |
| CPC | Cleared | 11/10/2020 | STEVEN WECHSLER |
| HPOZ | Cleared | 11/16/2020 | DANIEL MATA |
| Miscellaneous | Cleared | 11/16/2020 | DANIEL MATA |
| Miscellaneous | Cleared | 11/16/2020 | DANIEL MATA |
| Miscellaneous | Cleared | 11/16/2020 | DANIEL MATA |
| Miscellaneous | Cleared | 11/16/2020 | DANIEL MATA |
| Miscellaneous | Cleared | 11/16/2020 | DANIEL MATA |
| Address approval | Cleared | 11/19/2020 | JEANIE LAM |
| Sewer availability | Cleared | 11/19/2020 | JEANIE LAM |
| Eng Process Fee Ord 176,300 | Cleared | 11/20/2020 | JEANIE LAM |
| Construction near power lines | Cleared | 1/24/2021 | RIDWAN HARDY |
| Construction within easement | Cleared | 1/24/2021 | RIDWAN HARDY |
Contact Information
| Architect | Dembsky,, Amit; Lic. No.: C30383 | 5739 KANAN ROAD # 133 AGOURA HILLS, CA 91301 |
| Contractor | Butel Construction Inc; Lic. No.: 852273-B | 257 SOUTH CITRUS AVE LOS ANGELES, CA 90036 |
Inspector Information
| JOSE MACIAS, (213) 202-3125 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 4/9/2021 | Approved | CHRIS CHRISTENSEN |
| Footing/Foundation/Slab | 4/30/2021 | Partial Approval | CHRIS CHRISTENSEN |
| Pre-Inspection | 4/30/2021 | Off-Hour Fees Due | |
| Footing/Foundation/Slab | 5/4/2021 | Approved | CHRIS CHRISTENSEN |
| ELECTRICAL-Rough | 5/27/2021 | Corrections Issued | CHRIS CHRISTENSEN |
| Floor/Roof Diaphrgm/Shear Wall | 5/27/2021 | Partial Approval | CHRIS CHRISTENSEN |
| HVAC-Rough | 5/27/2021 | Approved | CHRIS CHRISTENSEN |
| PLUMBING-Rough | 5/27/2021 | Approved | CHRIS CHRISTENSEN |
| Wood Frame | 5/27/2021 | Partial Approval | CHRIS CHRISTENSEN |
| BUILDING-Rough-Frame | 6/10/2021 | Partial Approval | CHRIS CHRISTENSEN |
| ELECTRICAL-Rough | 6/10/2021 | Approved | CHRIS CHRISTENSEN |
| BUILDING-Rough-Frame | 6/25/2021 | Approved | CHRIS CHRISTENSEN |
| Floor/Roof Diaphrgm/Shear Wall | 6/25/2021 | Approved | CHRIS CHRISTENSEN |
| Green Building Rough | 6/25/2021 | Approved | CHRIS CHRISTENSEN |
| Insulation | 6/25/2021 | Approved | CHRIS CHRISTENSEN |
| Interior/Exterior Lathing | 6/25/2021 | Partial Approval | CHRIS CHRISTENSEN |
| METHANE-Rough | 6/25/2021 | Approved | CHRIS CHRISTENSEN |
| Wood Frame | 6/25/2021 | Approved | CHRIS CHRISTENSEN |
| Drywall Nailing | 7/2/2021 | Approved | BENEVA JACKSON |
| ELECTRICAL-Final | 11/22/2021 | Corrections Issued | CHRIS CHRISTENSEN |
| Final | 11/22/2021 | Corrections Issued | CHRIS CHRISTENSEN |
| Green Building Final | 11/22/2021 | Corrections Issued | CHRIS CHRISTENSEN |
| HVAC-Final | 11/22/2021 | Approved | CHRIS CHRISTENSEN |
| PLUMBING-Final | 11/22/2021 | Approved | CHRIS CHRISTENSEN |
| SGSOV-Seismic Gas S/O Valve | 11/22/2021 | SGSOV Approved | CHRIS CHRISTENSEN |
| Smoke Detectors | 11/22/2021 | Approved | CHRIS CHRISTENSEN |
| ELECTRICAL-Final | 11/24/2021 | Off-Hour Fees Due | |
| Final | 11/24/2021 | Off-Hour Fees Due | |
| Green Building Final | 11/24/2021 | Off-Hour Fees Due | |
| HVAC-Final | 11/24/2021 | Off-Hour Fees Due | |
| PLUMBING-Final | 11/24/2021 | Off-Hour Fees Due | |
| ELECTRICAL-Final | 11/30/2021 | Approved | CHRIS CHRISTENSEN |
| Green Building Final | 11/30/2021 | Approved | CHRIS CHRISTENSEN |
| HVAC-Final | 11/30/2021 | Approved | CHRIS CHRISTENSEN |
| PLUMBING-Final | 11/30/2021 | Approved | CHRIS CHRISTENSEN |
| Special/Order Compliance | 8/18/2022 | Approved | MICHAEL LEWIS |
| Final | 8/25/2022 | Corrections Issued | MICHAEL LEWIS |
| Final | 2/28/2023 | OK to Issue CofO | MICHAEL LEWIS |