4620 N TILDEN AVE 117 91423

Certificate Information: 4620 N TILDEN AVE 117 91423

Application / Permit
20016-20000-27812
Plan Check / Job No.
B20VN14150
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
CONVERT (E) 27' X 16' IRR.-SHAPE ATTACHED 2-STORY RECREATION ROOM & LAUNDRY ROOM TO ADU PER GCS 65852.2(e)(1)(C). NO STRUCTURAL CHANGES TO BE MADE.
Permit Issued
Issued on 5/24/2021
Issuing Office
Current Status
CofO Issued on 7/16/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/29/2020 APPLICANT
Assigned to Plan Check Engineer 11/6/2020 GURUNATH NESARAJAH
Corrections Issued 11/8/2020 GURUNATH NESARAJAH
Plan Check Approved 4/2/2021 GURUNATH NESARAJAH
Issued 5/24/2021 APPLICANT
CofO in Progress 7/15/2024 STEVEN LEVITT
CofO in Progress 7/16/2024 STEVEN LEVITT
CofO in Progress 7/16/2024 STEVEN LEVITT
CofO Issued 7/16/2024 JEFFREY DURAN
Permit Finaled 7/16/2024 JEFFREY DURAN

Permit Application Clearance Information

ZI Cleared 12/9/2020 LAUREN PADICK
Sewer availability Cleared 12/17/2020 GABRIEL ROBLES
Eng Process Fee Ord 176,300 Cleared 12/18/2020 GABRIEL ROBLES
Fire Marshal Fire Life Safety Cleared 2/26/2021 OSCAR SALGADO JR
Address approval Cleared 3/9/2021 ADRIAN CASTRO

Contact Information

Contractor Owner-Builder       ,

Inspector Information

SEAN GRIFFITH, (818) 374-1102 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 6/17/2021 Corrections Issued ANDREW DORSO
Drywall Nailing 9/2/2021 Approved CAMERON CHABAN
Final 9/2/2021 Not Ready for Inspection CAMERON CHABAN
Green Building Final 9/2/2021 Not Ready for Inspection CAMERON CHABAN
Green Building Rough 9/2/2021 Approved CAMERON CHABAN
SGSOV-Seismic Gas S/O Valve 9/2/2021 SGSOV Approved CAMERON CHABAN
Smoke Detectors 9/2/2021 Not Ready for Inspection CAMERON CHABAN
Wood Frame 9/2/2021 Approved CAMERON CHABAN
Final 10/5/2021 Not Ready for Inspection ROBERT DAVIS
Green Building Final 10/5/2021 Approved ROBERT DAVIS
Smoke Detectors 10/5/2021 Approved ROBERT DAVIS
Special/Order Compliance 10/7/2021 Corrections Issued ROBERT DAVIS
Final 6/3/2024 Not Ready for Inspection STEVEN LEVITT
Final 6/10/2024 Not Ready for Inspection STEVEN LEVITT
Final 6/13/2024 OK to Issue CofO STEVEN LEVITT