13645 PINNEY ST 91331
Certificate Information: 13645 PINNEY ST 91331
- Application / Permit
- 20016-20000-27628
- Plan Check / Job No.
- B20VN14031
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT THE 10' x 20' GARAGE TO AN ACCESSORY DWELLING UNIT (ADU) PER LAMC 12.22 A.33(c) AND (d) ADDITION OF 10' x 20' TO THE ADU AND 15.5' x 16.5" PATIO COVER.
- Permit Issued
- Issued on 6/9/2022
- Issuing Office
- Current Status
- CofO Issued on 3/18/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/27/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 11/2/2020 | LUIS RINCON |
| Corrections Issued | 11/4/2020 | LUIS RINCON |
| Applicant returned to address corrections | 4/1/2022 | LUIS RINCON |
| Building Plans Picked Up | 5/20/2022 | APPLICANT |
| Plan Check Approved | 6/2/2022 | LUIS RINCON |
| Issued | 6/9/2022 | APPLICANT |
| CofO in Progress | 12/15/2023 | MICHEL ABAJAN |
| Permit Finaled | 3/18/2024 | RUBEN SALAS |
| CofO Issued | 3/18/2024 | RUBEN SALAS |
| Permit Finaled | 3/18/2024 | RUBEN SALAS |
Permit Application Clearance Information
| Construction near power lines | Cleared | 3/31/2021 | RIDWAN HARDY |
| Address approval | Cleared | 6/15/2021 | DAGOVERTO GUERRERO |
| Clean Up Green Up | Cleared | 6/15/2021 | MIGUEL GAMBOA |
| Sewer availability | Cleared | 6/15/2021 | DAGOVERTO GUERRERO |
| Eng Process Fee Ord 176,300 | Cleared | 6/16/2021 | DAGOVERTO GUERRERO |
| Hydrant and Access approval | Cleared | 2/17/2022 | JOHN CONNEALLY |
| Low Impact Development | Cleared | 3/7/2022 | TA ANH |
| Roof/Waste drainage to street | Cleared | 3/18/2022 | JOSE DUARTE-DIAZ |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Espino,, Manuel A; Lic. No.: C55526 | 12109 WOODRUFF AVE DOWNEY, CA 90241 |
Inspector Information
| MICHEL ABAJAN, (818) 374-9932 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 7/12/2022 | Approved | MICHEL ABAJAN |
| Footing/Foundation/Slab | 7/18/2022 | Corrections Issued | MICHEL ABAJAN |
| METHANE-Barrier | 7/18/2022 | Approved | MICHEL ABAJAN |
| METHANE-Subgrade | 7/18/2022 | Approved | MICHEL ABAJAN |
| Footing/Foundation/Slab | 7/29/2022 | Approved | MICHEL ABAJAN |
| Deputy Drilled-In Anchors | 9/14/2022 | Approved | MICHEL ABAJAN |
| Sewer | 9/21/2022 | No Access for Inspection | MICHEL ABAJAN |
| Wood Frame | 9/21/2022 | No Access for Inspection | MICHEL ABAJAN |
| Floor/Roof Diaphrgm/Shear Wall | 9/22/2022 | Not Ready for Inspection | MICHEL ABAJAN |
| Sewer | 9/22/2022 | Not Ready for Inspection | MICHEL ABAJAN |
| Sewer | 9/27/2022 | Not Ready for Inspection | MICHEL ABAJAN |
| Wood Frame | 9/27/2022 | Partial Inspection | MICHEL ABAJAN |
| Floor/Roof Diaphrgm/Shear Wall | 12/12/2022 | Partial Approval | MICHEL ABAJAN |
| Green Building Rough | 12/12/2022 | Not Ready for Inspection | MICHEL ABAJAN |
| METHANE-Rough | 12/12/2022 | Approved | MICHEL ABAJAN |
| PLUMBING-Rough | 12/12/2022 | Approved | MICHEL ABAJAN |
| Underground Mechanical | 3/3/2023 | Approved | MICHEL ABAJAN |
| ELECTRICAL-Rough | 4/14/2023 | Approved | MICHEL ABAJAN |
| HVAC-Rough | 4/14/2023 | Not Ready for Inspection | MICHEL ABAJAN |
| HVAC-Rough | 5/11/2023 | Approved | MATTHEW NELSON |
| Wood Frame | 5/11/2023 | Approved | MATTHEW NELSON |
| Interior/Exterior Lathing | 5/25/2023 | Approved | MICHEL ABAJAN |
| Insulation | 6/2/2023 | Approved | MICHEL ABAJAN |
| Drywall Nailing | 6/26/2023 | Approved | MICHEL ABAJAN |
| Green Building Rough | 6/26/2023 | Approved | MICHEL ABAJAN |
| BUILDING-Rough-Frame | 10/5/2023 | Approved | MICHEL ABAJAN |
| ELECTRICAL-Final | 10/5/2023 | Approved | MICHEL ABAJAN |
| Final | 10/5/2023 | Corrections Issued | MICHEL ABAJAN |
| Green Building Final | 10/5/2023 | Approved | MICHEL ABAJAN |
| HVAC-Final | 10/5/2023 | Approved | MICHEL ABAJAN |
| PLUMBING-Final | 10/5/2023 | Approved | MICHEL ABAJAN |
| SGSOV-Seismic Gas S/O Valve | 10/5/2023 | SGSOV Approved | MICHEL ABAJAN |
| Smoke Detectors | 10/5/2023 | Approved | MICHEL ABAJAN |
| Final | 11/17/2023 | Corrections Issued | MICHEL ABAJAN |
| Final | 12/15/2023 | OK to Issue CofO | MICHEL ABAJAN |