6041 N SIMPSON AVE 91606
Certificate Information: 6041 N SIMPSON AVE 91606
- Application / Permit
- 20016-20000-27545
- Plan Check / Job No.
- B20VN13997
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- DEMO EXISTING FRONT PORCH AND CONSTRUCT IRR SHAPED ADDN (11'X5') OF FOYER/ENTRY. DEMO HALLWAY WALLS PER PLAN TO ENLARGE EX LIVING RM & KITCHEN. ENLARGE & REMODEL EX BATHRM. REMODEL KITCHEN. ALL WORK PER ENGR DESIGN.
- Permit Issued
- Issued on 12/22/2020
- Issuing Office
- Current Status
- CofO Issued on 5/21/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/27/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 11/4/2020 | HAYATO TSUCHIYA |
| Corrections Issued | 11/5/2020 | HAYATO TSUCHIYA |
| Plan Check Approved | 12/17/2020 | HAYATO TSUCHIYA |
| Issued | 12/22/2020 | APPLICANT |
| CofO in Progress | 4/21/2022 | JACK KARGODORIAN |
| CofO Issued | 5/21/2022 | MICHAEL SMITH |
| Permit Finaled | 5/21/2022 | MICHAEL SMITH |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 11/18/2020 | GUILLERMO PETRA |
| Eng Process Fee Ord 176,300 | Cleared | 11/24/2020 | GUILLERMO PETRA |
Contact Information
| Architect | Dembsky,, Amit; Lic. No.: C30383 | 5739 KANAN ROAD # 133 AGOURA HILLS, CA 91301 |
| Contractor | N A Designs Inc; Lic. No.: 996566-B | 4821 LANKERSHIM BLVD F488 NORTH HOLLYWOOD, CA 91601 |
Inspector Information
| GAREN HAYRAPETYAN, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
| ROBERTO PALACIOS-LOPEZ, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 1/29/2021 | Approved | DANIEL DREW |
| Wood Frame | 2/16/2021 | Approved | DANIEL DREW |
| ELECTRICAL-Rough | 3/24/2021 | Approved | DANIEL DREW |
| HVAC-Rough | 3/24/2021 | Approved | DANIEL DREW |
| PLUMBING-Rough | 3/24/2021 | Approved | DANIEL DREW |
| Shower Pan | 4/12/2021 | Approved | DANIEL DREW |
| Insulation | 4/23/2021 | Approved | DANIEL DREW |
| Interior/Exterior Lathing | 4/23/2021 | Approved | DANIEL DREW |
| Drywall Nailing | 5/11/2021 | Approved | JOHN HAYES |
| Green Building Rough | 5/11/2021 | Approved | JOHN HAYES |
| Interior/Exterior Lathing | 5/11/2021 | Approved | JOHN HAYES |
| BUILDING-Rough-Frame | 4/14/2022 | Approved | CHRISTOPHE COCHRAN |
| Final | 4/14/2022 | Corrections Issued | CHRISTOPHE COCHRAN |
| Green Building Final | 4/14/2022 | Approved | CHRISTOPHE COCHRAN |
| Smoke Detectors | 4/14/2022 | Approved | CHRISTOPHE COCHRAN |
| Final | 4/21/2022 | OK to Issue CofO | JACK KARGODORIAN |