114 S ROSSMORE AVE 90004
Certificate Information: 114 S ROSSMORE AVE 90004
- Application / Permit
- 20016-20000-27121
- Plan Check / Job No.
- B20VN13845
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- INTERIOR REMODEL TO THE (E) KITCHEN, CONVERT TWO BACK ROOMS INTO A (N) FIRST FLOOR FAMILY ROOM AND DEN. RELOCATE THE BATHROOM, REMODEL THE BALCONY; INTERIOR REMODEL
- Permit Issued
- Issued on 12/11/2020
- Issuing Office
- Current Status
- Permit Finaled on 10/29/2021
Permit Application Status History
| Submitted | 10/26/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 11/5/2020 | SELLA BENYAMIN |
| Corrections Issued | 11/10/2020 | SELLA BENYAMIN |
| Building Plans Picked Up | 11/12/2020 | APPLICANT |
| Issued | 12/11/2020 | APPLICANT |
| Permit Finaled | 10/28/2021 | ARTHUR SARGSYAN |
Permit Application Clearance Information
| HPOZ | Cleared | 11/25/2020 | SUKI GERSHENHORN |
Contact Information
| Contractor | Concept Renovations Inc; Lic. No.: 1016942-B | 15928 VENTURA BLVD 225 ENCINO, CA 91436 |
| Engineer | Barakat,, Fouad Chafic; Lic. No.: C67449 | 8916 LONGDON AVE #C TEMPLE CITY, CA 91780 |
Inspector Information
| RONNIE MINDANAO, (213) 202-3252 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| BUILDING-Rough-Frame | 1/29/2021 | Partial Inspection | JOSEPH MCGARRY |
| Footing/Foundation/Slab | 1/29/2021 | Conditional Approval | JOSEPH MCGARRY |
| BUILDING-Rough-Frame | 2/17/2021 | Conditional Approval | JOSEPH MCGARRY |
| ELECTRICAL-Rough | 2/17/2021 | Approved | JOSEPH MCGARRY |
| HVAC-Rough | 2/17/2021 | Approved | JOSEPH MCGARRY |
| PLUMBING-Rough | 2/17/2021 | Approved | JOSEPH MCGARRY |
| Underground Mechanical | 2/17/2021 | Partial Approval | JOSEPH MCGARRY |
| Wood Frame | 2/17/2021 | Conditional Approval | JOSEPH MCGARRY |
| Deputy Wood Construction | 3/3/2021 | Approved | JOSEPH MCGARRY |
| Insulation | 3/3/2021 | Approved | JOSEPH MCGARRY |
| Interior/Exterior Lathing | 3/3/2021 | Partial Approval | JOSEPH MCGARRY |
| Shower Pan | 3/3/2021 | Approved | JOSEPH MCGARRY |
| Wood Frame | 3/3/2021 | Conditional Approval | JOSEPH MCGARRY |
| Drywall Nailing | 3/15/2021 | Approved | JOSEPH MCGARRY |
| Interior/Exterior Lathing | 6/24/2021 | Approved | BENEVA JACKSON |
| Final | 10/28/2021 | Permit Finaled | ARTHUR SARGSYAN |
| SGSOV-Seismic Gas S/O Valve | 10/28/2021 | SGSOV Approved | ARTHUR SARGSYAN |
| Smoke Detectors | 10/28/2021 | Approved | ARTHUR SARGSYAN |