11524 W HUSTON ST 91601
Certificate Information: 11524 W HUSTON ST 91601
- Application / Permit
- 20016-20000-27078
- Plan Check / Job No.
- B20VN13821
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (23) Recreation Room
- Work Description
- CONVERT 5'-1" X 8'-6" PORTION OF (E) REC ROOM TO POOL BATHROOM (EXTERIOR ACCESS ONLY). ALL WORK PER WFPP.
- Permit Issued
- Issued on 2/1/2021
- Issuing Office
- Current Status
- Permit Finaled on 7/14/2021
Permit Application Status History
| Submitted | 10/22/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 11/2/2020 | RARES BODEA |
| Corrections Issued | 11/4/2020 | RARES BODEA |
| Applicant returned to address corrections | 12/10/2020 | ALFRED RAMIREZ |
| Applicant returned to address corrections | 12/11/2020 | ALFRED RAMIREZ |
| Plan Check Approved | 1/12/2021 | RAPHAEL ROSAS |
| Issued | 2/1/2021 | APPLICANT |
| Permit Finaled | 7/14/2021 | THOMAS FINNILA |
Permit Application Clearance Information
| Specific Plan | Cleared | 11/19/2020 | MIGUEL GAMBOA |
| ZI | Cleared | 11/19/2020 | MIGUEL GAMBOA |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JAVIER RAMOS JR, (818) 374-1163 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 3/15/2021 | Conditional Approval | THOMAS FINNILA |
| Footing/Foundation/Slab | 3/17/2021 | Corrections Issued | THOMAS FINNILA |
| PLUMBING-Rough | 4/6/2021 | Partial Approval | MATTHEW NELSON |
| Deputy Drilled-In Anchors | 4/13/2021 | Conditional Approval | THOMAS FINNILA |
| Deputy Drilled-In Anchors | 4/14/2021 | Conditional Approval | THOMAS FINNILA |
| Deputy Wood Construction | 4/14/2021 | Conditional Approval | THOMAS FINNILA |
| BUILDING-Rough-Frame | 4/21/2021 | Conditional Approval | THOMAS FINNILA |
| ELECTRICAL-Rough | 4/21/2021 | Approved | THOMAS FINNILA |
| MERV13>=Rough | 4/21/2021 | Approved | THOMAS FINNILA |
| Drywall Nailing | 4/30/2021 | Approved | ARTHUR SARGSYAN |
| Insulation | 4/30/2021 | Approved | ARTHUR SARGSYAN |
| Pre-Inspection | 5/17/2021 | Approved | THOMAS FINNILA |
| BUILDING-Rough-Frame | 7/14/2021 | Approved | THOMAS FINNILA |
| Final | 7/14/2021 | Permit Finaled | THOMAS FINNILA |
| MERV13>=Final | 7/14/2021 | Approved | THOMAS FINNILA |
| SGSOV-Seismic Gas S/O Valve | 7/14/2021 | SGSOV Approved | THOMAS FINNILA |
| Smoke Detectors | 7/14/2021 | Approved | THOMAS FINNILA |