12115 W VENTURA BLVD 91604
Certificate Information: 12115 W VENTURA BLVD 91604
- Application / Permit
- 20016-20000-26987
- Plan Check / Job No.
- B20VN13785
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (16) Retail
- Work Description
- NONSTRUCT INT T.I. OF EXISTING RETAIL SUITE. (1,898SF)
- Permit Issued
- Issued on 2/25/2021
- Issuing Office
- Current Status
- Permit Finaled on 4/7/2021
Permit Application Status History
| Submitted | 10/21/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 10/22/2020 | HAYATO TSUCHIYA |
| Corrections Issued | 10/24/2020 | HAYATO TSUCHIYA |
| Quality Review Completed | 10/27/2020 | STEVEN KIM |
| Building Plans Picked Up | 10/28/2020 | APPLICANT |
| Disabled Access Plans Picked Up | 11/5/2020 | APPLICANT |
| Plan Check Approved | 12/11/2020 | HAYATO TSUCHIYA |
| Issued | 2/25/2021 | APPLICANT |
| Permit Finaled | 4/5/2021 | ROBERT DAVIS |
Permit Application Clearance Information
| Miscellaneous | Cleared | 11/10/2020 | DANG NGUYEN |
| Miscellaneous | Cleared | 11/10/2020 | DANG NGUYEN |
| Miscellaneous | Cleared | 11/10/2020 | DANG NGUYEN |
| Miscellaneous | Cleared | 11/10/2020 | DANG NGUYEN |
| Miscellaneous | Cleared | 11/10/2020 | DANG NGUYEN |
| Miscellaneous | Cleared | 11/10/2020 | DANG NGUYEN |
| Miscellaneous | Cleared | 11/10/2020 | DANG NGUYEN |
| Miscellaneous | Cleared | 11/10/2020 | DANG NGUYEN |
| ZA Case | Cleared | 11/10/2020 | DANG NGUYEN |
| ZA Case | Cleared | 11/10/2020 | DANG NGUYEN |
| ZA Case | Cleared | 11/10/2020 | DANG NGUYEN |
| ZA Case | Cleared | 11/10/2020 | DANG NGUYEN |
| DAS Clearance | Cleared | 12/11/2020 | HAYATO TSUCHIYA |
Contact Information
| Architect | Vanney,, Robert Francis; Lic. No.: C22242 | 401 MT. CURVE BLVD. ST PAUL, MN 55105 |
| Contractor | J C O R Inc; Lic. No.: 872762-B | P O BOX 26864 OVERLAND PARK, KS 66225 |
Inspector Information
| JEFFREY FULTON, (818) 374-1132 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Light Gage Steel Frame | 3/1/2021 | Conditional Approval | ROBERT DAVIS |
| Excavation/Setback/Form/Re-Bar | 3/10/2021 | Approved | ROBERT DAVIS |
| Footing/Foundation/Slab | 3/10/2021 | Approved | ROBERT DAVIS |
| Drywall Nailing | 3/12/2021 | Conditional Approval | ROBERT DAVIS |
| T-Bar Ceiling | 3/23/2021 | Conditional Approval | ROBERT DAVIS |
| Final | 4/5/2021 | Permit Finaled | ROBERT DAVIS |
| SGSOV-Seismic Gas S/O Valve | 4/5/2021 | SGSOV No Gas | ROBERT DAVIS |
| Smoke Detectors | 4/5/2021 | Approved | ROBERT DAVIS |
| Wood Frame | 4/5/2021 | Approved | ROBERT DAVIS |