10924 N PASO ROBLES AVE 91344

Certificate Information: 10924 N PASO ROBLES AVE 91344

Application / Permit
20016-20000-26814
Plan Check / Job No.
B20VN13703
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT THE (E) 2-CAR DETACHED GARAGE INTO A (N) ACCESSORY DWELLING UNIT PER GCS 65852.2 (e)(1)(A) PER LA STD WFPP
Permit Issued
Issued on 4/29/2021
Issuing Office
Current Status
CofO Issued on 11/18/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/21/2020 APPLICANT
Assigned to Plan Check Engineer 11/2/2020 TROY DEGUZMAN
Corrections Issued 11/2/2020 TROY DEGUZMAN
Plan Check Approved 1/20/2021 ANGELICA MARTINEZ
Issued 4/29/2021 APPLICANT
CofO in Progress 11/16/2022 DAVID SCANTLIN
Permit Finaled 11/18/2022 JOHN JANSON
CofO Issued 11/18/2022 JOHN JANSON
Permit Finaled 11/18/2022 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 1/11/2021 ADRIAN CASTRO
Sewer availability Cleared 1/11/2021 ADRIAN CASTRO
Eng Process Fee Ord 176,300 Cleared 1/13/2021 ADRIAN CASTRO

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JEFFREY PARD, (818) 774-4312 Office Hours: 7:00-8:00 AM MON-FRI
STEVEN BACK, (818) 774-4312 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 10/6/2021 Partial Approval DAVID SCANTLIN
ELECTRICAL-Rough 10/25/2021 Partial Approval DAVID SCANTLIN
Floor/Roof Diaphrgm/Shear Wall 10/25/2021 Partial Approval DAVID SCANTLIN
Floor/Roof Diaphrgm/Shear Wall 11/4/2021 Partial Approval DAVID SCANTLIN
Footing/Foundation/Slab 11/4/2021 Approved DAVID SCANTLIN
BUILDING-Rough-Frame 11/9/2021 Approved DAVID SCANTLIN
Rough-Elec/Plmb/HVAC 11/9/2021 Approved DAVID SCANTLIN
Drywall Nailing 11/17/2021 Approved DAVID SCANTLIN
Interior/Exterior Lathing 11/17/2021 Approved DAVID SCANTLIN
BUILDING-Rough-Frame 7/5/2022 Approved JEFFREY PARD
Final 7/5/2022 Corrections Issued JEFFREY PARD
Green Building Final 7/5/2022 Corrections Issued JEFFREY PARD
Green Building Rough 7/5/2022 Approved JEFFREY PARD
SGSOV-Seismic Gas S/O Valve 7/5/2022 SGSOV Approved JEFFREY PARD
Smoke Detectors 7/5/2022 Approved JEFFREY PARD
ELECTRICAL-Final 7/18/2022 Approved DAVID SCANTLIN
Final 7/18/2022 Partial Approval DAVID SCANTLIN
Green Building Final 7/18/2022 Approved DAVID SCANTLIN
HVAC-Final 7/18/2022 Approved DAVID SCANTLIN
PLUMBING-Final 7/18/2022 Approved DAVID SCANTLIN
Final 11/16/2022 OK to Issue CofO DAVID SCANTLIN