17558 W DEVONSHIRE ST 91325

Certificate Information: 17558 W DEVONSHIRE ST 91325

Application / Permit
20016-20000-26787
Plan Check / Job No.
B20VN13687
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) DETACHED GARAGE TO ACCESSORY DWELLING UNIT (427 SQ FT)
Permit Issued
Issued on 2/9/2021
Issuing Office
Current Status
CofO Issued on 11/18/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/20/2020 APPLICANT
Assigned to Plan Check Engineer 10/29/2020 JEROME MAGAT PALMA
Corrections Issued 11/1/2020 JEROME MAGAT PALMA
Plan Check Approved 12/7/2020 JEROME MAGAT PALMA
Issued 2/9/2021 APPLICANT
CofO in Progress 11/15/2024 ROBERT GOLD
Permit Finaled 11/18/2024 DANIEL ORRANTE
CofO Issued 11/18/2024 DANIEL ORRANTE
Permit Finaled 11/18/2024 DANIEL ORRANTE

Permit Application Clearance Information

Address approval Cleared 11/20/2020 ADRIAN CASTRO
Eng Process Fee Ord 176,300 Cleared 11/20/2020 ADRIAN CASTRO
Sewer availability Cleared 11/20/2020 ADRIAN CASTRO

Contact Information

Contractor Owner-Builder       ,

Inspector Information

CHRISTOPHER ROJAS, (818) 374-1160 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 2/17/2021 Corrections Issued MARK JOHNSON
Wood Frame 2/17/2021 Corrections Issued MARK JOHNSON
PLUMBING-Rough 2/25/2021 Not Ready for Inspection MARK JOHNSON
Underground Mechanical 2/25/2021 Partial Approval MARK JOHNSON
Wood Frame 2/25/2021 Partial Approval MARK JOHNSON
ELECTRICAL-Rough 3/3/2021 Approved MARK JOHNSON
HVAC-Rough 3/3/2021 Approved MARK JOHNSON
PLUMBING-Rough 3/3/2021 Approved MARK JOHNSON
Wood Frame 3/3/2021 Not Ready for Inspection MARK JOHNSON
Insulation 3/9/2021 Partial Approval MARK JOHNSON
Shower Pan 3/9/2021 Approved MARK JOHNSON
BUILDING-Rough-Frame 3/16/2021 Partial Approval MARK JOHNSON
Drywall Nailing 3/16/2021 Approved MARK JOHNSON
Green Building Rough 3/16/2021 Approved MARK JOHNSON
Interior/Exterior Lathing 1/18/2022 Corrections Issued JESUS RODRIGUEZ
Final 8/30/2024 Corrections Issued JAVIER RAMOS JR
BUILDING-Rough-Frame 9/9/2024 Approved JENNIFER RABUCHIN
Final 9/9/2024 Corrections Issued JENNIFER RABUCHIN
Green Building Final 9/9/2024 Corrections Issued JENNIFER RABUCHIN
SGSOV-Seismic Gas S/O Valve 9/9/2024 SGSOV Not Ready JENNIFER RABUCHIN
Smoke Detectors 9/9/2024 Approved JENNIFER RABUCHIN
Final 9/17/2024 OK to Issue CofO JAVIER RAMOS JR
Green Building Final 9/17/2024 Approved JAVIER RAMOS JR
SGSOV-Seismic Gas S/O Valve 9/17/2024 SGSOV Approved JAVIER RAMOS JR