16717 S FIGUEROA ST 90248

Certificate Information: 16717 S FIGUEROA ST 90248

Application / Permit
20016-20000-26652
Plan Check / Job No.
B20VN13631
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Commercial
Primary Use
(17) Restaurant
Work Description
PROPOSED FIRE DAMAGE REPAIR WITHIN EX KITCHEN/FOOD PREP AREA. REMODEL EX ONE UNISEX RESTRM FOR HANDICAP ACCESSIBILITY COMPLIANCE. ENLARGE EXISTING EXTERIOR OPENING FOR NEW DOOR. ONE NEW ROOF TOP EQUIPMENT. AND RESTRIPING OF PARKING STALLS. SEE COMMENTS.
Permit Issued
Issued on 11/8/2021
Issuing Office
Current Status
CofO Issued on 11/17/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/19/2020 APPLICANT
Disabled Access Plans Picked Up 11/6/2020 APPLICANT
Assigned to Plan Check Engineer 11/12/2020 HAYATO TSUCHIYA
Corrections Issued 11/14/2020 HAYATO TSUCHIYA
Quality Review Completed 11/18/2020 STEVEN KIM
Applicant returned to address corrections 2/23/2021 HAYATO TSUCHIYA
Applicant returned to address corrections 5/10/2021 HAYATO TSUCHIYA
Applicant returned to address corrections 7/23/2021 HAYATO TSUCHIYA
Plan Check Approved 9/24/2021 HAYATO TSUCHIYA
Building Plans Picked Up 9/27/2021 APPLICANT
Issued 11/8/2021 APPLICANT
CofO in Progress 11/15/2022 JOEY BUCHANAN
CofO Issued 11/17/2022 DAVID TSAU
Permit Finaled 11/17/2022 DAVID TSAU

Permit Application Clearance Information

DAS Clearance Cleared 3/11/2021 HAYATO TSUCHIYA
Food Service Establishment Cleared 9/24/2021 PAWAN VERMA
Food establishment approval Cleared 9/24/2021 LACDHS APPROVED

Contact Information

Contractor Macco Construction Inc; Lic. No.: 793557-B 4833 SAN MARCOS PLACE      LOS ANGELES, CA 90042
Engineer Reith,, David Lee; Lic. No.: C72122 1319 FEATHER AVE      THOUSAND OAKS, CA 91360

Inspector Information

MICHAEL PETRUSKO, (310) 732-4552 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 2/25/2022 Partial Approval DAVID TSAU
Deputy Drilled-In Anchors 3/7/2022 Approved JOEY BUCHANAN
Excavation/Setback/Form/Re-Bar 3/15/2022 Approved JOEY BUCHANAN
Floor/Roof Diaphrgm/Shear Wall 3/15/2022 Partial Inspection JOEY BUCHANAN
Wood Frame 3/30/2022 Partial Approval JOEY BUCHANAN
Insulation 4/1/2022 Approved JOEY BUCHANAN
Drywall Nailing 4/4/2022 Approved JOEY BUCHANAN
Interior/Exterior Lathing 5/4/2022 Approved JOEY BUCHANAN
Final 9/6/2022 Not Ready for Inspection DAVID TSAU
SGSOV-Seismic Gas S/O Valve 9/6/2022 SGSOV Not Ready DAVID TSAU
Smoke Detectors 9/6/2022 Approved DAVID TSAU
Wood Frame 9/6/2022 Approved DAVID TSAU
Final 9/28/2022 Corrections Issued JOEY BUCHANAN
SGSOV-Seismic Gas S/O Valve 9/28/2022 SGSOV Approved JOEY BUCHANAN
Final 11/10/2022 Conditional Approval JOEY BUCHANAN