8029 N IRONDALE AVE 91306

Certificate Information: 8029 N IRONDALE AVE 91306

Application / Permit
20016-20000-26609
Plan Check / Job No.
B20VN13618
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT EX DETACHED GARAGE INTO ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) AND (d). ALL WORK PER ENGINEERING.
Permit Issued
Issued on 11/30/2020
Issuing Office
Current Status
CofO Issued on 4/22/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/19/2020 APPLICANT
Assigned to Plan Check Engineer 10/29/2020 HAYATO TSUCHIYA
Corrections Issued 11/24/2020 HAYATO TSUCHIYA
Issued 11/30/2020 APPLICANT
CofO in Progress 4/21/2021 HENRY KIM
Permit Finaled 4/22/2021 JOHN JANSON
CofO Issued 4/22/2021 JOHN JANSON
Permit Finaled 4/22/2021 JOHN JANSON

Permit Application Clearance Information

Construction near power lines Cleared 11/5/2020 WALTER RAMIREZ
Construction within easement Cleared 11/5/2020 WALTER RAMIREZ
Address approval Cleared 11/17/2020 JOHN TRIANTAFYLLOS
Eng Process Fee Ord 176,300 Cleared 11/17/2020 JOHN TRIANTAFYLLOS
Permit Cleared 11/17/2020 JOHN TRIANTAFYLLOS
Sewer availability Cleared 11/17/2020 JOHN TRIANTAFYLLOS

Contact Information

Contractor Golan Remodeling Inc; Lic. No.: 868800-B 20723 CHASE STREET      WINNETKA, CA 91306
Engineer Barakat,, Fouad Chafic; Lic. No.: C67449 8916 LONGDON AVE #C      TEMPLE CITY, CA 91780

Inspector Information

DAVID FASTIGGI, (818) 774-4317 Office Hours: 7:00-8:00 AM MON-FRI
ALEXANDER HANDY, (818) 774-4317 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

ELECTRICAL-Rough 12/21/2020 Not Ready for Inspection TROY SANDERS
Footing/Foundation/Slab 12/21/2020 Approved TROY SANDERS
HVAC-Rough 12/21/2020 Not Ready for Inspection TROY SANDERS
PLUMBING-Rough 12/21/2020 Partial Approval TROY SANDERS
BUILDING-Rough-Frame 12/28/2020 Not Ready for Inspection HENRY KIM
ELECTRICAL-Rough 12/28/2020 Not Ready for Inspection HENRY KIM
Floor/Roof Diaphrgm/Shear Wall 12/28/2020 Not Ready for Inspection HENRY KIM
Green Building Rough 12/28/2020 Not Ready for Inspection HENRY KIM
BUILDING-Rough-Frame 12/31/2020 Corrections Issued HENRY KIM
ELECTRICAL-Rough 12/31/2020 Corrections Issued HENRY KIM
HVAC-Rough 12/31/2020 Corrections Issued HENRY KIM
PLUMBING-Rough 12/31/2020 Approved HENRY KIM
BUILDING-Rough-Frame 1/8/2021 Corrections Issued HENRY KIM
ELECTRICAL-Rough 1/8/2021 Approved HENRY KIM
Floor/Roof Diaphrgm/Shear Wall 1/8/2021 Approved HENRY KIM
Green Building Rough 1/8/2021 Not Ready for Inspection HENRY KIM
HVAC-Rough 1/8/2021 Approved HENRY KIM
BUILDING-Rough-Frame 1/13/2021 Approved HENRY KIM
Green Building Rough 1/13/2021 Approved HENRY KIM
Insulation 1/13/2021 Approved HENRY KIM
Interior/Exterior Lathing 1/13/2021 Approved HENRY KIM
Drywall Nailing 1/19/2021 Approved CHRISTOPHER DELLEFIELD
Interior/Exterior Lathing 1/27/2021 Approved HENRY KIM
Shower Pan 1/27/2021 Approved HENRY KIM
Green Building Final 2/1/2021 Partial Approval HENRY KIM
ELECTRICAL-Final 3/18/2021 Corrections Issued HENRY KIM
Final 3/18/2021 Corrections Issued HENRY KIM
Gas Test 3/18/2021 Approved HENRY KIM
Green Building Final 3/18/2021 Approved HENRY KIM
HVAC-Final 3/18/2021 Corrections Issued HENRY KIM
PLUMBING-Final 3/18/2021 Corrections Issued HENRY KIM
SGSOV-Seismic Gas S/O Valve 3/18/2021 SGSOV Not Ready HENRY KIM
Smoke Detectors 3/18/2021 Approved HENRY KIM
ELECTRICAL-Final 4/8/2021 Approved HENRY KIM
Final 4/8/2021 Not Ready for Inspection HENRY KIM
HVAC-Final 4/8/2021 Corrections Issued HENRY KIM
PLUMBING-Final 4/8/2021 Approved HENRY KIM
SGSOV-Seismic Gas S/O Valve 4/8/2021 SGSOV Approved HENRY KIM
Final 4/21/2021 OK to Issue CofO HENRY KIM
HVAC-Final 4/21/2021 Approved HENRY KIM