15753-15755 W LEMARSH ST 91343
Certificate Information: 15753-15755 W LEMARSH ST 91343
- Application / Permit
- 20016-20000-26390
- Plan Check / Job No.
- B20VN13510
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- CONVERT (E) ATTACHED GARAGE TO JUNIOR ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(A) AND 65852.22
- Permit Issued
- Issued on 1/15/2021
- Issuing Office
- Current Status
- CofO Issued on 2/5/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/15/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 10/28/2020 | ROSENDO MEDINA |
| Corrections Issued | 10/31/2020 | ROSENDO MEDINA |
| Plan Check Approved | 12/26/2020 | ROSENDO MEDINA |
| Issued | 1/15/2021 | APPLICANT |
| CofO in Progress | 7/13/2021 | JENNIFER RABUCHIN |
| No Progress | 12/11/2021 | MICHAEL SMITH |
| CofO in Progress | 2/5/2022 | MICHAEL TEMPLE |
| Permit Finaled | 2/5/2022 | MICHAEL SMITH |
| CofO Issued | 2/5/2022 | MICHAEL SMITH |
| Permit Finaled | 2/5/2022 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 12/7/2020 | ABDULLAH SADOZAI |
| Eng Process Fee Ord 176,300 | Cleared | 12/7/2020 | ABDULLAH SADOZAI |
| Sewer availability | Cleared | 12/7/2020 | ABDULLAH SADOZAI |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| CHRISTOPHER ROJAS, (818) 374-1160 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 2/10/2021 | Partial Approval | MARK JOHNSON |
| Footing/Foundation/Slab | 3/18/2021 | Partial Approval | MARK JOHNSON |
| ELECTRICAL-Rough | 4/5/2021 | Partial Approval | MARK JOHNSON |
| PLUMBING-Final | 4/5/2021 | Not Ready for Inspection | MARK JOHNSON |
| Wood Frame | 4/5/2021 | Partial Approval | MARK JOHNSON |
| BUILDING-Rough-Frame | 4/13/2021 | Approved | MARK JOHNSON |
| ELECTRICAL-Rough | 4/13/2021 | Approved | MARK JOHNSON |
| Green Building Rough | 4/13/2021 | Approved | MARK JOHNSON |
| HVAC-Rough | 4/13/2021 | Approved | MARK JOHNSON |
| MERV13>=Rough | 4/13/2021 | Approved | MARK JOHNSON |
| PLUMBING-Rough | 4/13/2021 | Approved | MARK JOHNSON |
| Insulation | 4/19/2021 | Approved | MARK JOHNSON |
| Interior/Exterior Lathing | 4/19/2021 | Approved | MARK JOHNSON |
| Drywall Nailing | 4/26/2021 | Approved | MARK JOHNSON |
| Shower Pan | 4/26/2021 | Not Ready for Inspection | MARK JOHNSON |
| Wood Frame | 4/30/2021 | Not Ready for Inspection | MARK JOHNSON |
| Shower Pan | 5/10/2021 | Approved | MARK JOHNSON |
| Final | 6/17/2021 | Corrections Issued | MICHAEL TEMPLE |
| Green Building Final | 6/17/2021 | Approved | MICHAEL TEMPLE |
| SGSOV-Seismic Gas S/O Valve | 6/17/2021 | SGSOV Approved | MICHAEL TEMPLE |
| Smoke Detectors | 6/17/2021 | Approved | MICHAEL TEMPLE |
| Final | 7/8/2021 | Partial Approval | JENNIFER RABUCHIN |
| ELECTRICAL-Final | 7/14/2021 | Approved | JENNIFER RABUCHIN |
| Final | 7/14/2021 | OK to Issue CofO | JENNIFER RABUCHIN |
| HVAC-Final | 7/14/2021 | Approved | JENNIFER RABUCHIN |
| PLUMBING-Final | 7/14/2021 | Approved | JENNIFER RABUCHIN |
| Special/Order Compliance | 12/15/2021 | Corrections Issued | JENNIFER RABUCHIN |