17933 W DUNCAN ST 91316
Certificate Information: 17933 W DUNCAN ST 91316
- Application / Permit
- 20016-20000-26372
- Plan Check / Job No.
- B20VN13493
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) DETACHED GARAGE TO ACCESSORY DWELLING UNIT (323 SQ FT)
- Permit Issued
- Issued on 12/23/2020
- Issuing Office
- Current Status
- CofO Issued on 4/13/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/15/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 10/28/2020 | ROSENDO MEDINA |
| Corrections Issued | 10/31/2020 | ROSENDO MEDINA |
| Plan Check Approved | 12/23/2020 | JEROME MAGAT PALMA |
| Issued | 12/23/2020 | APPLICANT |
| CofO in Progress | 4/12/2021 | VINCENT HANLEY |
| Permit Finaled | 4/13/2021 | JOHN JANSON |
| CofO Issued | 4/13/2021 | JOHN JANSON |
| Permit Finaled | 4/13/2021 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 11/13/2020 | JOHN TRIANTAFYLLOS |
| Sewer availability | Cleared | 11/13/2020 | JOHN TRIANTAFYLLOS |
| Eng Process Fee Ord 176,300 | Cleared | 11/16/2020 | JOHN TRIANTAFYLLOS |
| Construction near power lines | Cleared | 12/13/2020 | RIDWAN HARDY |
Contact Information
| Contractor | Mnm Remodeling Inc; Lic. No.: 1003511-B | 6200 CANOGA AVE SUITE 207 WOODLAND HILLS, CA 91367 |
Inspector Information
| ARUTYUN MADATYAN, (818) 774-4307 | Office Hours: 7:00-8:00 AM MON-FRI |
| JUAN ALVARADO, (818) 774-4307 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Sewer | 1/13/2021 | Approved | VINCENT HANLEY |
| Underground Mechanical | 1/13/2021 | Partial Approval | VINCENT HANLEY |
| Underground Mechanical | 1/15/2021 | Corrections Issued | VINCENT HANLEY |
| Footing/Foundation/Slab | 1/21/2021 | Approved | VINCENT HANLEY |
| BUILDING-Rough-Frame | 2/2/2021 | Not Ready for Inspection | VINCENT HANLEY |
| ELECTRICAL-Rough | 2/2/2021 | Approved | VINCENT HANLEY |
| Green Building Rough | 2/2/2021 | Approved | VINCENT HANLEY |
| HVAC-Rough | 2/2/2021 | Approved | VINCENT HANLEY |
| PLUMBING-Rough | 2/2/2021 | Approved | VINCENT HANLEY |
| Insulation | 2/4/2021 | Approved | VINCENT HANLEY |
| Shower Pan | 2/4/2021 | Approved | VINCENT HANLEY |
| Drywall Nailing | 2/10/2021 | Approved | VINCENT HANLEY |
| Interior/Exterior Lathing | 2/10/2021 | Approved | VINCENT HANLEY |
| BUILDING-Rough-Frame | 3/30/2021 | Approved | VINCENT HANLEY |
| ELECTRICAL-Final | 3/30/2021 | Approved | VINCENT HANLEY |
| Final | 3/30/2021 | Corrections Issued | VINCENT HANLEY |
| Green Building Final | 3/30/2021 | Approved | VINCENT HANLEY |
| HVAC-Final | 3/30/2021 | Approved | VINCENT HANLEY |
| PLUMBING-Final | 3/30/2021 | Approved | VINCENT HANLEY |
| SGSOV-Seismic Gas S/O Valve | 3/30/2021 | SGSOV Approved | VINCENT HANLEY |
| Smoke Detectors | 3/30/2021 | Approved | VINCENT HANLEY |
| ELECTRICAL-Final | 4/5/2021 | Corrections Issued | VINCENT HANLEY |
| Final | 4/5/2021 | Not Ready for Inspection | VINCENT HANLEY |
| HVAC-Final | 4/5/2021 | Approved | VINCENT HANLEY |
| PLUMBING-Final | 4/5/2021 | Approved | VINCENT HANLEY |
| Final | 4/12/2021 | OK to Issue CofO | VINCENT HANLEY |