17933 W DUNCAN ST 91316

Certificate Information: 17933 W DUNCAN ST 91316

Application / Permit
20016-20000-26372
Plan Check / Job No.
B20VN13493
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) DETACHED GARAGE TO ACCESSORY DWELLING UNIT (323 SQ FT)
Permit Issued
Issued on 12/23/2020
Issuing Office
Current Status
CofO Issued on 4/13/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/15/2020 APPLICANT
Assigned to Plan Check Engineer 10/28/2020 ROSENDO MEDINA
Corrections Issued 10/31/2020 ROSENDO MEDINA
Plan Check Approved 12/23/2020 JEROME MAGAT PALMA
Issued 12/23/2020 APPLICANT
CofO in Progress 4/12/2021 VINCENT HANLEY
Permit Finaled 4/13/2021 JOHN JANSON
CofO Issued 4/13/2021 JOHN JANSON
Permit Finaled 4/13/2021 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 11/13/2020 JOHN TRIANTAFYLLOS
Sewer availability Cleared 11/13/2020 JOHN TRIANTAFYLLOS
Eng Process Fee Ord 176,300 Cleared 11/16/2020 JOHN TRIANTAFYLLOS
Construction near power lines Cleared 12/13/2020 RIDWAN HARDY

Contact Information

Contractor Mnm Remodeling Inc; Lic. No.: 1003511-B 6200 CANOGA AVE SUITE 207      WOODLAND HILLS, CA 91367

Inspector Information

ARUTYUN MADATYAN, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI
JUAN ALVARADO, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Sewer 1/13/2021 Approved VINCENT HANLEY
Underground Mechanical 1/13/2021 Partial Approval VINCENT HANLEY
Underground Mechanical 1/15/2021 Corrections Issued VINCENT HANLEY
Footing/Foundation/Slab 1/21/2021 Approved VINCENT HANLEY
BUILDING-Rough-Frame 2/2/2021 Not Ready for Inspection VINCENT HANLEY
ELECTRICAL-Rough 2/2/2021 Approved VINCENT HANLEY
Green Building Rough 2/2/2021 Approved VINCENT HANLEY
HVAC-Rough 2/2/2021 Approved VINCENT HANLEY
PLUMBING-Rough 2/2/2021 Approved VINCENT HANLEY
Insulation 2/4/2021 Approved VINCENT HANLEY
Shower Pan 2/4/2021 Approved VINCENT HANLEY
Drywall Nailing 2/10/2021 Approved VINCENT HANLEY
Interior/Exterior Lathing 2/10/2021 Approved VINCENT HANLEY
BUILDING-Rough-Frame 3/30/2021 Approved VINCENT HANLEY
ELECTRICAL-Final 3/30/2021 Approved VINCENT HANLEY
Final 3/30/2021 Corrections Issued VINCENT HANLEY
Green Building Final 3/30/2021 Approved VINCENT HANLEY
HVAC-Final 3/30/2021 Approved VINCENT HANLEY
PLUMBING-Final 3/30/2021 Approved VINCENT HANLEY
SGSOV-Seismic Gas S/O Valve 3/30/2021 SGSOV Approved VINCENT HANLEY
Smoke Detectors 3/30/2021 Approved VINCENT HANLEY
ELECTRICAL-Final 4/5/2021 Corrections Issued VINCENT HANLEY
Final 4/5/2021 Not Ready for Inspection VINCENT HANLEY
HVAC-Final 4/5/2021 Approved VINCENT HANLEY
PLUMBING-Final 4/5/2021 Approved VINCENT HANLEY
Final 4/12/2021 OK to Issue CofO VINCENT HANLEY