10669 N EL DORADO AVE 91331

Certificate Information: 10669 N EL DORADO AVE 91331

Application / Permit
20016-20000-26321
Plan Check / Job No.
B20VN13470
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT THE RECREATION ROOM AND STORAGE TO AN IRREGULAR 20' x 44'9" ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33 (c) AND (d).
Permit Issued
Issued on 6/8/2022
Issuing Office
Valley
Current Status
CofO Issued on 4/27/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/28/2020 APPLICANT
Assigned to Plan Check Engineer 11/5/2020 LUIS RINCON
Corrections Issued 11/9/2020 LUIS RINCON
Applicant returned to address corrections 8/24/2021 LUIS RINCON
Applicant returned to address corrections 9/20/2021 LUISANGEL VALENZUELA
Applicant returned to address corrections 3/27/2022 LUIS RINCON
Plan Check Approved 4/3/2022 LUIS RINCON
No Progress 4/4/2022 LUIS RINCON
Plan Check Approved 4/20/2022 LUIS RINCON
Building Plans Picked Up 4/22/2022 APPLICANT
Issued 6/8/2022 APPLICANT
CofO in Progress 4/27/2023 MICHEL ABAJAN
CofO Issued 4/27/2023 MICHAEL SMITH
Permit Finaled 4/27/2023 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 9/24/2021 DAGOVERTO GUERRERO
Eng Process Fee Ord 176,300 Cleared 9/24/2021 DAGOVERTO GUERRERO
Sewer availability Cleared 9/24/2021 DAGOVERTO GUERRERO
Hydrant and Access approval Cleared 10/22/2021 MATTHEW CRAIG
ZI Cleared 4/19/2022 DANG NGUYEN

Contact Information

Contractor Owner-Builder       ,

Inspector Information

MICHEL ABAJAN, (818) 374-9932 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Rough-Elec/Plmb/HVAC 9/21/2022 Corrections Issued MICHEL ABAJAN
Wood Frame 9/21/2022 Corrections Issued MICHEL ABAJAN
ELECTRICAL-Rough 10/5/2022 Corrections Issued ARAM AVEDISIAN
HVAC-Rough 10/5/2022 Corrections Issued ARAM AVEDISIAN
PLUMBING-Rough 10/5/2022 Corrections Issued ARAM AVEDISIAN
ELECTRICAL-Rough 10/18/2022 Approved MICHEL ABAJAN
HVAC-Rough 10/18/2022 Approved MICHEL ABAJAN
PLUMBING-Rough 10/18/2022 Corrections Issued MICHEL ABAJAN
BUILDING-Rough-Frame 11/18/2022 Approved MICHEL ABAJAN
Green Building Rough 11/18/2022 Approved MICHEL ABAJAN
METHANE-Rough 11/18/2022 Approved MICHEL ABAJAN
PLUMBING-Rough 11/18/2022 Approved MICHEL ABAJAN
Insulation 12/1/2022 No Access for Inspection MICHEL ABAJAN
Insulation 12/5/2022 Approved MICHEL ABAJAN
Interior/Exterior Lathing 12/5/2022 Approved MICHEL ABAJAN
Drywall Nailing 12/9/2022 Approved MICHEL ABAJAN
Shower Pan 12/20/2022 Approved MICHEL ABAJAN
ELECTRICAL-Final 2/3/2023 Corrections Issued MICHEL ABAJAN
Final 2/3/2023 Corrections Issued MICHEL ABAJAN
Green Building Final 2/3/2023 Not Ready for Inspection MICHEL ABAJAN
HVAC-Final 2/3/2023 Approved MICHEL ABAJAN
PLUMBING-Final 2/3/2023 Approved MICHEL ABAJAN
Smoke Detectors 2/3/2023 Approved MICHEL ABAJAN
ELECTRICAL-Final 4/3/2023 Corrections Issued CHRISTOPHER DELLEFIELD
Final 4/3/2023 Corrections Issued CHRISTOPHER DELLEFIELD
Green Building Final 4/3/2023 Not Ready for Inspection CHRISTOPHER DELLEFIELD
PLUMBING-Final 4/3/2023 Corrections Issued CHRISTOPHER DELLEFIELD
ELECTRICAL-Final 4/10/2023 Approved MICHEL ABAJAN
Final 4/10/2023 Corrections Issued MICHEL ABAJAN
Green Building Final 4/10/2023 Approved MICHEL ABAJAN
Final 4/26/2023 OK to Issue CofO MICHEL ABAJAN