10669 N EL DORADO AVE 91331
Certificate Information: 10669 N EL DORADO AVE 91331
- Application / Permit
- 20016-20000-26321
- Plan Check / Job No.
- B20VN13470
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT THE RECREATION ROOM AND STORAGE TO AN IRREGULAR 20' x 44'9" ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33 (c) AND (d).
- Permit Issued
- Issued on 6/8/2022
- Issuing Office
- Valley
- Current Status
- CofO Issued on 4/27/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/28/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 11/5/2020 | LUIS RINCON |
| Corrections Issued | 11/9/2020 | LUIS RINCON |
| Applicant returned to address corrections | 8/24/2021 | LUIS RINCON |
| Applicant returned to address corrections | 9/20/2021 | LUISANGEL VALENZUELA |
| Applicant returned to address corrections | 3/27/2022 | LUIS RINCON |
| Plan Check Approved | 4/3/2022 | LUIS RINCON |
| No Progress | 4/4/2022 | LUIS RINCON |
| Plan Check Approved | 4/20/2022 | LUIS RINCON |
| Building Plans Picked Up | 4/22/2022 | APPLICANT |
| Issued | 6/8/2022 | APPLICANT |
| CofO in Progress | 4/27/2023 | MICHEL ABAJAN |
| CofO Issued | 4/27/2023 | MICHAEL SMITH |
| Permit Finaled | 4/27/2023 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 9/24/2021 | DAGOVERTO GUERRERO |
| Eng Process Fee Ord 176,300 | Cleared | 9/24/2021 | DAGOVERTO GUERRERO |
| Sewer availability | Cleared | 9/24/2021 | DAGOVERTO GUERRERO |
| Hydrant and Access approval | Cleared | 10/22/2021 | MATTHEW CRAIG |
| ZI | Cleared | 4/19/2022 | DANG NGUYEN |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| MICHEL ABAJAN, (818) 374-9932 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Rough-Elec/Plmb/HVAC | 9/21/2022 | Corrections Issued | MICHEL ABAJAN |
| Wood Frame | 9/21/2022 | Corrections Issued | MICHEL ABAJAN |
| ELECTRICAL-Rough | 10/5/2022 | Corrections Issued | ARAM AVEDISIAN |
| HVAC-Rough | 10/5/2022 | Corrections Issued | ARAM AVEDISIAN |
| PLUMBING-Rough | 10/5/2022 | Corrections Issued | ARAM AVEDISIAN |
| ELECTRICAL-Rough | 10/18/2022 | Approved | MICHEL ABAJAN |
| HVAC-Rough | 10/18/2022 | Approved | MICHEL ABAJAN |
| PLUMBING-Rough | 10/18/2022 | Corrections Issued | MICHEL ABAJAN |
| BUILDING-Rough-Frame | 11/18/2022 | Approved | MICHEL ABAJAN |
| Green Building Rough | 11/18/2022 | Approved | MICHEL ABAJAN |
| METHANE-Rough | 11/18/2022 | Approved | MICHEL ABAJAN |
| PLUMBING-Rough | 11/18/2022 | Approved | MICHEL ABAJAN |
| Insulation | 12/1/2022 | No Access for Inspection | MICHEL ABAJAN |
| Insulation | 12/5/2022 | Approved | MICHEL ABAJAN |
| Interior/Exterior Lathing | 12/5/2022 | Approved | MICHEL ABAJAN |
| Drywall Nailing | 12/9/2022 | Approved | MICHEL ABAJAN |
| Shower Pan | 12/20/2022 | Approved | MICHEL ABAJAN |
| ELECTRICAL-Final | 2/3/2023 | Corrections Issued | MICHEL ABAJAN |
| Final | 2/3/2023 | Corrections Issued | MICHEL ABAJAN |
| Green Building Final | 2/3/2023 | Not Ready for Inspection | MICHEL ABAJAN |
| HVAC-Final | 2/3/2023 | Approved | MICHEL ABAJAN |
| PLUMBING-Final | 2/3/2023 | Approved | MICHEL ABAJAN |
| Smoke Detectors | 2/3/2023 | Approved | MICHEL ABAJAN |
| ELECTRICAL-Final | 4/3/2023 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| Final | 4/3/2023 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| Green Building Final | 4/3/2023 | Not Ready for Inspection | CHRISTOPHER DELLEFIELD |
| PLUMBING-Final | 4/3/2023 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| ELECTRICAL-Final | 4/10/2023 | Approved | MICHEL ABAJAN |
| Final | 4/10/2023 | Corrections Issued | MICHEL ABAJAN |
| Green Building Final | 4/10/2023 | Approved | MICHEL ABAJAN |
| Final | 4/26/2023 | OK to Issue CofO | MICHEL ABAJAN |