7831 S KENYON AVE 90045
Certificate Information: 7831 S KENYON AVE 90045
- Application / Permit
- 20016-20000-26166
- Plan Check / Job No.
- B20VN13425
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- INTERIOR REMODEL TO (E) KITCHEN, RELOCATE LAUNDRY, REPLACE EXTERIOR DOOR WITH WINDOW AND REMOVE THE FIREPLACE. ALL WORK DONE PER STRUCTURAL ENGINEERING.
- Permit Issued
- Issued on 11/10/2020
- Issuing Office
- Current Status
- Permit Finaled on 5/5/2021
Permit Application Status History
| Submitted | 10/14/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 10/23/2020 | GURUNATH NESARAJAH |
| Corrections Issued | 10/25/2020 | GURUNATH NESARAJAH |
| Plan Check Approved | 11/10/2020 | GURUNATH NESARAJAH |
| Issued | 11/10/2020 | APPLICANT |
| Permit Finaled | 5/4/2021 | BRENDAN LOONEY |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 10/29/2020 | BRIAN MILLER |
Contact Information
| Architect | Dembsky,, Amit; Lic. No.: C30383 | 5739 KANAN ROAD # 133 AGOURA HILLS, CA 91301 |
| Contractor | Butel Construction Inc; Lic. No.: 852273-B | 257 SOUTH CITRUS AVE LOS ANGELES, CA 90036 |
Inspector Information
| MICHAEL LEWIS, (310) 914-3979 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| BUILDING-Rough-Frame | 1/27/2021 | Corrections Issued | JUAN VALENZUELA |
| ELECTRICAL-Rough | 1/27/2021 | Approved | JUAN VALENZUELA |
| HVAC-Rough | 1/27/2021 | Approved | JUAN VALENZUELA |
| PLUMBING-Rough | 1/27/2021 | Approved | JUAN VALENZUELA |
| BUILDING-Rough-Frame | 2/1/2021 | Approved | DAVID HEINE |
| Footing/Foundation/Slab | 2/1/2021 | Approved | DAVID HEINE |
| Insulation | 2/3/2021 | Approved | EVAN COOPER |
| Drywall Nailing | 2/5/2021 | Approved | DAVID HEINE |
| ELECTRICAL-Final | 5/4/2021 | Approved | BRENDAN LOONEY |
| Final | 5/4/2021 | Permit Finaled | BRENDAN LOONEY |
| HVAC-Final | 5/4/2021 | Approved | BRENDAN LOONEY |
| PLUMBING-Final | 5/4/2021 | Approved | BRENDAN LOONEY |
| SGSOV-Seismic Gas S/O Valve | 5/4/2021 | SGSOV Approved | BRENDAN LOONEY |
| Smoke Detectors | 5/4/2021 | Approved | BRENDAN LOONEY |