15067 W LA MESA ST 91342

Certificate Information: 15067 W LA MESA ST 91342

Application / Permit
20016-20000-26159
Plan Check / Job No.
B20VN13423
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT THE EXISTING ATTACHED 3-CAR GARAGE (27'4"X18') INTO ACCESSORY DWELLING UNIT PER LAMC 12.22A33(c)(d).
Permit Issued
Issued on 10/20/2022
Issuing Office
Valley
Current Status
CofO Issued on 3/4/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/16/2020 APPLICANT
Assigned to Plan Check Engineer 10/29/2020 NILOOFAR MEHRAIN
Corrections Issued 11/4/2020 NILOOFAR MEHRAIN
Applicant returned to address corrections 6/16/2022 ALEC MOUSAKHANIAN
Building Plans Picked Up 6/16/2022 APPLICANT
Applicant returned to address corrections 10/19/2022 HAYATO TSUCHIYA
Issued 10/20/2022 APPLICANT
CofO in Progress 2/15/2024 CHRISTOPHER ROJAS
Permit Finaled 3/4/2024 RUBEN SALAS
CofO Issued 3/4/2024 RUBEN SALAS
Permit Finaled 3/4/2024 RUBEN SALAS

Permit Application Clearance Information

Hydrant and Access approval Cleared 3/5/2022 DWIGHT SANKEY
Address approval Cleared 6/6/2022 JOSE DUARTE-DIAZ
Sewer availability Cleared 6/6/2022 JOSE DUARTE-DIAZ
Eng Process Fee Ord 176,300 Cleared 6/9/2022 JOSE DUARTE-DIAZ

Contact Information

Contractor Owner-Builder       ,
Engineer Garcia,, Eddy Alexander; Lic. No.: S6159 17958 LULL ST      RESEDA, CA 91335

Inspector Information

KEVIN BERBERYAN, (818) 374-9931 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 10/27/2022 Partial Inspection ARAM AVEDISIAN
Footing/Foundation/Slab 11/14/2022 Approved ARAM AVEDISIAN
PLUMBING-Rough 11/14/2022 Partial Approval ARAM AVEDISIAN
BUILDING-Rough-Frame 12/1/2022 Not Ready for Inspection CHRISTOPHER DELLEFIELD
Floor/Roof Diaphrgm/Shear Wall 12/1/2022 Corrections Issued CHRISTOPHER DELLEFIELD
Green Building Rough 12/1/2022 Not Ready for Inspection CHRISTOPHER DELLEFIELD
PLUMBING-Rough 12/1/2022 Not Ready for Inspection CHRISTOPHER DELLEFIELD
BUILDING-Rough-Frame 12/6/2022 Not Ready for Inspection ARAM AVEDISIAN
ELECTRICAL-Rough 12/6/2022 Approved ARAM AVEDISIAN
Floor/Roof Diaphrgm/Shear Wall 12/6/2022 Approved ARAM AVEDISIAN
Green Building Rough 12/6/2022 Not Ready for Inspection ARAM AVEDISIAN
PLUMBING-Rough 12/6/2022 Approved ARAM AVEDISIAN
Interior/Exterior Lathing 12/12/2022 Not Ready for Inspection MICHEL ABAJAN
BUILDING-Rough-Frame 12/15/2022 Approved ARAM AVEDISIAN
HVAC-Rough 12/15/2022 Approved ARAM AVEDISIAN
Interior/Exterior Lathing 12/15/2022 Partial Approval ARAM AVEDISIAN
Insulation 12/21/2022 Approved ARAM AVEDISIAN
Shower Pan 12/21/2022 Approved ARAM AVEDISIAN
Drywall Nailing 12/29/2022 Approved ARAM AVEDISIAN
Floor/Roof Diaphrgm/Shear Wall 12/29/2022 Approved ARAM AVEDISIAN
Interior/Exterior Lathing 12/29/2022 Partial Approval ARAM AVEDISIAN
BUILDING-Rough-Frame 1/23/2023 Approved ROBERT GOLD
Final 1/23/2023 Corrections Issued ROBERT GOLD
Green Building Final 1/23/2023 Not Ready for Inspection ROBERT GOLD
Green Building Rough 1/23/2023 Approved ROBERT GOLD
SGSOV-Seismic Gas S/O Valve 1/23/2023 SGSOV Not Ready ROBERT GOLD
Smoke Detectors 1/23/2023 Corrections Issued ROBERT GOLD
Underground Mechanical 1/23/2023 Corrections Issued ROBERT GOLD
Final 2/1/2023 Corrections Issued ROBERT GOLD
Green Building Final 2/1/2023 Approved ROBERT GOLD
SGSOV-Seismic Gas S/O Valve 2/1/2023 SGSOV Not Ready ROBERT GOLD
Smoke Detectors 2/1/2023 Approved ROBERT GOLD
ELECTRICAL-Final 2/28/2023 Approved MICHEL ABAJAN
Final 2/28/2023 Corrections Issued MICHEL ABAJAN
HVAC-Final 2/28/2023 Approved MICHEL ABAJAN
PLUMBING-Final 2/28/2023 Approved MICHEL ABAJAN
SGSOV-Seismic Gas S/O Valve 2/28/2023 SGSOV Approved MICHEL ABAJAN
Final 3/22/2023 Corrections Issued ARAM AVEDISIAN
Final 1/29/2024 OK to Issue CofO CHRISTOPHER ROJAS