22441 W SATICOY ST 91307

Certificate Information: 22441 W SATICOY ST 91307

Application / Permit
20016-20000-25600
Plan Check / Job No.
B20VN13238
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) 21' X 21' DETACHED GARAGE TO (N) ACCESSORY DWELLING UNIT PER GCS 65852.2(E)(1)(A). ALL WORK PER ENGINEERING.
Permit Issued
Issued on 3/26/2021
Issuing Office
Valley
Current Status
CofO Issued on 11/22/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/9/2020 APPLICANT
Assigned to Plan Check Engineer 10/15/2020 HAYATO TSUCHIYA
Corrections Issued 10/18/2020 HAYATO TSUCHIYA
Plan Check Approved 3/4/2021 JENNIFER LEE
Building Plans Picked Up 3/8/2021 APPLICANT
Issued 3/26/2021 APPLICANT
CofO in Progress 11/19/2021 DAVID STEPANYAN
CofO Issued 11/22/2021 MICHAEL SMITH
Permit Finaled 11/22/2021 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 11/23/2020 ABDULLAH SADOZAI
Sewer availability Cleared 11/23/2020 ABDULLAH SADOZAI
Eng Process Fee Ord 176,300 Cleared 11/24/2020 ABDULLAH SADOZAI
Construction near power lines Cleared 1/10/2021 RIDWAN HARDY

Contact Information

Contractor Owner-Builder       ,
Engineer Cooke,, Conway Cecil; Lic. No.: S5524 34658 LINDA ROSEA RD      TEMECULA, CA 92592

Inspector Information

JEFFREY HARTLINE, (818) 774-4320 Office Hours: 7:00-8:00 AM MON-FRI
CHRIS CHRISTENSEN, (818) 774-4320 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 4/20/2021 Partial Approval DAVID STEPANYAN
Footing/Foundation/Slab 5/3/2021 Approved DAVID STEPANYAN
ELECTRICAL-Rough 5/20/2021 Partial Approval TROY SANDERS
ELECTRICAL-Rough 6/1/2021 Not Ready for Inspection JOSEPH SAGEN
ELECTRICAL-Rough 6/8/2021 Not Ready for Inspection PETER FOLLING
ELECTRICAL-Rough 7/9/2021 Corrections Issued DAVID STEPANYAN
BUILDING-Rough-Frame 7/27/2021 Not Ready for Inspection DAVID STEPANYAN
ELECTRICAL-Rough 7/27/2021 Approved DAVID STEPANYAN
Floor/Roof Diaphrgm/Shear Wall 7/27/2021 Partial Approval DAVID STEPANYAN
Green Building Rough 7/27/2021 Not Ready for Inspection DAVID STEPANYAN
Insulation 7/27/2021 Corrections Issued DAVID STEPANYAN
PLUMBING-Rough 7/27/2021 Approved DAVID STEPANYAN
BUILDING-Rough-Frame 9/14/2021 Approved DAVID STEPANYAN
Floor/Roof Diaphrgm/Shear Wall 9/14/2021 Approved DAVID STEPANYAN
Green Building Rough 9/14/2021 Approved DAVID STEPANYAN
HVAC-Rough 9/14/2021 Approved DAVID STEPANYAN
Insulation 9/14/2021 Partial Approval DAVID STEPANYAN
Wood Frame 9/14/2021 Not Ready for Inspection DAVID STEPANYAN
Drywall Nailing 9/21/2021 Approved PETER FOLLING
Special/Order Compliance 10/6/2021 Approved DAVID STEPANYAN
ELECTRICAL-Final 11/8/2021 Approved DAVID STEPANYAN
Final 11/8/2021 Not Ready for Inspection DAVID STEPANYAN
Green Building Final 11/8/2021 Corrections Issued DAVID STEPANYAN
HVAC-Final 11/8/2021 Approved DAVID STEPANYAN
PLUMBING-Final 11/8/2021 Corrections Issued DAVID STEPANYAN
SGSOV-Seismic Gas S/O Valve 11/8/2021 SGSOV Not Ready DAVID STEPANYAN
Smoke Detectors 11/8/2021 Approved DAVID STEPANYAN
Final 11/10/2021 Not Ready for Inspection DAVID STEPANYAN
Gas Test 11/10/2021 Approved DAVID STEPANYAN
Green Building Final 11/10/2021 Approved DAVID STEPANYAN
SGSOV-Seismic Gas S/O Valve 11/10/2021 SGSOV Approved DAVID STEPANYAN
Final 11/18/2021 OK to Issue CofO DAVID STEPANYAN
PLUMBING-Final 11/18/2021 Approved DAVID STEPANYAN