9656 N MASON AVE 91311

Certificate Information: 9656 N MASON AVE 91311

Application / Permit
20016-20000-25491
Plan Check / Job No.
B20VN13182
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
PROPOSED 6'-8" x 29'-6" IRREGULAR SHAPED ADDITION AT FIRST FLOOR, 30'-0" x 29'-5" AT SECOND FLOOR AND CONVERT THE (E) DETACHED GARAGE INTO A (N) ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33 (c)-(d).
Permit Issued
Issued on 6/24/2022
Issuing Office
Current Status
CofO Issued on 8/25/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/7/2020 APPLICANT
Assigned to Plan Check Engineer 10/13/2020 SARKIS HARABEDIAN
Corrections Issued 10/14/2020 SARKIS HARABEDIAN
Plan Check Approved 6/13/2022 SARKIS HARABEDIAN
Building Plans Picked Up 6/21/2022 APPLICANT
Issued 6/24/2022 APPLICANT
CofO in Progress 8/8/2023 DAVID SCANTLIN
Permit Finaled 8/25/2023 JOHN JANSON
CofO Issued 8/25/2023 JOHN JANSON
Permit Finaled 8/25/2023 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 1/8/2021 ADRIAN CASTRO
Sewer availability Cleared 1/8/2021 ADRIAN CASTRO
Eng Process Fee Ord 176,300 Cleared 1/11/2021 ADRIAN CASTRO
Construction near power lines Cleared 3/17/2021 RIDWAN HARDY
Construction within easement Cleared 3/17/2021 RIDWAN HARDY
Low Impact Development Cleared 4/15/2022 NICK RAYGOZA
Hydrant and Access approval Cleared 4/29/2022 MATTHEW CRAIG
Roof/Waste drainage to street Cleared 6/13/2022 LEE GUILBEAUX
Public Works-Highway Ded. Cleared 6/13/2022 LEE GUILBEAUX

Contact Information

Contractor Owner-Builder       ,
Engineer Babapirzadeh,, Ghazal; Lic. No.: C90480 7270 HILLSIDE AVE   APT 306    LOS ANGELES, CA 90046

Inspector Information

JACK KARGODORIAN, (818) 774-4319 Office Hours: 7:00-8:00 AM MON-FRI
KRISTEN CAUSEY, (818) 774-4319 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 10/5/2022 Partial Approval VINCENT HANLEY
Sewer 10/5/2022 Approved VINCENT HANLEY
Footing/Foundation/Slab 10/12/2022 Approved JOHN KIDWELL
Excavation/Setback/Form/Re-Bar 10/26/2022 Approved JOHN KIDWELL
Floor/Roof Diaphrgm/Shear Wall 12/6/2022 Approved DAVID SCANTLIN
HVAC-Rough 12/6/2022 Partial Approval DAVID SCANTLIN
PLUMBING-Rough 12/6/2022 Approved DAVID SCANTLIN
ELECTRICAL-Rough 12/22/2022 Approved JOHN KIDWELL
Wood Frame 1/12/2023 Partial Inspection JOHN KIDWELL
BUILDING-Rough-Frame 1/31/2023 Approved DAVID SCANTLIN
Green Building Rough 1/31/2023 Approved DAVID SCANTLIN
Interior/Exterior Lathing 1/31/2023 Partial Approval DAVID SCANTLIN
Insulation 2/8/2023 Approved MORRIS JACKSON
Drywall Nailing 2/16/2023 Approved JON MCHUGH
Interior/Exterior Lathing 2/16/2023 Not Ready for Inspection JON MCHUGH
Interior/Exterior Lathing 2/21/2023 Approved MORRIS JACKSON
Final 7/12/2023 Corrections Issued JOHN KIDWELL
Green Building Final 7/12/2023 Not Ready for Inspection JOHN KIDWELL
SGSOV-Seismic Gas S/O Valve 7/12/2023 SGSOV Approved JOHN KIDWELL
Smoke Detectors 7/12/2023 Approved JOHN KIDWELL
ELECTRICAL-Final 8/7/2023 Approved DAVID SCANTLIN
Final 8/7/2023 OK to Issue CofO DAVID SCANTLIN
Green Building Final 8/7/2023 Approved DAVID SCANTLIN
HVAC-Final 8/7/2023 Approved DAVID SCANTLIN
PLUMBING-Final 8/7/2023 Approved DAVID SCANTLIN