19504 W GAULT ST 91335

Certificate Information: 19504 W GAULT ST 91335

Application / Permit
20016-20000-25477
Plan Check / Job No.
B20VN13178
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT 18'-9" X 45'-7" (E) DETACHED GARAGE INTO A (N) ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) AND (d). ALL WORK PER ENGINEERING.
Permit Issued
Issued on 9/14/2021
Issuing Office
Valley
Current Status
CofO Issued on 8/28/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/8/2020 APPLICANT
Assigned to Plan Check Engineer 10/14/2020 ROSENDO MEDINA
Corrections Issued 10/16/2020 ROSENDO MEDINA
Applicant returned to address corrections 12/16/2020 ROSENDO MEDINA
Applicant returned to address corrections 1/15/2021 RAPHAEL ROSAS
Plan Check Approved 1/29/2021 RAPHAEL ROSAS
Issued 9/14/2021 APPLICANT
CofO in Progress 8/22/2024 JEFFREY BULL
Permit Finaled 8/28/2024 JOHN JANSON
CofO Issued 8/28/2024 JOHN JANSON
Permit Finaled 8/28/2024 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 10/27/2020 ADRIAN CASTRO
Sewer availability Cleared 10/27/2020 ADRIAN CASTRO
Eng Process Fee Ord 176,300 Cleared 10/29/2020 ADRIAN CASTRO
Construction near power lines Cleared 1/20/2021 RIDWAN HARDY

Contact Information

Contractor Owner-Builder       ,
Engineer Almalla,, Dean; Lic. No.: C58024 15053 VENTURA BLVD STE 205      SHERMAN OAKS, CA 91403

Inspector Information

ARUTYUN MADATYAN, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI
JUAN ALVARADO, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 4/12/2022 Approved VINCENT HANLEY
PLUMBING-Rough 6/8/2022 Partial Approval STEVEN BACK
Green Building Rough 9/15/2022 Not Ready for Inspection JEFFREY BULL
Pre-Inspection 9/15/2022 Approved JEFFREY BULL
Footing/Foundation/Slab 11/2/2022 Approved JEFFREY BULL
ELECTRICAL-Rough 12/29/2022 Approved JEFFREY BULL
PLUMBING-Rough 12/29/2022 Approved JEFFREY BULL
BUILDING-Rough-Frame 10/11/2023 Approved JEFFREY BULL
Green Building Rough 10/11/2023 Approved JEFFREY BULL
HVAC-Rough 10/11/2023 Approved JEFFREY BULL
Interior/Exterior Lathing 10/11/2023 Partial Approval JEFFREY BULL
Drywall Nailing 11/20/2023 Approved DAVID SCANTLIN
Interior/Exterior Lathing 12/7/2023 Approved JEFFREY BULL
Service/Power Release 12/7/2023 Approved JEFFREY BULL
Final 8/1/2024 Corrections Issued JEFFREY BULL
Green Building Final 8/1/2024 Not Ready for Inspection JEFFREY BULL
SGSOV-Seismic Gas S/O Valve 8/1/2024 SGSOV Approved JEFFREY BULL
Smoke Detectors 8/1/2024 Not Ready for Inspection JEFFREY BULL
Final 8/13/2024 Not Ready for Inspection JEFFREY BULL
Green Building Final 8/13/2024 Approved JEFFREY BULL
Smoke Detectors 8/13/2024 Approved JEFFREY BULL
Final 8/22/2024 OK to Issue CofO JEFFREY BULL
Service/Power Release 8/22/2024 Approved JEFFREY BULL