7444 N WOODMAN AVE 91405
Certificate Information: 7444 N WOODMAN AVE 91405
- Application / Permit
- 20016-20000-25434
- Plan Check / Job No.
- B20VN13157
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- CONVERT (E) MECHANICAL ROOM & TWO (E) RECREATION ROOMS INTO TWO (N) ACCESSORY DWELLING UNITS PER GCS 65852.2(e)(1)(C) TO (E) 79-UNIT APT BLDG
- Permit Issued
- Issued on 3/4/2021
- Issuing Office
- Metro
- Current Status
- CofO Issued on 12/1/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/8/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 10/15/2020 | NILOOFAR MEHRAIN |
| Corrections Issued | 10/20/2020 | NILOOFAR MEHRAIN |
| Building Plans Picked Up | 10/23/2020 | APPLICANT |
| Applicant returned to address corrections | 1/21/2021 | NILOOFAR MEHRAIN |
| Plan Check Approved | 1/21/2021 | NILOOFAR MEHRAIN |
| Issued | 3/4/2021 | APPLICANT |
| CofO in Progress | 11/22/2022 | ROBERT DAVIS |
| Permit Finaled | 12/1/2022 | JEFFREY DURAN |
| CofO Issued | 12/1/2022 | JEFFREY DURAN |
| Permit Finaled | 12/1/2022 | JEFFREY DURAN |
Permit Application Clearance Information
| Hydrant and Access approval | Cleared | 12/15/2020 | MATTHEW CRAIG |
| Address approval | Cleared | 12/22/2020 | LEE GUILBEAUX |
| Highway dedication | Cleared | 12/22/2020 | LEE GUILBEAUX |
| Sewer availability | Cleared | 12/22/2020 | LEE GUILBEAUX |
| Eng Process Fee Ord 176,300 | Cleared | 12/23/2020 | LEE GUILBEAUX |
| Public Works-Highway Ded. | Cleared | 12/23/2020 | LEE GUILBEAUX |
| Public Works-Sewers | Cleared | 12/23/2020 | LEE GUILBEAUX |
Contact Information
| Contractor | D T A G Inc; Lic. No.: 1061967-B | 13547 VENTURA BLVD #171 SHERMAN OAKS, CA 91423 |
Inspector Information
| JEFFREY FULTON, (818) 374-1132 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Final | 3/18/2021 | Corrections Issued | ROBERT DAVIS |
| Green Building Final | 3/18/2021 | Not Ready for Inspection | ROBERT DAVIS |
| Green Building Rough | 3/18/2021 | Not Ready for Inspection | ROBERT DAVIS |
| SGSOV-Seismic Gas S/O Valve | 3/18/2021 | SGSOV Not Ready | ROBERT DAVIS |
| Smoke Detectors | 3/18/2021 | Not Ready for Inspection | ROBERT DAVIS |
| Wood Frame | 3/18/2021 | Not Ready for Inspection | ROBERT DAVIS |
| Pre-Inspection | 5/21/2021 | Approved | ROBERT DAVIS |
| Pre-Inspection | 7/8/2021 | Approved | ROBERT DAVIS |
| Final | 2/9/2022 | Not Ready for Inspection | ROBERT DAVIS |
| Green Building Final | 2/9/2022 | Approved | ROBERT DAVIS |
| Green Building Rough | 2/9/2022 | Approved | ROBERT DAVIS |
| SGSOV-Seismic Gas S/O Valve | 2/9/2022 | SGSOV Approved | ROBERT DAVIS |
| Smoke Detectors | 2/9/2022 | Approved | ROBERT DAVIS |
| Wood Frame | 2/9/2022 | Approved | ROBERT DAVIS |
| Final | 11/8/2022 | OK to Issue CofO | ROBERT DAVIS |