4532 N LENNOX AVE 91423

Certificate Information: 4532 N LENNOX AVE 91423

Application / Permit
20016-20000-24977
Plan Check / Job No.
B20VN13009
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT THE (E) 20'-1" X 19'-11" GARAGE INTO A (N) ACCESSORY DWELLING UNIT PER GCS. 65852.2(e)(1)A). PER ENGINEERING DESIGN.
Permit Issued
Issued on 3/12/2021
Issuing Office
Metro
Current Status
CofO Issued on 5/9/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/2/2020 APPLICANT
Assigned to Plan Check Engineer 10/8/2020 PARISA ZAHABI
Corrections Issued 10/10/2020 PARISA ZAHABI
Plan Check Approved 2/17/2021 PARISA ZAHABI
Issued 3/12/2021 APPLICANT
Building Plans Picked Up 3/19/2021 APPLICANT
CofO in Progress 5/9/2023 MISAEL ESPARZA
Permit Finaled 5/9/2023 MICHAEL SMITH
CofO Issued 5/9/2023 MICHAEL SMITH
Permit Finaled 5/9/2023 MICHAEL SMITH

Permit Application Clearance Information

CPC Cleared 10/29/2020 RICHARD REASER
Address approval Cleared 12/9/2020 MARKOS PEREZ-BRAN
Sewer availability Cleared 12/9/2020 MARKOS PEREZ-BRAN
Eng Process Fee Ord 176,300 Cleared 12/14/2020 MARKOS PEREZ-BRAN
Construction near power lines Cleared 2/10/2021 RIDWAN HARDY

Contact Information

Engineer Helou,, Dawn Renee; Lic. No.: C52361 22701 ERWIN ST      WOODLAND HILLS, CA 91367

Inspector Information

MISAEL ESPARZA, (818) 374-1169 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 2/3/2022 Corrections Issued MISAEL ESPARZA
Footing/Foundation/Slab 2/7/2022 Conditional Approval MISAEL ESPARZA
PLUMBING-Rough 2/7/2022 Partial Approval MISAEL ESPARZA
Sewer 2/15/2022 Approved MISAEL ESPARZA
ELECTRICAL-Rough 4/22/2022 Approved MISAEL ESPARZA
HVAC-Rough 7/15/2022 Approved MISAEL ESPARZA
Insulation 7/15/2022 Approved MISAEL ESPARZA
PLUMBING-Rough 7/15/2022 Approved MISAEL ESPARZA
Wood Frame 7/15/2022 Approved MISAEL ESPARZA
Drywall Nailing 7/27/2022 Approved MISAEL ESPARZA
Shower Pan 7/27/2022 Not Ready for Inspection MISAEL ESPARZA
Interior/Exterior Lathing 8/1/2022 Partial Approval JACK KARGODORIAN
BUILDING-Rough-Frame 3/7/2023 Approved MISAEL ESPARZA
Final 3/7/2023 Corrections Issued MISAEL ESPARZA
MERV13>=Final 3/7/2023 Approved MISAEL ESPARZA
MERV13>=Rough 3/7/2023 Approved MISAEL ESPARZA
SGSOV-Seismic Gas S/O Valve 3/7/2023 SGSOV Approved MISAEL ESPARZA
Smoke Detectors 3/7/2023 Corrections Issued MISAEL ESPARZA
Final 4/26/2023 Not Ready for Inspection THOMAS FINNILA
Smoke Detectors 4/26/2023 Approved THOMAS FINNILA
Final 5/2/2023 Corrections Issued MISAEL ESPARZA
ELECTRICAL-Final 5/8/2023 Approved MISAEL ESPARZA
Final 5/8/2023 OK to Issue CofO MISAEL ESPARZA
HVAC-Final 5/8/2023 Approved MISAEL ESPARZA
PLUMBING-Final 5/8/2023 Approved MISAEL ESPARZA