4900-4902 N MATULA DR 91356
Certificate Information: 4900-4902 N MATULA DR 91356
- Application / Permit
- 20016-20000-24951
- Plan Check / Job No.
- B20VN12985
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- CONVERT EX ATT GARAGE INTO ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(A).
- Permit Issued
- Issued on 2/24/2021
- Issuing Office
- Current Status
- Issued on 2/24/2021
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 10/3/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 10/9/2020 | HAYATO TSUCHIYA |
| Corrections Issued | 10/10/2020 | HAYATO TSUCHIYA |
| Applicant returned to address corrections | 1/5/2021 | HAYATO TSUCHIYA |
| Plan Check Approved | 1/29/2021 | HAYATO TSUCHIYA |
| Issued | 2/24/2021 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 11/18/2020 | JOHN TRIANTAFYLLOS |
| BHO/Hillside ordinance | Cleared | 11/18/2020 | JOHN TRIANTAFYLLOS |
| BHO/Hillside ordinance | Cleared | 11/18/2020 | JOHN TRIANTAFYLLOS |
| BHO/Hillside ordinance | Cleared | 11/18/2020 | JOHN TRIANTAFYLLOS |
| BHO/Hillside ordinance | Cleared | 11/18/2020 | JOHN TRIANTAFYLLOS |
| Eng Process Fee Ord 176,300 | Cleared | 12/1/2020 | JOHN TRIANTAFYLLOS |
| Sewer availability | Cleared | 12/1/2020 | JOHN TRIANTAFYLLOS |
| Grading Pre-Inspection | Cleared | 12/3/2020 | BRIAN MILLER |
Contact Information
| Architect | , ; Lic. No.: C35150 | , |
| Contractor | Owner-Builder | , |
| Engineer | Khanlou,, Amir; Lic. No.: C87550 | 10671 HOLMAN AVE APT 207 LOS ANGELES, CA 90024 |
Inspector Information
| JOHN KIDWELL, (818) 774-4314 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 3/2/2021 | Corrections Issued | DAVID SANDOVAL |
| PLUMBING-Rough | 3/24/2021 | No Access for Inspection | DAVID SANDOVAL |
| Footing/Foundation/Slab | 3/30/2021 | Corrections Issued | DAVID SANDOVAL |
| PLUMBING-Rough | 3/30/2021 | Not Ready for Inspection | DAVID SANDOVAL |
| Deputy Drilled-In Anchors | 4/16/2021 | Conditional Approval | DAVID SANDOVAL |
| Footing/Foundation/Slab | 4/23/2021 | Corrections Issued | RONALD COWAN |
| Footing/Foundation/Slab | 5/6/2021 | Corrections Issued | DAVID SANDOVAL |
| Footing/Foundation/Slab | 5/17/2021 | Approved | DAVID SANDOVAL |
| Underground Mechanical | 5/17/2021 | Partial Approval | DAVID SANDOVAL |
| Insulation | 6/15/2021 | Partial Approval | DAVID SANDOVAL |
| BUILDING-Rough-Frame | 6/29/2021 | Not Ready for Inspection | DAVID SANDOVAL |
| Drywall Nailing | 6/29/2021 | Partial Approval | DAVID SANDOVAL |
| Green Building Rough | 6/29/2021 | Not Ready for Inspection | DAVID SANDOVAL |
| PLUMBING-Rough | 6/29/2021 | Not Ready for Inspection | DAVID SANDOVAL |
| BUILDING-Rough-Frame | 7/6/2021 | Not Ready for Inspection | DAVID SANDOVAL |
| PLUMBING-Rough | 7/6/2021 | Approved | DAVID SANDOVAL |
| BUILDING-Rough-Frame | 7/26/2021 | Approved | DAVID SANDOVAL |
| Drywall Nailing | 7/26/2021 | Not Ready for Inspection | DAVID SANDOVAL |
| Final | 7/26/2021 | Not Ready for Inspection | DAVID SANDOVAL |
| Green Building Final | 7/26/2021 | Not Ready for Inspection | DAVID SANDOVAL |
| Green Building Rough | 7/26/2021 | Approved | DAVID SANDOVAL |
| Insulation | 7/26/2021 | Approved | DAVID SANDOVAL |
| Smoke Detectors | 7/26/2021 | Not Ready for Inspection | DAVID SANDOVAL |
| Drywall Nailing | 8/13/2021 | Approved | DAVID SANDOVAL |
| Interior/Exterior Lathing | 8/13/2021 | Approved | DAVID SANDOVAL |
| SGSOV-Seismic Gas S/O Valve | 8/13/2021 | SGSOV Not Ready | DAVID SANDOVAL |
| Final | 9/23/2021 | Corrections Issued | DAVID SANDOVAL |
| Green Building Final | 9/23/2021 | Not Ready for Inspection | DAVID SANDOVAL |
| SGSOV-Seismic Gas S/O Valve | 9/23/2021 | SGSOV Not Ready | DAVID SANDOVAL |
| Smoke Detectors | 9/23/2021 | Approved | DAVID SANDOVAL |
| Final | 10/20/2021 | Not Ready for Inspection | DAVID SANDOVAL |
| Green Building Final | 10/20/2021 | Approved | DAVID SANDOVAL |
| SGSOV-Seismic Gas S/O Valve | 10/20/2021 | SGSOV Not Ready | DAVID SANDOVAL |
| Final | 11/2/2021 | No Access for Inspection | DAVID SANDOVAL |
| SGSOV-Seismic Gas S/O Valve | 11/2/2021 | SGSOV Not Ready | DAVID SANDOVAL |
| Final | 11/9/2021 | Corrections Issued | VINCENT HANLEY |
| SGSOV-Seismic Gas S/O Valve | 11/9/2021 | SGSOV Approved | VINCENT HANLEY |