8244 N BRIMFIELD AVE 91402
Certificate Information: 8244 N BRIMFIELD AVE 91402
- Application / Permit
- 20016-20000-24844
- Plan Check / Job No.
- B20VN12921
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT THE (E) DETACHED GARAGE INTO A (N) ACCESSORY DWELLING UNIT PER GCS 65852.2 (e) (1) (A).
- Permit Issued
- Issued on 1/12/2023
- Issuing Office
- Metro
- Current Status
- CofO Issued on 8/14/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/1/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 10/7/2020 | SELLA BENYAMIN |
| Corrections Issued | 10/8/2020 | SELLA BENYAMIN |
| Applicant returned to address corrections | 12/31/2020 | JEROME MAGAT PALMA |
| Applicant returned to address corrections | 3/4/2021 | MOHAMMAD ESMAILI |
| Building Plans Picked Up | 3/8/2021 | APPLICANT |
| Applicant returned to address corrections | 12/5/2022 | ALEC MOUSAKHANIAN |
| Applicant returned to address corrections | 12/23/2022 | MOHAMMAD ESMAILI |
| Applicant returned to address corrections | 1/10/2023 | DANIEL SMILEY |
| Plan Check Approved | 1/12/2023 | WEIJIAN HUANG |
| Issued | 1/12/2023 | APPLICANT |
| CofO in Progress | 7/11/2024 | VINCENT HANLEY |
| Permit Finaled | 8/14/2024 | DANIEL ORRANTE |
| CofO Issued | 8/14/2024 | DANIEL ORRANTE |
| Permit Finaled | 8/14/2024 | DANIEL ORRANTE |
Permit Application Clearance Information
| Address approval | Cleared | 2/4/2021 | GABRIEL ROBLES |
| Sewer availability | Cleared | 2/4/2021 | GABRIEL ROBLES |
| Eng Process Fee Ord 176,300 | Cleared | 8/16/2022 | CARLOS AGUILERA |
| Hydrant and Access approval | Cleared | 11/22/2022 | ROBERT DUFF |
| Roof/Waste drainage to street | Cleared | 12/21/2022 | LEE GUILBEAUX |
Contact Information
| Contractor | Treeium Inc; Lic. No.: 617148-B | 5352 LAUREL CANYON BLVD #200 VALLEY VILLAGE, CA 91607 |
Inspector Information
| OGANES TARAKHCHYAN, (818) 374-1162 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 4/10/2023 | Approved | CHRISTOPHER DELLEFIELD |
| Footing/Foundation/Slab | 4/12/2023 | No Access for Inspection | CHRISTOPHER DELLEFIELD |
| Pre-Inspection | 7/24/2023 | Approved | GREGG CUMMINGS |
| Excavation/Setback/Form/Re-Bar | 8/7/2023 | Approved | GREGG CUMMINGS |
| Floor/Roof Diaphrgm/Shear Wall | 8/7/2023 | Corrections Issued | GREGG CUMMINGS |
| Footing/Foundation/Slab | 8/7/2023 | Approved | GREGG CUMMINGS |
| Floor/Roof Diaphrgm/Shear Wall | 8/17/2023 | Partial Approval | GREGG CUMMINGS |
| Underground Mechanical | 8/17/2023 | Corrections Issued | GREGG CUMMINGS |
| BUILDING-Rough-Frame | 9/19/2023 | Not Ready for Inspection | GREGG CUMMINGS |
| Green Building Rough | 9/19/2023 | Not Ready for Inspection | GREGG CUMMINGS |
| Floor/Roof Diaphrgm/Shear Wall | 10/10/2023 | Partial Approval | DAVID MATSON |
| Pre-Inspection | 10/24/2023 | Corrections Issued | CHRISTOPHER ROJAS |
| Pre-Inspection | 11/29/2023 | Partial Approval | GREGG CUMMINGS |
| ELECTRICAL-Final | 12/19/2023 | Corrections Issued | CHRISTOPHER ROJAS |
| Gas Test | 12/19/2023 | Approved | CHRISTOPHER ROJAS |
| HVAC-Final | 12/19/2023 | Corrections Issued | CHRISTOPHER ROJAS |
| PLUMBING-Final | 12/19/2023 | Corrections Issued | CHRISTOPHER ROJAS |
| Wood Frame | 12/19/2023 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| ELECTRICAL-Final | 1/23/2024 | No Access for Inspection | CHRISTOPHER ROJAS |
| Gas Test | 1/23/2024 | No Access for Inspection | CHRISTOPHER ROJAS |
| Grounding or Bonding | 1/23/2024 | No Access for Inspection | CHRISTOPHER ROJAS |
| PLUMBING-Final | 1/23/2024 | No Access for Inspection | CHRISTOPHER ROJAS |
| Shower Pan | 1/23/2024 | No Access for Inspection | CHRISTOPHER ROJAS |
| Smoke Detectors | 1/23/2024 | No Access for Inspection | CHRISTOPHER ROJAS |
| BUILDING-Rough-Frame | 1/25/2024 | Partial Approval | CHRISTOPHER ROJAS |
| ELECTRICAL-Rough | 1/25/2024 | Approved | CHRISTOPHER ROJAS |
| Green Building Rough | 1/25/2024 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| Grounding or Bonding | 1/25/2024 | Partial Approval | CHRISTOPHER ROJAS |
| HVAC-Rough | 1/25/2024 | Approved | CHRISTOPHER ROJAS |
| PLUMBING-Rough | 1/25/2024 | Approved | CHRISTOPHER ROJAS |
| Shower Pan | 1/25/2024 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| Insulation | 2/21/2024 | Approved | CRAIG DAVIS |
| Interior/Exterior Lathing | 2/21/2024 | Partial Approval | CRAIG DAVIS |
| Drywall Nailing | 3/26/2024 | Approved | KIRK SANDERS |
| Interior/Exterior Lathing | 3/26/2024 | Corrections Issued | KIRK SANDERS |
| Shower Pan | 3/26/2024 | Approved | KIRK SANDERS |
| Interior/Exterior Lathing | 4/3/2024 | Approved | DAVID ANDERSON |
| Shower Pan | 4/3/2024 | Approved | DAVID ANDERSON |
| BUILDING-Rough-Frame | 6/11/2024 | Approved | VINCENT HANLEY |
| Final | 6/11/2024 | Corrections Issued | VINCENT HANLEY |
| Green Building Final | 6/11/2024 | Approved | VINCENT HANLEY |
| Green Building Rough | 6/11/2024 | Approved | VINCENT HANLEY |
| SGSOV-Seismic Gas S/O Valve | 6/11/2024 | SGSOV Not Ready | VINCENT HANLEY |
| Smoke Detectors | 6/11/2024 | Approved | VINCENT HANLEY |
| ELECTRICAL-Final | 7/10/2024 | Approved | VINCENT HANLEY |
| Final | 7/10/2024 | OK to Issue CofO | VINCENT HANLEY |
| HVAC-Final | 7/10/2024 | Approved | VINCENT HANLEY |
| PLUMBING-Final | 7/10/2024 | Approved | VINCENT HANLEY |
| SGSOV-Seismic Gas S/O Valve | 7/10/2024 | SGSOV Approved | VINCENT HANLEY |