849 W 43RD ST 90037
Certificate Information: 849 W 43RD ST 90037
- Application / Permit
- 20016-20000-24604
- Plan Check / Job No.
- B20VN12290
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) DETACHED GARAGE TO ACCESSORY DWELLING UNIT (296 SQ FT) PER LAMC 12.22 A. 33(c) and (d)
- Permit Issued
- Issued on 8/3/2021
- Issuing Office
- Current Status
- CofO Issued on 12/7/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/17/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 9/29/2020 | JEROME MAGAT PALMA |
| Corrections Issued | 9/29/2020 | JEROME MAGAT PALMA |
| Plan Check Approved | 3/19/2021 | JEROME MAGAT PALMA |
| Building Plans Picked Up | 3/24/2021 | APPLICANT |
| Issued | 8/3/2021 | APPLICANT |
| CofO in Progress | 11/17/2022 | SABAS ALONSO |
| Permit Finaled | 12/7/2022 | DEROLD HAUFF |
| CofO Issued | 12/7/2022 | DEROLD HAUFF |
| Permit Finaled | 12/7/2022 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 12/7/2020 | THOMAS LANG |
| Eng Process Fee Ord 176,300 | Cleared | 12/9/2020 | THOMAS LANG |
| Sewer availability | Cleared | 3/11/2021 | JEANIE LAM |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Morales,, Cesar Del Valle; Lic. No.: C76612 | 11735 THORSON AVE LYNWOOD, CA 90262 |
Inspector Information
| SABAS ALONSO, (213) 202-3468 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 7/5/2022 | Partial Approval | SABAS ALONSO |
| ELECTRICAL-Rough | 7/19/2022 | Not Ready for Inspection | SABAS ALONSO |
| Footing/Foundation/Slab | 7/19/2022 | Partial Approval | SABAS ALONSO |
| Underground Mechanical | 7/19/2022 | Approved | SABAS ALONSO |
| ELECTRICAL-Rough | 8/8/2022 | Not Ready for Inspection | SABAS ALONSO |
| Footing/Foundation/Slab | 8/8/2022 | Not Ready for Inspection | SABAS ALONSO |
| Underground Mechanical | 8/8/2022 | Partial Approval | SABAS ALONSO |
| Footing/Foundation/Slab | 8/11/2022 | Approved | SABAS ALONSO |
| ELECTRICAL-Rough | 9/8/2022 | Approved | HORACE FULTZ |
| PLUMBING-Rough | 9/8/2022 | Approved | HORACE FULTZ |
| Floor/Roof Diaphrgm/Shear Wall | 9/12/2022 | No Access for Inspection | SABAS ALONSO |
| Insulation | 9/12/2022 | Not Ready for Inspection | SABAS ALONSO |
| BUILDING-Rough-Frame | 9/15/2022 | Approved | SABAS ALONSO |
| Floor/Roof Diaphrgm/Shear Wall | 9/15/2022 | Approved | SABAS ALONSO |
| Green Building Rough | 9/15/2022 | Approved | SABAS ALONSO |
| HVAC-Rough | 9/15/2022 | Approved | SABAS ALONSO |
| Insulation | 9/19/2022 | Approved | SABAS ALONSO |
| Interior/Exterior Lathing | 9/19/2022 | Partial Approval | SABAS ALONSO |
| Drywall Nailing | 9/22/2022 | Approved | SABAS ALONSO |
| ELECTRICAL-Final | 10/14/2022 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Green Building Final | 10/14/2022 | Corrections Issued | ALEJANDRO DE ARTOLA |
| HVAC-Final | 10/14/2022 | Corrections Issued | ALEJANDRO DE ARTOLA |
| PLUMBING-Final | 10/14/2022 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Green Building Rough | 10/20/2022 | Approved | SABAS ALONSO |
| Underground Mechanical | 10/20/2022 | Approved | SABAS ALONSO |
| Wood Frame | 10/20/2022 | Approved | SABAS ALONSO |
| Drywall Nailing | 10/25/2022 | Approved | SABAS ALONSO |
| ELECTRICAL-Final | 11/3/2022 | Approved | SABAS ALONSO |
| HVAC-Final | 11/3/2022 | Approved | SABAS ALONSO |
| PLUMBING-Final | 11/3/2022 | Approved | SABAS ALONSO |
| Final | 11/8/2022 | Corrections Issued | SABAS ALONSO |
| Green Building Final | 11/8/2022 | Approved | SABAS ALONSO |
| SGSOV-Seismic Gas S/O Valve | 11/8/2022 | SGSOV Not Ready | SABAS ALONSO |
| Smoke Detectors | 11/8/2022 | Approved | SABAS ALONSO |
| Final | 11/16/2022 | OK to Issue CofO | SABAS ALONSO |
| SGSOV-Seismic Gas S/O Valve | 11/16/2022 | SGSOV Approved | SABAS ALONSO |