849 W 43RD ST 90037

Certificate Information: 849 W 43RD ST 90037

Application / Permit
20016-20000-24604
Plan Check / Job No.
B20VN12290
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) DETACHED GARAGE TO ACCESSORY DWELLING UNIT (296 SQ FT) PER LAMC 12.22 A. 33(c) and (d)
Permit Issued
Issued on 8/3/2021
Issuing Office
Current Status
CofO Issued on 12/7/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/17/2020 APPLICANT
Assigned to Plan Check Engineer 9/29/2020 JEROME MAGAT PALMA
Corrections Issued 9/29/2020 JEROME MAGAT PALMA
Plan Check Approved 3/19/2021 JEROME MAGAT PALMA
Building Plans Picked Up 3/24/2021 APPLICANT
Issued 8/3/2021 APPLICANT
CofO in Progress 11/17/2022 SABAS ALONSO
Permit Finaled 12/7/2022 DEROLD HAUFF
CofO Issued 12/7/2022 DEROLD HAUFF
Permit Finaled 12/7/2022 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 12/7/2020 THOMAS LANG
Eng Process Fee Ord 176,300 Cleared 12/9/2020 THOMAS LANG
Sewer availability Cleared 3/11/2021 JEANIE LAM

Contact Information

Contractor Owner-Builder       ,
Engineer Morales,, Cesar Del Valle; Lic. No.: C76612 11735 THORSON AVE      LYNWOOD, CA 90262

Inspector Information

SABAS ALONSO, (213) 202-3468 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 7/5/2022 Partial Approval SABAS ALONSO
ELECTRICAL-Rough 7/19/2022 Not Ready for Inspection SABAS ALONSO
Footing/Foundation/Slab 7/19/2022 Partial Approval SABAS ALONSO
Underground Mechanical 7/19/2022 Approved SABAS ALONSO
ELECTRICAL-Rough 8/8/2022 Not Ready for Inspection SABAS ALONSO
Footing/Foundation/Slab 8/8/2022 Not Ready for Inspection SABAS ALONSO
Underground Mechanical 8/8/2022 Partial Approval SABAS ALONSO
Footing/Foundation/Slab 8/11/2022 Approved SABAS ALONSO
ELECTRICAL-Rough 9/8/2022 Approved HORACE FULTZ
PLUMBING-Rough 9/8/2022 Approved HORACE FULTZ
Floor/Roof Diaphrgm/Shear Wall 9/12/2022 No Access for Inspection SABAS ALONSO
Insulation 9/12/2022 Not Ready for Inspection SABAS ALONSO
BUILDING-Rough-Frame 9/15/2022 Approved SABAS ALONSO
Floor/Roof Diaphrgm/Shear Wall 9/15/2022 Approved SABAS ALONSO
Green Building Rough 9/15/2022 Approved SABAS ALONSO
HVAC-Rough 9/15/2022 Approved SABAS ALONSO
Insulation 9/19/2022 Approved SABAS ALONSO
Interior/Exterior Lathing 9/19/2022 Partial Approval SABAS ALONSO
Drywall Nailing 9/22/2022 Approved SABAS ALONSO
ELECTRICAL-Final 10/14/2022 Corrections Issued ALEJANDRO DE ARTOLA
Green Building Final 10/14/2022 Corrections Issued ALEJANDRO DE ARTOLA
HVAC-Final 10/14/2022 Corrections Issued ALEJANDRO DE ARTOLA
PLUMBING-Final 10/14/2022 Corrections Issued ALEJANDRO DE ARTOLA
Green Building Rough 10/20/2022 Approved SABAS ALONSO
Underground Mechanical 10/20/2022 Approved SABAS ALONSO
Wood Frame 10/20/2022 Approved SABAS ALONSO
Drywall Nailing 10/25/2022 Approved SABAS ALONSO
ELECTRICAL-Final 11/3/2022 Approved SABAS ALONSO
HVAC-Final 11/3/2022 Approved SABAS ALONSO
PLUMBING-Final 11/3/2022 Approved SABAS ALONSO
Final 11/8/2022 Corrections Issued SABAS ALONSO
Green Building Final 11/8/2022 Approved SABAS ALONSO
SGSOV-Seismic Gas S/O Valve 11/8/2022 SGSOV Not Ready SABAS ALONSO
Smoke Detectors 11/8/2022 Approved SABAS ALONSO
Final 11/16/2022 OK to Issue CofO SABAS ALONSO
SGSOV-Seismic Gas S/O Valve 11/16/2022 SGSOV Approved SABAS ALONSO