20451-20453 W GAULT ST 91306

Certificate Information: 20451-20453 W GAULT ST 91306

Application / Permit
20016-20000-24179
Plan Check / Job No.
B20VN12647
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
CONVERT (E) ATTACHED GARAGE INTO A (N) ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(A)
Permit Issued
Issued on 10/28/2020
Issuing Office
Current Status
CofO Issued on 12/6/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/25/2020 APPLICANT
Assigned to Plan Check Engineer 10/1/2020 ARTIN ZARUKIAN
Corrections Issued 10/5/2020 ARTIN ZARUKIAN
Plan Check Approved 10/27/2020 ARTIN ZARUKIAN
Issued 10/28/2020 APPLICANT
CofO in Progress 12/2/2021 STEVEN BACK
Permit Finaled 12/6/2021 JOHN JANSON
CofO Issued 12/6/2021 JOHN JANSON
Permit Finaled 12/6/2021 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 10/19/2020 JOHN TRIANTAFYLLOS
Sewer availability Cleared 10/19/2020 JOHN TRIANTAFYLLOS
Eng Process Fee Ord 176,300 Cleared 10/20/2020 JOHN TRIANTAFYLLOS

Contact Information

Contractor Evergreen Construction Group Inc; Lic. No.: 998238-B 6444 BELLINGHAM AVE #204      NORTH HOLLYWOOD, CA 91606
Engineer Espino,, Manuel A; Lic. No.: C55526 12109 WOODRUFF AVE      DOWNEY, CA 90241

Inspector Information

ALEXANDER HANDY, (818) 774-4317 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 1/4/2021 Corrections Issued HENRY KIM
Footing/Foundation/Slab 1/14/2021 Approved HENRY KIM
PLUMBING-Rough 1/21/2021 Partial Approval HENRY KIM
Sewer 1/21/2021 Approved HENRY KIM
ELECTRICAL-Rough 2/2/2021 Corrections Issued HENRY KIM
PLUMBING-Rough 2/2/2021 Corrections Issued HENRY KIM
ELECTRICAL-Rough 2/4/2021 Approved HENRY KIM
PLUMBING-Rough 2/4/2021 Corrections Issued HENRY KIM
PLUMBING-Rough 2/12/2021 Approved HENRY KIM
BUILDING-Rough-Frame 2/24/2021 Approved HENRY KIM
Floor/Roof Diaphrgm/Shear Wall 2/24/2021 Approved HENRY KIM
Green Building Rough 2/24/2021 Approved HENRY KIM
Insulation 2/24/2021 Approved HENRY KIM
Shower Pan 2/24/2021 Approved HENRY KIM
Shower Pan 2/26/2021 Approved CHRISTOPHER DELLEFIELD
Interior/Exterior Lathing 3/12/2021 Approved HENRY KIM
Drywall Nailing 3/18/2021 Approved HENRY KIM
Smoke Detectors 3/18/2021 Corrections Issued HENRY KIM
Interior/Exterior Lathing 5/7/2021 Not Ready for Inspection STEPHANIE SWANSON
Final 5/14/2021 Not Ready for Inspection HENRY KIM
Green Building Final 5/14/2021 Partial Approval HENRY KIM
Interior/Exterior Lathing 5/14/2021 Approved HENRY KIM
SGSOV-Seismic Gas S/O Valve 5/14/2021 SGSOV Not Ready HENRY KIM
Smoke Detectors 5/14/2021 Not Ready for Inspection HENRY KIM
ELECTRICAL-Rough 6/9/2021 Not Ready for Inspection HENRY KIM
PLUMBING-Rough 6/9/2021 Not Ready for Inspection HENRY KIM
ELECTRICAL-Final 10/28/2021 Corrections Issued HENRY KIM
Final 10/28/2021 Corrections Issued HENRY KIM
Gas Test 10/28/2021 Corrections Issued HENRY KIM
Green Building Final 10/28/2021 Corrections Issued HENRY KIM
HVAC-Final 10/28/2021 Approved HENRY KIM
PLUMBING-Final 10/28/2021 Corrections Issued HENRY KIM
SGSOV-Seismic Gas S/O Valve 10/28/2021 SGSOV Not Ready HENRY KIM
Smoke Detectors 10/28/2021 Approved HENRY KIM
Final 11/8/2021 Not Ready for Inspection STEVEN BACK
Green Building Final 11/8/2021 Corrections Issued STEVEN BACK
SGSOV-Seismic Gas S/O Valve 11/8/2021 SGSOV Approved STEVEN BACK
Final 12/2/2021 OK to Issue CofO STEVEN BACK
Green Building Final 12/2/2021 Approved STEVEN BACK
PLUMBING-Final 12/2/2021 Approved STEVEN BACK