10744 N PETIT AVE 91344
Certificate Information: 10744 N PETIT AVE 91344
- Application / Permit
- 20016-20000-24095
- Plan Check / Job No.
- B20VN12608
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) DETACHED GARAGE TO ACCESSORY DWELLING UNIT (360 SQ FT)
- Permit Issued
- Issued on 10/23/2020
- Issuing Office
- Current Status
- CofO Issued on 10/18/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/24/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 10/1/2020 | JEROME MAGAT PALMA |
| Corrections Issued | 10/4/2020 | JEROME MAGAT PALMA |
| Plan Check Approved | 10/22/2020 | JEROME MAGAT PALMA |
| Issued | 10/23/2020 | APPLICANT |
| CofO in Progress | 9/13/2021 | MARK JOHNSON |
| Permit Finaled | 10/18/2021 | MICHAEL SMITH |
| CofO Issued | 10/18/2021 | MICHAEL SMITH |
| Permit Finaled | 10/18/2021 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 10/7/2020 | JOHN TRIANTAFYLLOS |
| Sewer availability | Cleared | 10/7/2020 | JOHN TRIANTAFYLLOS |
| Eng Process Fee Ord 176,300 | Cleared | 10/8/2020 | JOHN TRIANTAFYLLOS |
| Construction near power lines | Cleared | 10/12/2020 | WALTER RAMIREZ |
Contact Information
| Contractor | Daniels Development Group Inc; Lic. No.: 1026444-B | 6952 SYLVIA AVENUE RESEDA, CA 91335 |
Inspector Information
| CHRISTOPHER ROJAS, (818) 374-1160 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 1/14/2021 | Not Ready for Inspection | MARK JOHNSON |
| PLUMBING-Rough | 1/22/2021 | Corrections Issued | MARK JOHNSON |
| PLUMBING-Rough | 1/28/2021 | Partial Approval | MARK JOHNSON |
| Footing/Foundation/Slab | 2/4/2021 | Approved | MARK JOHNSON |
| BUILDING-Rough-Frame | 2/18/2021 | Not Ready for Inspection | MARK JOHNSON |
| ELECTRICAL-Rough | 2/26/2021 | Approved | MARK JOHNSON |
| HVAC-Rough | 2/26/2021 | Approved | MARK JOHNSON |
| PLUMBING-Rough | 2/26/2021 | Approved | MARK JOHNSON |
| BUILDING-Rough-Frame | 3/5/2021 | Approved | MARK JOHNSON |
| Interior/Exterior Lathing | 3/5/2021 | Partial Approval | MARK JOHNSON |
| Insulation | 3/10/2021 | Partial Approval | MARK JOHNSON |
| Floor/Roof Diaphrgm/Shear Wall | 3/16/2021 | Corrections Issued | MARK JOHNSON |
| Floor/Roof Diaphrgm/Shear Wall | 3/19/2021 | Not Ready for Inspection | MARK JOHNSON |
| Floor/Roof Diaphrgm/Shear Wall | 3/23/2021 | Partial Approval | MARK JOHNSON |
| Insulation | 3/23/2021 | Approved | MARK JOHNSON |
| Drywall Nailing | 4/1/2021 | Approved | MARK JOHNSON |
| Sewer | 5/28/2021 | Not Ready for Inspection | MARK JOHNSON |
| PLUMBING-Rough | 6/11/2021 | Corrections Issued | MARK JOHNSON |
| PLUMBING-Rough | 6/17/2021 | Not Ready for Inspection | MICHAEL PELHAM |
| Sewer | 6/22/2021 | Approved | MARK JOHNSON |
| SGSOV-Seismic Gas S/O Valve | 6/25/2021 | SGSOV Not Ready | MICHAEL TEMPLE |
| Final | 6/28/2021 | Corrections Issued | MARK JOHNSON |
| Drywall Nailing | 7/2/2021 | Approved | MORRIS JACKSON |
| Final | 7/7/2021 | Not Ready for Inspection | MARK JOHNSON |
| Green Building Final | 7/7/2021 | Approved | MARK JOHNSON |
| SGSOV-Seismic Gas S/O Valve | 7/7/2021 | SGSOV Not Ready | MARK JOHNSON |
| Smoke Detectors | 7/7/2021 | Approved | MARK JOHNSON |
| ELECTRICAL-Rough | 9/7/2021 | Not Ready for Inspection | MARK JOHNSON |
| Final | 9/10/2021 | OK to Issue CofO | MARK JOHNSON |
| SGSOV-Seismic Gas S/O Valve | 9/10/2021 | SGSOV Approved | MARK JOHNSON |